UDRP/AF/BR/39
Agreement signed
|
Project: |
UDRP-AF(Bridge And Slope) |
Package No.: |
616 |
Package Name: |
UDRP/AF/BR/39 |
Sanction Cost: |
507.75 lakhs |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4055 Bridge on Kapkot Pindari Glacier MR KM-13 (24.000 M.) (in prorgress) |
|
Procurement: |
Package No.: 616
Package Name: UDRP/AF/BR/39
Tender Date: 02-09-2019
Current Status: Agreement signed
Achieved on Date: 20-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/39
Contractor Name: M/S.Dalip Singh Adhikari
|
Start Date: 27-01-2020
Intended Completion Date: 16-08-2021
Original End Date: 26-04-2021
|
Total Bond Cost: 39760202.23 (397.6 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 8946000 for 450 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 3.32 | 1.00 Job | 0.30 Job | 0.28 | 1.00 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 1.20 | 1.00 Job | 0.30 Job | 0.1 | 0.36 | 3. | Foundation RHS | 1.00 Job | 16.57 | 1.00 Job | 1.00 Job | 4.72 | 16.57 | 4. | Foundation LHS | 1.00 Job | 16.57 | 1.00 Job | 1.00 Job | 4.72 | 16.57 | 5. | Fixing of chequered Plate/RCC Deck | 49.10 sqm | 15.86 | 49.10 sqm | 0.00 sqm | 0 | 0.00 | 6. | Steel Railing/crush barrier | 48.00 m | 2.61 | 48.00 m | 0.00 m | 0 | 0.00 | 7. | Approach Ramp /path | 200.00 m | 23.54 | 200.00 m | 0.00 m | 0 | 0.00 | 8. | Protection Work | 1.00 Job | 111.95 | 1.00 Job | 0.40 Job | 12.74 | 44.78 | 9. | Errection Work | 1.00 Job | 31.06 | 1.00 Job | 0.00 Job | 0 | 0.00 | 10. | Fabrication Work | 1.00 job | 32.79 | 1.00 job | 0.00 job | 0 | 0.00 | 11. | Abutment Substructure RHS | 1.00 Job | 47.98 | 1.00 Job | 1.00 Job | 13.65 | 47.98 | 12. | Abutment Substructure LHS | 1.00 Job | 47.98 | 1.00 Job | 1.00 Job | 13.65 | 47.98 |
Total Amount: |
351.43 |
|
49.86 |
175.24 |
|
Remarks:
No Remarks
Work Program Made On:
06-06-2020
Updation of work program on:
19-10-2020
|
|
Work Program Status:Work Programme workable. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2020 | 92.38 lakhs |
2. | 23-December-2020 | 39.66 lakhs |
Total |
132.04 lakhs |
% Payment |
33.21 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Bridge on Kapkot Pindari Glacier MR KM-13(4055) | water sprinkling, Query |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 31 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-02-2021 | Km 13 of pindari glacir motor raod | R.H.S. approach road work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
2. | 22-02-2021 | Km 13 of pindari glacier motor road | R.H.S. abutment | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
3. | 22-02-2021 | Km 13 of pindari glacier motor raod | L. H. S abutment | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
4. | 03-02-2021 | Abutment A1, BR-39, KM-13, kapkot Pindari-Glecier Road Bageshwar | Abutment A1 first lift shuttering work in progress. | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
5. | 11-01-2021 | Km 13 of pindari glacier motor road | Survey work for RHS approach road | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
6. | 11-01-2021 | Km 13 of kapkot pindari glacier motor road | Exen. Sir visited site | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
7. | 04-12-2020 | Km -13 of kapkot pindari glacier road | Work completed upto aputment cap | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
8. | 08-08-2020 | Kapkot Pindari Glacier(BR-39), KM-13 | A1(RHS) foundation Excavation Work | Sumit Bisht(SS) | unknown | unknown | See Pic |
9. | 30-07-2020 | Km 13 of pindari glacier motor road | LHS abutment 1st lift reinforcement & gabion work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
10. | 27-07-2020 | Kapkot Pindari Glacier(BR-39) | Gabion wall(Protection work) LHS Abutment Side | Sumit Bisht(SS) | unknown | unknown | See Pic |
11. | 26-06-2020 | At Km 13 of pindari glacier road kapkot dist. Bageshwar | L. H. S. Side abutment raft reinforcement work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
12. | 20-06-2020 | Span 24-M,steel girder bridge Kapkot Pindari-Glecier KM-13,BR-39. | Site inspection of BR-39 by DTL Sri RM Sharma (DSC-1) | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
13. | 20-06-2020 | Span -24M street girder bridge of Kapkot Pindari Glacier | LHS ABUTMENT foundation level checking. | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
14. | 20-06-2020 | Span -24M, Motor-Road steel girder bridge, Pindari Gliciar ,KM-13 spa | Level Checking for foundation of LHS abutment. | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
15. | 20-06-2020 | Kapkot Pindari Glacier site BR-39 | Reinforcement work in progress BR-39, | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
16. | 20-06-2020 | Kapkot Pindari-Glecier, KM-13 | Kapkot Pindari -GLECIERKM-13, reinforcement work in progress. | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
17. | 10-06-2020 | Kapkot pindari mr km 13, 24 mtr span bridge | Project site | Jagdish Narayan Meena | AE | UDRP R&B Bageshwar | See Pic |
18. | 10-06-2020 | Kapkot pindari mr km 13, 24 mtr span bridge | Staff room | Jagdish Narayan Meena | AE | UDRP R&B Bageshwar | See Pic |
19. | 10-06-2020 | Kapkot pindari mr km 13, 24 mtr span bridge | Toilet facilities | Jagdish Narayan Meena | AE | UDRP R&B Bageshwar | See Pic |
20. | 10-06-2020 | Kapkot pindari mr km 13, 24 mtr span bridge | Drinking water facilities | Jagdish Narayan Meena | AE | UDRP R&B Bageshwar | See Pic |
|
|