Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/37 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 614 Package Name: UDRP/AF/BR/37 Sanction Cost: 456.41  lakhs
District: Pauri Block: Zahrikhal Constituency: Lansdowne Circle:
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4066   Bridge in KM-3 of Sisaldi Satpuli MR (45.000 M.) (in prorgress)
Procurement:
Package No.: 614        Package Name: UDRP/AF/BR/37        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/37        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 01-02-2020        Intended Completion Date: 29-11-2021        Original End Date:  30-04-2021
Total Bond Cost: 46758700.08 (467.59 lakhs)        Variation Cost: 425490.63 (4.25 lakhs)     Hence Total Bond Cost is   47184190.71 (471.84 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 12998724 for 556 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.11 KM7.830.11 KM0.05 KM0.753.56
2.R/Wall, B/ Wall Type Protection works70.00 m16.9170.00 m35.00 m1.798.46
3.PC/CC i/c Prime Coat, Tack Coat0.15 KM1.290.15 KM0.00 KM00.00
4.longitudinal Drain105.00 m1.23105.00 m0.00 m00.00
5.Crash Barrier94.00 m5.5594.00 m0.00 m00.00
6.Road Furniture4.00 No0.404.00 No4.00 No0.090.40
7.Env. Man & Moni Plan1.00 Job2.861.00 Job0.75 Job0.462.15
8.Other Allied Works & Finishing Work 10.00 Job8.0310.00 Job5.00 Job0.854.02
9.Foundation RHS1.00 Job0.921.00 Job1.00 Job0.20.92
10.Foundation LHS1.00 Job0.921.00 Job1.00 Job0.20.92
11.Abutment Superstructure RHS1.00 Job19.831.00 Job1.00 Job4.219.83
12.Abutment Superstructure LHS1.00 Job8.751.00 Job1.00 Job1.868.75
13.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no23.691.00 no0.00 no00.00
14.Steel Railing/crush barrier0.00 m0.000.00 m0.00 m00.00
15.Approach Ramp /path 105.00 m2.83105.00 m0.00 m00.00
16.Protection Work1.00 Job5.781.00 Job0.50 Job0.612.89
17.Errection Work1.00 Job132.061.00 Job0.60 Job16.7979.24
18.Gabion work150.00 m4.84150.00 m150.00 m1.034.84
19.PCC in Foundation13.62 cum0.9814.30 cum12.25 cum0.180.76
20.Fabrication Work1.00 job219.531.00 job1.00 job46.53219.53
21.Fixing Bearing/Slab Casting6.00 job4.576.00 job0.00 job00.00
22.Wearing Coat9.88 Cum3.039.88 Cum0.00 Cum00.00
Total Amount: 471.83 75.52   356.27
Remarks: Work in progress and EOT sanctioned Upto 20/08/2021       Work Program Made On: 05-12-2020       Updation of work program on: 15-09-2021      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-March-202126.85  lakhs
2.29-July-2021204.41  lakhs
3.31-August-202136.62  lakhs
4.02-November-20219.10  lakhs
Total 276.98  lakhs
% Payment 58.7 %
Advance Amount:  41.75  lakhs        Recovered Amount:  41.75  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 240     No. of Test Done : 242      No. of Test Passed : 240      No. of Test Failed : 2   Test report of this package
Number of Pics Available on Web Repository: 580
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-11-2021Erection workErection work is in progressVineet kumar je ` ` See Pic
2.25-11-2021Erection workErection work checkingVineet kumar je ` ` See Pic
3.24-11-2021Br 37Truss launching work is in progressKrishnan gopalunknownunknown See Pic
4.23-11-2021BR-37Placing of top chord at L6 to L8Deepak Rawat ` ` See Pic
5.23-11-2021BR-37Placing of top chord at L6 to L8Deepak Rawat ` ` See Pic
6.23-11-2021BR-37Placing of vertical member at L8Deepak Rawat ` ` See Pic
7.23-11-2021BR-37Placing of vertical member at L8Deepak Rawat ` ` See Pic
8.22-11-2021BR-37Errection work is in progressDeepak Rawat ` ` See Pic
9.22-11-2021BR-37Errection work is in progressDeepak Rawat ` ` See Pic
10.22-11-2021BR-37Errection work is in progressDeepak Rawat ` ` See Pic
11.22-11-2021BR-37Errection work is in progressDeepak Rawat ` ` See Pic
12.22-11-2021BR-37Placing of diagonal memberDeepak Rawat ` ` See Pic
13.20-11-2021BR-37Fixing of daigonal member is in progressDeepak Rawat ` ` See Pic
14.20-11-2021BR-37Fixing of daigonal member work is in progressDeepak Rawat ` ` See Pic
15.20-11-2021BR-37Top horizontal bracing placing at A1 side work is in progressDeepak Rawat ` ` See Pic
16.20-11-2021BR-37Top horizontal bracing placing at A1 side work is in progressDeepak Rawat ` ` See Pic
17.19-11-2021BR-37Errection work is in progressDeepak Rawat ` ` See Pic
18.19-11-2021BR-37Placing of vertical member at L6Deepak Rawat ` ` See Pic
19.19-11-2021BR-37Placing of vertical member at L6Deepak Rawat ` ` See Pic
20.19-11-2021BR-37Placing of vertical member at L6Deepak Rawat ` ` See Pic