UDRP/AF/BR/36
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
Package No.: |
613 |
Package Name: |
UDRP/AF/BR/36 |
Sanction Cost: |
162.79 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 4060 Bridge on KM-11 of Agrakhal Kusraila (24.000 M.) (completed) |
|
Procurement: |
Package No.: 613
Package Name: UDRP/AF/BR/36
Tender Date: 02-09-2019
Current Status: Agreement signed
Achieved on Date: 22-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/36
Contractor Name: M/S.ARKS Universal pvt.ltd
|
Start Date: 01-02-2020
Intended Completion Date: 18-09-2021
Original End Date: 31-01-2021
|
Total Bond Cost: 14987873.41 (149.88 lakhs)
Variation Cost: -2464057.81 (-24.64 lakhs) Hence Total Bond Cost is 12523815.6 (125.24 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 3477216 for 464 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 13.53 | 1.00 Job | 1.00 Job | 9.42 | 13.53 | 2. | Foundation RHS | 1.00 Job | 0.56 | 1.00 Job | 1.00 Job | 0.39 | 0.56 | 3. | Foundation LHS | 1.00 Job | 0.56 | 1.00 Job | 1.00 Job | 0.39 | 0.56 | 4. | Abutment Superstructure RHS | 1.00 Job | 7.29 | 1.00 Job | 1.00 Job | 5.08 | 7.29 | 5. | Abutment Superstructure LHS | 1.00 Job | 7.29 | 1.00 Job | 1.00 Job | 5.08 | 7.29 | 6. | Steel Railing/crush barrier | 50.00 m | 2.58 | 50.00 m | 50.00 m | 1.8 | 2.58 | 7. | Approach Ramp /path | 100.00 m | 24.31 | 100.00 m | 100.00 m | 16.92 | 24.31 | 8. | Protection Work | 1.00 Job | 23.34 | 1.00 Job | 1.00 Job | 16.25 | 23.34 | 9. | Errection Work | 1.00 Job | 15.24 | 1.00 Job | 1.00 Job | 10.61 | 15.24 | 10. | PCC in Foundation | 8.87 cum | 0.61 | 8.87 cum | 8.87 cum | 0.43 | 0.61 | 11. | Fabrication Work | 1.00 job | 35.70 | 1.00 job | 1.00 job | 24.85 | 35.70 | 12. | Abutment Substructure RHS | 1.00 Job | 4.60 | 1.00 Job | 1.00 Job | 3.2 | 4.60 | 13. | Abutment Substructure LHS | 1.00 Job | 4.60 | 1.00 Job | 1.00 Job | 3.2 | 4.60 | 14. | Fixing Bearing/Slab Casting | 1.00 job | 1.67 | 1.00 job | 1.00 job | 1.16 | 1.67 | 15. | Back Wall/ Approach slab | 1.00 job | 0.83 | 1.00 job | 1.00 job | 0.58 | 0.83 | 16. | Wearing Coat | 7.97 Cum | 0.91 | 7.97 Cum | 7.97 Cum | 0.64 | 0.91 |
Total Amount: |
143.62 |
|
100 |
143.62 |
|
Remarks:
No Remarks
Work Program Made On:
15-10-2020
Updation of work program on:
25-02-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-February-2021 | 52.30 lakhs |
2. | 30-March-2021 | 3.72 lakhs |
3. | 31-May-2021 | 37.68 lakhs |
4. | 04-September-2021 | 14.02 lakhs |
5. | 31-March-2022 | 17.52 lakhs |
Total |
125.24 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 64 |
No Notice issued. |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Agrakhal Kushrela km 11 | Bridge work Completed | Sudhir Kumar | ` | ` | See Pic |
2. | 21-03-2022 | Agrakhal-Kusraila KM-11 | Down stream side of bridge | Suresh Prasad | ` | ` | See Pic |
3. | 21-03-2022 | Agrakhal-Kusraila KM-11 | Approach road LHS side to RHS SIDE | Suresh Prasad | ` | ` | See Pic |
4. | 21-03-2022 | Agrakhal-Kusraila KM-11 | Agrakhal-Kusraila KM-11 bridge RHS SIDE | Suresh Prasad | ` | ` | See Pic |
5. | 21-03-2022 | Agrakhal-Kusraila KM-11 | Up stream side of the bridge | Suresh Prasad | ` | ` | See Pic |
6. | 21-03-2022 | Agrakhal-Kusraila KM-11 | Agrakhal-Kusraila KM-11 bridge LHS SIDE | Suresh Prasad | ` | ` | See Pic |
7. | 11-08-2021 | Agrakhal-Kusraila KM-11 | Deck Slab curing by pond | Deepak Rawat | unknown | unknown | See Pic |
8. | 11-08-2021 | Agrakhal-Kusraila KM-11 A2 side | Protection work RR wall A2 side for approach road | Deepak Rawat | unknown | unknown | See Pic |
9. | 17-07-2021 | Agrakhal-Kusraila KM-11 | Crash Barrier D/S casting work in progress | Suresh Prasad | ` | ` | See Pic |
10. | 17-07-2021 | Agrakhal-Kusraila KM-11 | Crash Barrier U/S Casting Completed | Suresh Prasad | ` | ` | See Pic |
11. | 14-07-2021 | Agrakhal kusraila km 11 bridge | Crash barrier concreting in progress | Pooja joshi | ` | ` | See Pic |
12. | 14-07-2021 | Agrakhal kusraila km 11 | Reinforcement work for deck slab | Pooja joshi | ` | ` | See Pic |
13. | 03-07-2021 | Agrakhal kusrila Km-11 | Deck Slab Curing work | Vikas Verma | unknown | unknown | See Pic |
14. | 02-07-2021 | Agrakhal-Kusraila KM-11 | Agrakhal-Kusraila KM-11 DECK SLAB RCC M-35 Casting Completed | Suresh Prasad | ` | ` | See Pic |
15. | 02-07-2021 | Agrakhal-Kusraila KM-11 | Agrakhal-Kusraila KM-11 Cube casting M-35 for Deck Slab | Suresh Prasad | ` | ` | See Pic |
16. | 02-07-2021 | Agrakhal-Kusraila KM-11 | Agrakhal-Kusraila KM-11 Deck slab Casting | Suresh Prasad | ` | ` | See Pic |
17. | 15-05-2021 | Agrakhal Kushrela km 11 | Pedestal Casting | Sudhir Kumar | ` | ` | See Pic |
18. | 06-05-2021 | Agrakhal Kushrela km 11 | Preparation for Steel citting | Sudhir Kumar | ` | ` | See Pic |
19. | 06-05-2021 | Agrakhal Kushrela km 11 | Site inspection for bearing fixing | Sudhir Kumar | ` | ` | See Pic |
20. | 29-04-2021 | Agarakhal km-11 | Bearing leveling work in progress | Atul | unknown | unknown | See Pic |
|
|