Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/39 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 616 Package Name: UDRP/AF/BR/39 Sanction Cost: 507.75  lakhs
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4055   Bridge on Kapkot Pindari Glacier MR KM-13 (24.000 M.) (completed)
Procurement:
Package No.: 616        Package Name: UDRP/AF/BR/39        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 20-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/39        Contractor Name: M/S.Dalip Singh Adhikari       
Start Date: 27-01-2020        Intended Completion Date: 09-12-2021        Original End Date:  26-04-2021
Total Bond Cost: 39760202.23 (397.6 lakhs)        Variation Cost: -12387.58 (-0.12 lakhs)     Hence Total Bond Cost is   39747814.65 (397.48 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10337600 for 520 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job3.721.00 Job1.00 Job0.973.72
2.Other Allied Works & Finishing Work 1.00 Job1.941.00 Job1.00 Job0.51.94
3.Foundation RHS1.00 Job27.331.00 Job1.00 Job7.0916.57
4.Foundation LHS1.00 Job27.331.00 Job1.00 Job7.0916.57
5.Abutment Superstructure RHS1.00 Job0.831.00 Job1.00 Job0.220.83
6.Abutment Superstructure LHS1.00 Job0.831.00 Job1.00 Job0.220.83
7.Fixing of chequered Plate/RCC Deck49.10 sqm17.3449.10 sqm49.10 sqm4.517.34
8.Steel Railing/crush barrier48.00 m2.9348.00 m48.00 m0.762.93
9.Approach Ramp /path 200.00 m73.58200.00 m200.00 m19.0873.58
10.Protection Work1.00 Job82.571.00 Job1.00 Job21.4182.57
11.Errection Work1.00 Job29.241.00 Job1.00 Job7.5829.24
12.Fabrication Work1.00 job41.961.00 job1.00 job10.8832.79
13.Abutment Substructure RHS1.00 Job38.041.00 Job1.00 Job9.8647.98
14.Abutment Substructure LHS1.00 Job38.041.00 Job1.00 Job9.8647.98
Total Amount: 385.68 100   374.87
Remarks: No Remarks       Work Program Made On: 06-06-2020       Updation of work program on: 31-12-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-202092.38  lakhs
2.23-December-202039.66  lakhs
3.29-May-202150.04  lakhs
4.28-January-2022162.67  lakhs
5.31-May-202252.73  lakhs
Total 397.48  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 409     No. of Test Done : 409      No. of Test Passed : 409      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 76
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Final view Motor-Road bridge Pindari-Glecier KM-13 BR-39 BageshwarAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
2.19-01-2022Kapkot Pindari-Glecier KM-13 BAGESHWARApproch road RHS locationAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
3.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Approach road LHS locationAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
4.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Final view of motor Road bridgeAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
5.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Protection work LHS locationAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
6.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Side view of bridge U/SAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
7.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39RR wall Approach road RHS U/S locationAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
8.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Approach road RR wall RHS D/SAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
9.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Side view of bridge D/SAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
10.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Deck slab bottom view of Abutment LHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
11.19-01-2022Kapkot Pindari-Glecier KM-13 BR-39Deck slab bottom view of Abutment RHSAnurag SinghR.E. UDRP-AF SB DSC Bageshwar See Pic
12.03-01-2022Kapkot pindari glacier km-13 BR-39 district BageshwarKapkot pindari glacier km-13 BR-39 district BageshwarAbhay Singh negiunknownunknown See Pic
13.23-11-2021Kapkot pindari glacier km-13 Br-39 district- BageshwarEarth filling and soil compaction work in a prograss approach road RHS side kapkot pindari glacier km-13 Br-39Abhay Singh negiunknownunknown See Pic
14.21-11-2021Kapkot pindari glacier km-13 Br-39 district- BageshwarApproach Road Earth filling work in a prograss kapkot pindari glacier km-13 Br-39Abhay Singh negiunknownunknown See Pic
15.13-11-2021Kapkot pindari glacier km-13 Br-39 district- BageshwarRcc cast in situ crash barrier work completed kapkot pindari glacier km-13 Br-39 district- BageshwarAbhay Singh negiunknownunknown See Pic
16.31-10-2021Kapkot pindari glacier motor road BR 39R.h.s side approach slab concreting work is in progressSarvesh chandra nautiyal ` ` See Pic
17.16-10-2021Kapkot pindari glacier km-13 Br-39 district- BageshwarCuring of deck slab kapkot pindari glacier km-13 Br-39 district- BageshwarAbhay Singh negiunknownunknown See Pic
18.09-10-202124mtr span steel girder bridge Pindari glacier road km.13Deck slab shuttering work in progressMukesh Kumar ` ` See Pic
19.04-10-2021Kapkot pindari glacier km-13 Br-39 District- Bageshwarchecking of Reinforcement deck slab with AE sir and RE sir kapkot pindari glacier km-13 Br-39 district- BageshwarAbhay Singh negiunknownunknown See Pic
20.04-10-2021Km 13 of kapkot pindari glacier motor roadDeck slab reinforcement work is in progressRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic