Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/BR/96 Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 610 Package Name: UDRP/AF/BR/96 Sanction Cost: 269.39  lakhs
District: Champawat Block: Champawat Constituency: Champawat Circle:
DEA: DEA Champawat DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4136   Bridge Over Gandak River at KM-2 of Champawat to Manch Tamali MR (30.000 M.) (in prorgress)
Procurement:
Package No.: 610        Package Name: UDRP/AF/BR/96        Tender Date: 30-12-2019        Current Status: Agreement signed        Achieved on Date: 14-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/96        Contractor Name: M/s Laxmi Datt Binwal       
Start Date: 21-08-2020        Intended Completion Date: 20-11-2021       
Total Bond Cost: 25133492.44 (251.33 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 6208098 for 494 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job21.691.00 Job0.40 Job3.458.68
2.Foundation RHS1.00 Job9.911.00 Job1.00 Job3.949.91
3.Foundation LHS1.00 Job14.541.00 Job1.00 Job5.7914.54
4.Abutment Superstructure RHS1.00 Job26.871.00 Job1.00 Job10.6926.87
5.Abutment Superstructure LHS1.00 Job26.871.00 Job1.00 Job10.6926.87
6.Fixing of chequered Plate/RCC Deck62.10 sqm6.4062.10 sqm0.00 sqm00.00
7.Steel Railing/crush barrier64.00 m3.4364.00 m0.00 m00.00
8.Approach Ramp /path 110.00 m45.10110.00 m20.00 m3.268.20
9.Protection Work1.00 Job22.811.00 Job0.40 Job3.639.13
10.Errection Work1.00 Job21.191.00 Job0.00 Job00.00
11.Fabrication Work1.00 job52.521.00 job1.00 job20.952.52
Total Amount: 251.33 62.35   156.72
Remarks: No Remarks       Work Program Made On: 16-12-2020       Updation of work program on: 03-08-2021      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-March-202118.45  lakhs
2.06-May-202120.48  lakhs
3.13-July-202152.20  lakhs
4.28-August-20215.68  lakhs
5.09-November-202123.10  lakhs
Total 119.91  lakhs
% Payment 47.71 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 235     No. of Test Done : 257      No. of Test Passed : 257      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 64
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-11-2021BR-96Erection work completedAbhay Singh ` ` See Pic
2.26-11-2021BR-96Retaining wall is in progress in abutment A1 side D/SAbhay Singh ` ` See Pic
3.22-11-2021BR -96 siteTorque monitoring of bolt in progress.Anuj shekhar ` ` See Pic
4.20-11-2021BR-96Sample collection for water ambient monitoring testAbhay singh ` ` See Pic
5.20-11-2021BR-96Sample collection for Soil ambient monitoring testAbhay Singh ` ` See Pic
6.20-11-2021BR-96Air quality monitoring test abutment A2 sideAbhay Singh ` ` See Pic
7.20-11-2021BR-96Noise quality monitoring test abutment A2 sideAbhay singh ` ` See Pic
8.20-11-2021BR-96Noise quality monitoring test abutment A1 sideAbhay Singh ` ` See Pic
9.20-11-2021BR-96Air quality monitoring test abutment A1 sideAbhay Singh ` ` See Pic
10.19-11-2021Abutment A1Bridge erection work is in progressSanjeev Kumar ` ` See Pic
11.19-11-2021Abutment A2 end BR-96Protection work is in progress at BR-96Sanjeev Kumar ` ` See Pic
12.14-11-2021ChampawatSteel girder erected and shiftedPARAMBEER SINGH RAWAT ` ` See Pic
13.12-11-2021ChampawatSteel girder assemble work in progress at site.PARAMBEER SINGH RAWAT ` ` See Pic
14.11-11-2021BR 96 siteLaunching work in progressAnuj shekhar ` ` See Pic
15.25-10-2021MeerutBearing testingV k srivastava ` ` See Pic
16.25-10-2021MeerutBearing testingV k srivastava ` ` See Pic
17.25-10-2021MeerutBearing testingVk srivastava ` ` See Pic
18.25-10-2021MeerutBearing testingVk srivastava ` ` See Pic
19.25-10-2021MeerutBearing testingV k srivastava ` ` See Pic
20.25-10-2021MeerutBearing testingVk srivastava ` ` See Pic