Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/38 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 615 Package Name: UDRP/AF/BR/38 Sanction Cost: 219.91  lakhs
District: Dehradun Block: Raipur Constituency: Mussoorie Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4064   Bridge on Chamasari Majhada MR (30.000 M.) (completed)
Procurement:
Package No.: 615        Package Name: UDRP/AF/BR/38        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/38        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 01-02-2020        Intended Completion Date: 23-07-2021        Original End Date:  31-01-2021
Total Bond Cost: 20027608.88 (200.28 lakhs)        Variation Cost: 1046205.57 (10.46 lakhs)     Hence Total Bond Cost is   21073814.45 (210.74 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 3534942 for 353 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job5.181.00 Job1.00 Job2.95.18
2.Foundation RHS1.00 Job5.231.00 Job1.00 Job2.935.23
3.Foundation LHS1.00 Job5.231.00 Job1.00 Job2.935.23
4.Steel Railing/crush barrier62.40 m2.5462.40 m62.40 m1.422.54
5.Approach Ramp /path 100.00 m35.24100.00 m100.00 m19.7135.24
6.Protection Work1.00 Job21.561.00 Job1.00 Job12.0621.56
7.Errection Work1.00 Job16.241.00 Job1.00 Job9.0816.24
8.PCC in Foundation12.58 cum0.6712.58 cum12.58 cum0.380.67
9.Fabrication Work1.00 job44.481.00 job1.00 job24.8844.48
10.Abutment Substructure RHS1.00 Job17.011.00 Job1.00 Job9.5117.01
11.Abutment Substructure LHS1.00 Job17.011.00 Job1.00 Job9.5117.01
12.Fixing Bearing/Slab Casting1.00 job6.861.00 job1.00 job3.846.86
13.Back Wall/ Approach slab1.00 job0.551.00 job1.00 job0.310.55
14.Wearing Coat9.95 Cum0.999.95 Cum9.95 Cum0.560.99
Total Amount: 178.79 100   178.79
Remarks: No Remarks       Work Program Made On: 15-10-2020       Updation of work program on: 12-08-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-202029.02  lakhs
2.14-December-202033.91  lakhs
3.18-December-202025.67  lakhs
4.19-February-202133.18  lakhs
5.03-April-202129.88  lakhs
6.31-May-202117.66  lakhs
7.22-October-202126.34  lakhs
8.31-March-202215.07  lakhs
Total 210.73  lakhs
% Payment 99.99 %
Advance Amount:  17.88  lakhs        Recovered Amount:  17.88  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 330     No. of Test Done : 330      No. of Test Passed : 330      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 83
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-01-2022Km 2Bridge view from approach roadAshish bhatt ` ` See Pic
2.31-01-2022Km 2Completed Chamasari Majhada bridgeAshish bhatt ` ` See Pic
3.31-01-2022Chamasari-Majhara Bridge BR-38Chamasari-Majhara Bridge Down to upstream streamSuresh Prasad ` ` See Pic
4.31-01-2022Chamasari-Majhara Bridge BR-38Chamasari-Majhara Bridge RHS sideSuresh Prasad ` ` See Pic
5.31-01-2022Chamasari-Majhara BridgeChamasari-Majhara Bridge completed open for trafficSuresh Prasad ` ` See Pic
6.31-01-2022Chamasari-Majhara Bridge BR-38Chamasari-Majhara BridgeSuresh Prasad ` ` See Pic
7.31-01-2022Chamasari-Majhara KM-02 BR-38Chamasari-Majhara Bridge Upstream to downstreamSuresh Prasad ` ` See Pic
8.31-01-2022Chamasari-Majhara KM-02 BR-38Chamasari-Majhara LHS sideSURESH PRASAD ` ` See Pic
9.17-09-2021Chamasari Majhada Steel girder Bridge Km 02Torque checking of 20 mm dia BoltAshish Singh ` ` See Pic
10.01-09-2021Chamasari Majhada bridge DehradunSite inspection by CE SirSudhir Kumar ` ` See Pic
11.14-08-2021Chamasari-Majhara KM-02Parapet A1 Side completedSuresh Prasad ` ` See Pic
12.12-08-2021Chamasari-Majhara KM-02Parapet shutteringSuresh Prasad ` ` See Pic
13.11-08-2021Chamasari-Majhara KM-02Protection work of approach road completed.Deepak Rawatunknownunknown See Pic
14.03-08-2021Chamasari-Majhara Bridge KM-02Protection work in progressSuresh Prasad ` ` See Pic
15.02-08-2021Chamasari-Majhara KM-02Protection work in progressSuresh Prasad ` ` See Pic
16.20-07-2021Chamasari-Majhara BR-38Chamasari-Majhara Bridge InspectionSuresh Prasad ` ` See Pic
17.20-07-2021Chamasari-MajharaBridge inspectionSuresh Prasad ` ` See Pic
18.07-07-2021Km 2Compacting approach via RollerAshiah Bhatt, S.S., UDRP-unknownunknown See Pic
19.05-07-20212kmCube testing of crash barrier 28daysWaqil singhunknownunknown See Pic
20.05-07-2021Km 2B/wall work in progressAshiah Bhatt, S.S., UDRP-unknownunknown See Pic