UDRP/PWD/01/30/RD/032(a)
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
61 |
Package Name: |
UDRP/PWD/01/30/RD/032(a) |
Sanction Cost: |
362.59 lakhs |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 3137 Dhanari Motor road to Pujargaon Motor road (3.100 KM.) (completed) | 2 3194 Pipli to gawana Motor road (2.900 KM.) (completed) |
|
Procurement: |
Package No.: 61
Package Name: UDRP/PWD/01/30/RD/032(a)
Tender Date: 13-02-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/032(a)
Contractor Name: Bharat Construction
|
Start Date: 14-07-2015
Intended Completion Date: 28-02-2018
Original End Date: 13-10-2016
|
Total Bond Cost: 36258671.4 (362.59 lakhs)
Variation Cost: -2116471.67 (-21.16 lakhs) Hence Total Bond Cost is 34142199.73 (341.42 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1685997 for 93 days
LD Analysis for Milestone2: calculated LD is Rs 5583732 for 308 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.10 KM | 1.57 | 3.10 KM | 3.10 KM | 0.42 | 1.57 | 2. | R/Wall, B/ Wall Type Protection works | 1458.00 m | 128.79 | 1458.00 m | 1458.00 m | 35.18 | 128.79 | 3. | GSB/RBI/G-1 | 3.60 KM | 28.87 | 3.10 KM | 3.10 KM | 8.04 | 28.87 | 4. | G-2 | 3.60 KM | 22.28 | 3.10 KM | 3.10 KM | 6.2 | 22.28 | 5. | G-3 | 4.20 KM | 27.29 | 3.60 KM | 3.60 KM | 7.56 | 27.29 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.90 KM | 100.48 | 5.90 KM | 5.90 KM | 27.66 | 100.48 | 7. | Culverts/Scupper | 21.00 No | 27.10 | 21.00 No | 21.00 No | 7.52 | 27.10 | 8. | longitudinal Drain | 5800.00 m | 14.80 | 5800.00 m | 5800.00 m | 4.08 | 14.80 | 9. | Parapet | 240.00 No | 8.21 | 260.00 No | 260.00 No | 2.26 | 8.21 | 10. | Road Furniture | 88.00 No | 3.92 | 176.00 No | 176.00 No | 1.08 | 3.92 |
Total Amount: |
363.31 |
|
100 |
363.31 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015
Updation of work program on:
28-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 14-March-2016 | 24.73 lakhs |
2. | 30-March-2016 | 14.97 lakhs |
3. | 28-March-2017 | 85.30 lakhs |
4. | 19-May-2017 | 16.00 lakhs |
5. | 26-December-2017 | 15.00 lakhs |
6. | 27-February-2018 | 51.26 lakhs |
7. | 31-March-2018 | 40.32 lakhs |
8. | 31-May-2018 | 31.15 lakhs |
9. | 09-November-2015 | 17.71 lakhs |
10. | 26-November-2015 | 7.33 lakhs |
11. | 21-January-2016 | 21.45 lakhs |
12. | 26-October-2016 | 15.35 lakhs |
Total |
340.57 lakhs |
% Payment |
99.75 % |
|
Advance Amount: 94.36 lakhs
Recovered Amount: 94.36 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 252 |
Number of Notice(s) issued: 151 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-03-2018 | Ch 2/2 | P. C work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 25-12-2017 | 1/4 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
3. | 17-12-2017 | 3/4 | Dhanari Pujargaon motor road PC work Start now | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
4. | 14-03-2017 | 1/11-12 | Plum and wirecrate work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
5. | 27-02-2017 | 0/32 | Patri compaction required | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
6. | 27-02-2017 | 1/12 | Protection work in B/wall in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 27-02-2017 | 1/12 | Protection work in R/wall in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
8. | 24-02-2017 | 0/30 | Third party test of PC | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
9. | 24-02-2017 | 1/20 | Plum and wire crate | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
10. | 15-01-2017 | 1/12 | Protection work in progress but no labour found on site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
11. | 15-01-2017 | 2/34 | Patri dressing & compaction required but no labour found on site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
12. | 02-01-2017 | 1/12 | Plum work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
13. | 02-01-2017 | 1/12 | Plum casting work in progress | Vikas Vyas | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
14. | 29-12-2016 | 1/11 | Plum work in progress | Vikas Vyas | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
15. | 29-12-2016 | 1/12 | Plum work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
16. | 21-12-2016 | Ch 1/12 | Material collection for damaged R.W reconstruction | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
17. | 13-12-2016 | 1/12 | Material for protection work collected no labour found | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
18. | 07-12-2016 | 2/11 -12 | Excavation for plum and wire crate | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
19. | 20-11-2016 | 0/15 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
20. | 17-11-2016 | 0/34 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|