Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/35(BR) Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 608 Package Name: UDRP/AF/35(BR) Sanction Cost: 1027.01  lakhs
District: Udham Singh Nagar Block: Sitarganj Constituency: Sitarganj Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4099   Sukhi River (120.000 M.) (in prorgress)
Procurement:
Package No.: 608        Package Name: UDRP/AF/35(BR)        Tender Date: 10-01-2019        Current Status: Agreement signed        Achieved on Date: 03-06-2019

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/35(BR)        Contractor Name: Doon Infrastructure Ltd.       
Start Date: 15-06-2019        Intended Completion Date: 12-05-2021        Original End Date:  14-09-2020
Total Bond Cost: 94827516.3 (948.28 lakhs)        Variation Cost: 11010137.81 (110.1 lakhs)     Hence Total Bond Cost is   105837654.11 (1058.38 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 29538922 for 623 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Stressing & Grouting48.00 Job69.44120.00 Job120.00 Job6.5669.44
2.Env. Man & Moni Plan45.00 Job5.1045.00 Job25.00 Job0.272.83
3.Other Allied Works & Finishing Work 12.00 Job27.570.00 Job0.00 Job00.00
4.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 6.00 no83.226.00 no6.00 no7.8683.22
5.Steel Railing/crush barrier240.00 m28.87360.00 m360.00 m2.7328.87
6.Approach Ramp /path 850.00 m156.96850.00 m300.00 m5.2355.40
7.Protection Work4.00 Job175.354.00 Job3.50 Job14.5153.43
8.Fixing Bearing/Slab Casting48.00 job15.0248.00 job48.00 job1.4215.02
9.Back Wall/ Approach slab2.00 job10.052.00 job0.00 job00.00
10.Providing and laying cutting6.78 mt6.086.78 mt6.78 mt0.576.08
11.Concreting Well Curb and Steaming7.00 job179.207.00 job7.00 job16.93179.20
12.Well Sinking160.38 rmt25.41149.00 rmt149.00 rmt2.425.41
13.Bottom Plug/Top Plug329.00 Cum40.32329.00 Cum329.00 Cum3.8140.32
14.Sand Filling2087.52 Cum41.212087.52 Cum2087.52 Cum3.8941.21
15.Well-Abutments/Pier/Shafts/Caps7.00 job63.737.00 job7.00 job6.0263.73
16.PSC girder & Diaphragms24.00 No118.4224.00 No24.00 No11.19118.42
17.Wearing Coat101.75 Cum12.42101.75 Cum101.75 Cum1.1712.42
Total Amount: 1058.37 84.57   895
Remarks: No Remarks       Work Program Made On: 26-11-2019       Updation of work program on: 05-04-2021      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.06-January-202070.21  lakhs
2.29-December-20200.00  lakhs
3.19-February-2021438.96  lakhs
4.30-March-202183.45  lakhs
5.31-May-2021106.06  lakhs
6.27-August-202192.03  lakhs
7.01-November-202197.52  lakhs
Total 888.23  lakhs
% Payment 83.92 %
Advance Amount:  113.28  lakhs        Recovered Amount:  113.28  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 4476     No. of Test Done : 4573      No. of Test Passed : 4502      No. of Test Failed : 71   Test report of this package
Number of Pics Available on Web Repository: 386
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-11-2021875 LH S SiteFDT check of GSB material Ch 875Santosh shukla ` ` See Pic
2.22-11-2021BR 35Channelized work in progressSantosh shukla ` ` See Pic
3.20-11-2021BR 35 ( U/s 230 mtr)Sukhi river water Channelization workSantosh shukla ` ` See Pic
4.20-11-2021Ch 0.700GSB laying 1st layer in progressPrem Prakash AE ` ` See Pic
5.20-11-2021Deck slab D2RCC M 30 for Wearing coat in D2Prem Prakash AE ` ` See Pic
6.20-11-2021Beam no B1Stressing work in progress in Beam B1 cable no 4Prem Prakash AE ` ` See Pic
7.18-11-2021U/s 230 mtr from BridgeRiver Dredging and Water Channelization workChhatrapati Pant ` ` See Pic
8.17-11-2021U/S 230 MtrSukhi River dredging work in progressChhatrapati Pant ` ` See Pic
9.17-11-2021MaaPurnagiri slope protectionSite physical handover to contractor representativeChhatrapati Pant ` ` See Pic
10.14-10-2021Chainage 800 to 900GSB laying work in ProgressSantosh shukla ` ` See Pic
11.12-10-2021Approach Slab A2 Side ( Chainage 510 to 513.5Approach Slab Concrete work in progressChhatrapati Pant ` ` See Pic
12.12-10-2021Chainage 700 to 900GSB material laying, BR 35, Sitarganj, U S NagarChhatrapati Pant ` ` See Pic
13.05-10-2021A I sideExpension joint concrete work in ProgressSantosh shukla ` ` See Pic
14.05-10-2021Abutment A1 Chainage 330Concreting of Expansion JointChhatrapati Pant ` ` See Pic
15.05-10-2021Chainage 330Concreting of Expansion jointChhatrapati Pant ` ` See Pic
16.05-10-2021A 1 site AbutmentExpension joint A1 Concrete Work M 45Santosh shukla ` ` See Pic
17.04-10-2021Road Curb Concrete Deck Slab 01 Right side ( Ch 330 to 360)Road Curb Concrete, BR35Chhatrapati Pant ` ` See Pic
18.04-10-2021Back Wall /Dirt wall Abutment A1 Side Chainage 330BR 35, Sitarganj, U S NagarChhatrapati Pant ` ` See Pic
19.04-10-2021A 1 L/HFootpath Kerb CH. 330 to 360 LHS Work in ProgressSantosh shukla ` ` See Pic
20.24-09-2021Chainage 950 to 1050Earthwork in progressSantosh shukla ` ` See Pic