Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/37 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 614 Package Name: UDRP/AF/BR/37 Sanction Cost: 456.41  lakhs
District: Pauri Block: Zahrikhal Constituency: Lansdowne Circle:
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4066   Bridge in KM-3 of Sisaldi Satpuli MR (45.000 M.) (completed)
Procurement:
Package No.: 614        Package Name: UDRP/AF/BR/37        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/37        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 01-02-2020        Intended Completion Date: 18-03-2022        Original End Date:  30-04-2021
Total Bond Cost: 46758700.08 (467.59 lakhs)        Variation Cost: -367948.17 (-3.68 lakhs)     Hence Total Bond Cost is   46390751.91 (463.91 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 12998724 for 556 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.11 KM7.830.11 KM0.11 KM1.667.83
2.R/Wall, B/ Wall Type Protection works70.00 m16.9170.00 m70.00 m3.5916.91
3.PC/CC i/c Prime Coat, Tack Coat0.15 KM1.290.15 KM0.15 KM0.271.29
4.longitudinal Drain105.00 m1.23105.00 m105.00 m0.261.23
5.Crash Barrier94.00 m5.5594.00 m94.00 m1.185.55
6.Road Furniture4.00 No0.404.00 No4.00 No0.090.40
7.Env. Man & Moni Plan1.00 Job2.861.00 Job1.00 Job0.612.86
8.Other Allied Works & Finishing Work 10.00 Job8.0310.00 Job10.00 Job1.78.03
9.Foundation RHS1.00 Job0.921.00 Job1.00 Job0.20.92
10.Foundation LHS1.00 Job0.921.00 Job1.00 Job0.20.92
11.Abutment Superstructure RHS1.00 Job19.831.00 Job1.00 Job4.219.83
12.Abutment Superstructure LHS1.00 Job8.751.00 Job1.00 Job1.868.75
13.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no23.691.00 no1.00 no5.0223.69
14.Steel Railing/crush barrier0.00 m0.000.00 m0.00 m00.00
15.Approach Ramp /path 105.00 m2.83105.00 m105.00 m0.62.83
16.Protection Work1.00 Job5.781.00 Job1.00 Job1.225.78
17.Errection Work1.00 Job132.061.00 Job1.00 Job27.99132.06
18.Gabion work150.00 m4.84150.00 m150.00 m1.034.84
19.PCC in Foundation13.62 cum0.9813.62 cum13.62 cum0.210.98
20.Fabrication Work1.00 job219.531.00 job1.00 job46.53219.53
21.Fixing Bearing/Slab Casting6.00 job4.576.00 job6.00 job0.974.57
22.Wearing Coat9.88 Cum3.039.88 Cum9.88 Cum0.643.03
Total Amount: 471.83 100   471.83
Remarks: WORK IN PROGRESS AND THIRD EOT IS SANCTIONED UPTO 28TH FEB 2022       Work Program Made On: 05-12-2020       Updation of work program on: 02-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-202126.85  lakhs
2.29-July-2021204.41  lakhs
3.31-August-202136.62  lakhs
4.02-November-20219.10  lakhs
5.28-December-202167.37  lakhs
6.21-February-202267.23  lakhs
7.31-May-202238.23  lakhs
8.15-June-202214.10  lakhs
Total 463.91  lakhs
% Payment 100 %
Advance Amount:  41.75  lakhs        Recovered Amount:  41.75  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 345     No. of Test Done : 350      No. of Test Passed : 348      No. of Test Failed : 2   Test report of this package
Number of Pics Available on Web Repository: 714
Number of Notice(s) issued: 2

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-04-2022Br37Bridge work completedKrishnan gopalunknownunknown See Pic
2.06-04-2022Br37Bridge work completedKrishnan gopalunknownunknown See Pic
3.06-04-2022Br37Bridge work completedKrishnan gopalunknownunknown See Pic
4.04-04-2022BR-37Bottom shuttring checking by R.E.sir for deck slabDeepak Rawat ` ` See Pic
5.30-03-2022Br37RCC crash barrier completedKrishnan gopalunknownunknown See Pic
6.30-03-2022Br37Downstream side crash barrier concrete work is in progressKrishnan gopalunknownunknown See Pic
7.30-03-2022Br37Deck slab concrete work is in progressKrishnan gopalunknownunknown See Pic
8.30-03-2022Br37Deck slab concrete work is in progress,slump checked and found satisfactoryKrishnan gopalunknownunknown See Pic
9.30-03-2022Br37Painting work is in progressKrishnan gopalunknownunknown See Pic
10.30-03-2022Br37Deck slab work is in progressKrishnan gopalunknownunknown See Pic
11.30-03-2022Br37Deck slab work is in progressKrishnan gopalunknownunknown See Pic
12.30-03-2022Br37Expansion joint fixing work is in progressKrishnan gopalunknownunknown See Pic
13.30-03-2022Br37Painting work is in progressKrishnan gopalunknownunknown See Pic
14.30-03-2022Br37Gradation workKrishnan gopalunknownunknown See Pic
15.30-03-2022Br37Deck slab crash barrier reinforcement work is in progressKrishnan gopalunknownunknown See Pic
16.27-02-2022BR-37Deck Slab reinforcement Checking is in progressBharat Bhoosan Sharmaunknownunknown See Pic
17.25-02-2022BR-37Curing at bearing pedestalDeepak Rawat ` ` See Pic
18.24-02-2022BR-37Paint work is in progressDeepak Rawat ` ` See Pic
19.24-02-2022BR-37Paint work is in progressDeepak Rawat ` ` See Pic
20.24-02-2022BR-37Steel binding work is in progressDeepak Rawat ` ` See Pic