Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/36 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 613 Package Name: UDRP/AF/BR/36 Sanction Cost: 162.79  lakhs
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4060   Bridge on KM-11 of Agrakhal Kusraila (24.000 M.) (completed)
Procurement:
Package No.: 613        Package Name: UDRP/AF/BR/36        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/36        Contractor Name: M/S.ARKS Universal pvt.ltd       
Start Date: 01-02-2020        Intended Completion Date: 18-09-2021        Original End Date:  31-01-2021
Total Bond Cost: 14987873.41 (149.88 lakhs)        Variation Cost: -257907.39 (-2.58 lakhs)     Hence Total Bond Cost is   14729966.02 (147.3 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 3477216 for 464 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job13.531.00 Job1.00 Job9.4213.53
2.Foundation RHS1.00 Job0.561.00 Job1.00 Job0.390.56
3.Foundation LHS1.00 Job0.561.00 Job1.00 Job0.390.56
4.Abutment Superstructure RHS1.00 Job7.291.00 Job1.00 Job5.087.29
5.Abutment Superstructure LHS1.00 Job7.291.00 Job1.00 Job5.087.29
6.Steel Railing/crush barrier50.00 m2.5850.00 m50.00 m1.82.58
7.Approach Ramp /path 100.00 m24.31100.00 m100.00 m16.9224.31
8.Protection Work1.00 Job23.341.00 Job1.00 Job16.2523.34
9.Errection Work1.00 Job15.241.00 Job1.00 Job10.6115.24
10.PCC in Foundation8.87 cum0.618.87 cum8.87 cum0.430.61
11.Fabrication Work1.00 job35.701.00 job1.00 job24.8535.70
12.Abutment Substructure RHS1.00 Job4.601.00 Job1.00 Job3.24.60
13.Abutment Substructure LHS1.00 Job4.601.00 Job1.00 Job3.24.60
14.Fixing Bearing/Slab Casting1.00 job1.671.00 job1.00 job1.161.67
15.Back Wall/ Approach slab1.00 job0.831.00 job1.00 job0.580.83
16.Wearing Coat7.97 Cum0.917.97 Cum7.97 Cum0.640.91
Total Amount: 143.62 100   143.62
Remarks: No Remarks       Work Program Made On: 15-10-2020       Updation of work program on: 25-02-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-February-202152.30  lakhs
2.30-March-20213.72  lakhs
3.31-May-202137.68  lakhs
4.04-September-202114.02  lakhs
Total 107.72  lakhs
% Payment 73.13 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 181     No. of Test Done : 182      No. of Test Passed : 181      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 58
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-08-2021Agrakhal-Kusraila KM-11Deck Slab curing by pondDeepak Rawatunknownunknown See Pic
2.11-08-2021Agrakhal-Kusraila KM-11 A2 sideProtection work RR wall A2 side for approach roadDeepak Rawatunknownunknown See Pic
3.17-07-2021Agrakhal-Kusraila KM-11Crash Barrier D/S casting work in progressSuresh Prasad ` ` See Pic
4.17-07-2021Agrakhal-Kusraila KM-11Crash Barrier U/S Casting CompletedSuresh Prasad ` ` See Pic
5.14-07-2021Agrakhal kusraila km 11 bridgeCrash barrier concreting in progressPooja joshi ` ` See Pic
6.14-07-2021Agrakhal kusraila km 11Reinforcement work for deck slabPooja joshi ` ` See Pic
7.03-07-2021Agrakhal kusrila Km-11Deck Slab Curing workVikas Vermaunknownunknown See Pic
8.02-07-2021Agrakhal-Kusraila KM-11Agrakhal-Kusraila KM-11 DECK SLAB RCC M-35 Casting CompletedSuresh Prasad ` ` See Pic
9.02-07-2021Agrakhal-Kusraila KM-11Agrakhal-Kusraila KM-11 Cube casting M-35 for Deck SlabSuresh Prasad ` ` See Pic
10.02-07-2021Agrakhal-Kusraila KM-11Agrakhal-Kusraila KM-11 Deck slab CastingSuresh Prasad ` ` See Pic
11.15-05-2021Agrakhal Kushrela km 11Pedestal CastingSudhir Kumar ` ` See Pic
12.06-05-2021Agrakhal Kushrela km 11Preparation for Steel cittingSudhir Kumar ` ` See Pic
13.06-05-2021Agrakhal Kushrela km 11Site inspection for bearing fixingSudhir Kumar ` ` See Pic
14.29-04-2021Agarakhal km-11Bearing leveling work in progressAtulunknownunknown See Pic
15.15-04-2021Agarakhal km-11Bracing angle & End cross girder work in progressAtulunknownunknown See Pic
16.15-04-2021Agarakhal Km-11Launching of steel girder bridge on abutment Km-11 work in progressAtulunknownunknown See Pic
17.15-04-2021Agrakhal Kushrela km 11Errection work completeSudhir Kumar ` ` See Pic
18.23-03-2021Agrakhal-Kusraila KM-11 erection work in progressAgrakhal-Kusraila KM-11 erection work in progressSuresh Prasad ` ` See Pic
19.23-03-2021Agrakhal Kushrela km 11Girder Assembling work in progressSudhir Kumar ` ` See Pic
20.21-03-2021Agarakhal Km-11Assembling of steel bridge girderAtulunknownunknown See Pic