UDRP/AF/BR/39
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
616 |
Package Name: |
UDRP/AF/BR/39 |
Sanction Cost: |
507.75 lakhs |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4055 Bridge on Kapkot Pindari Glacier MR KM-13 (24.000 M.) (completed) |
|
Procurement: |
Package No.: 616
Package Name: UDRP/AF/BR/39
Tender Date: 02-09-2019
Current Status: Agreement signed
Achieved on Date: 20-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/39
Contractor Name: M/S.Dalip Singh Adhikari
|
Start Date: 27-01-2020
Intended Completion Date: 09-12-2021
Original End Date: 26-04-2021
|
Total Bond Cost: 39760202.23 (397.6 lakhs)
Variation Cost: -12387.58 (-0.12 lakhs) Hence Total Bond Cost is 39747814.65 (397.48 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 10337600 for 520 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 3.72 | 1.00 Job | 1.00 Job | 0.97 | 3.72 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 1.94 | 1.00 Job | 1.00 Job | 0.5 | 1.94 | 3. | Foundation RHS | 1.00 Job | 27.33 | 1.00 Job | 1.00 Job | 7.09 | 16.57 | 4. | Foundation LHS | 1.00 Job | 27.33 | 1.00 Job | 1.00 Job | 7.09 | 16.57 | 5. | Abutment Superstructure RHS | 1.00 Job | 0.83 | 1.00 Job | 1.00 Job | 0.22 | 0.83 | 6. | Abutment Superstructure LHS | 1.00 Job | 0.83 | 1.00 Job | 1.00 Job | 0.22 | 0.83 | 7. | Fixing of chequered Plate/RCC Deck | 49.10 sqm | 17.34 | 49.10 sqm | 49.10 sqm | 4.5 | 17.34 | 8. | Steel Railing/crush barrier | 48.00 m | 2.93 | 48.00 m | 48.00 m | 0.76 | 2.93 | 9. | Approach Ramp /path | 200.00 m | 73.58 | 200.00 m | 200.00 m | 19.08 | 73.58 | 10. | Protection Work | 1.00 Job | 82.57 | 1.00 Job | 1.00 Job | 21.41 | 82.57 | 11. | Errection Work | 1.00 Job | 29.24 | 1.00 Job | 1.00 Job | 7.58 | 29.24 | 12. | Fabrication Work | 1.00 job | 41.96 | 1.00 job | 1.00 job | 10.88 | 32.79 | 13. | Abutment Substructure RHS | 1.00 Job | 38.04 | 1.00 Job | 1.00 Job | 9.86 | 47.98 | 14. | Abutment Substructure LHS | 1.00 Job | 38.04 | 1.00 Job | 1.00 Job | 9.86 | 47.98 |
Total Amount: |
385.68 |
|
100 |
374.87 |
|
Remarks:
No Remarks
Work Program Made On:
06-06-2020
Updation of work program on:
31-12-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2020 | 92.38 lakhs |
2. | 23-December-2020 | 39.66 lakhs |
3. | 29-May-2021 | 50.04 lakhs |
4. | 28-January-2022 | 162.67 lakhs |
5. | 31-May-2022 | 52.73 lakhs |
Total |
397.48 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 76 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Final view Motor-Road bridge Pindari-Glecier KM-13 BR-39 Bageshwar | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
2. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BAGESHWAR | Approch road RHS location | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
3. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Approach road LHS location | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
4. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Final view of motor Road bridge | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
5. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Protection work LHS location | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
6. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Side view of bridge U/S | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
7. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | RR wall Approach road RHS U/S location | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
8. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Approach road RR wall RHS D/S | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
9. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Side view of bridge D/S | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
10. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Deck slab bottom view of Abutment LHS | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
11. | 19-01-2022 | Kapkot Pindari-Glecier KM-13 BR-39 | Deck slab bottom view of Abutment RHS | Anurag Singh | R.E. | UDRP-AF SB DSC Bageshwar | See Pic |
12. | 03-01-2022 | Kapkot pindari glacier km-13 BR-39 district Bageshwar | Kapkot pindari glacier km-13 BR-39 district Bageshwar | Abhay Singh negi | unknown | unknown | See Pic |
13. | 23-11-2021 | Kapkot pindari glacier km-13 Br-39 district- Bageshwar | Earth filling and soil compaction work in a prograss approach road RHS side kapkot pindari glacier km-13 Br-39 | Abhay Singh negi | unknown | unknown | See Pic |
14. | 21-11-2021 | Kapkot pindari glacier km-13 Br-39 district- Bageshwar | Approach Road Earth filling work in a prograss kapkot pindari glacier km-13 Br-39 | Abhay Singh negi | unknown | unknown | See Pic |
15. | 13-11-2021 | Kapkot pindari glacier km-13 Br-39 district- Bageshwar | Rcc cast in situ crash barrier work completed kapkot pindari glacier km-13 Br-39 district- Bageshwar | Abhay Singh negi | unknown | unknown | See Pic |
16. | 31-10-2021 | Kapkot pindari glacier motor road BR 39 | R.h.s side approach slab concreting work is in progress | Sarvesh chandra nautiyal | ` | ` | See Pic |
17. | 16-10-2021 | Kapkot pindari glacier km-13 Br-39 district- Bageshwar | Curing of deck slab kapkot pindari glacier km-13 Br-39 district- Bageshwar | Abhay Singh negi | unknown | unknown | See Pic |
18. | 09-10-2021 | 24mtr span steel girder bridge Pindari glacier road km.13 | Deck slab shuttering work in progress | Mukesh Kumar | ` | ` | See Pic |
19. | 04-10-2021 | Kapkot pindari glacier km-13 Br-39 District- Bageshwar | checking of Reinforcement deck slab with AE sir and RE sir kapkot pindari glacier km-13 Br-39 district- Bageshwar | Abhay Singh negi | unknown | unknown | See Pic |
20. | 04-10-2021 | Km 13 of kapkot pindari glacier motor road | Deck slab reinforcement work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
|
|