Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/29(BR) Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 606 Package Name: UDRP/AF/29(BR) Sanction Cost: 988.42  lakhs
District: Tehri Block: Pratapnagar Constituency: Pratapnagar Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4087   120m span bridle Suspension Bridge at Piplogi (120.000 M.) (completed)
Procurement:
Package No.: 606        Package Name: UDRP/AF/29(BR)        Tender Date: 07-02-2018        Current Status: Agreement signed        Achieved on Date: 02-07-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/29(BR)        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 12-07-2018        Intended Completion Date: 27-07-2021        Original End Date:  11-10-2019
Total Bond Cost: 85440257.95 (854.4 lakhs)        Variation Cost: 1331444.34 (13.31 lakhs)     Hence Total Bond Cost is   86771702.29 (867.72 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 37123680 for 869 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job22.631.00 Job1.00 Job2.9222.63
2.Foundation RHS1.00 Job2.591.00 Job1.00 Job0.342.59
3.Foundation LHS1.00 Job2.591.00 Job1.00 Job0.342.59
4.Abutment Superstructure RHS1.00 Job56.121.00 Job1.00 Job7.2456.12
5.Abutment Superstructure LHS1.00 Job56.121.00 Job1.00 Job7.2456.12
6.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job170.371.00 job1.00 job21.99170.37
7.Anchor Block for Wind Cable: Reinforcement, Lewis 1.00 job92.871.00 job1.00 job11.9992.87
8.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no9.182.00 no2.00 no1.199.18
9.Fixing of Saddle pulley along with Rib plate and 4.00 no15.764.00 no4.00 no2.0315.76
10.Fixing Suspenders to Main cable with clamps and Ha154.00 no5.24154.00 no154.00 no0.685.24
11.Stretching Wind Guy cable, Fixing wind Ties with 574.00 m20.35574.00 m574.00 m2.6320.35
12.Fixing longitudinal Stringers/girders120.00 m12.48120.00 m120.00 m1.6112.48
13.Fixing of chequered Plate/RCC Deck306.00 sqm4.65306.00 sqm306.00 sqm0.64.65
14.Steel Railing/crush barrier240.00 m8.93240.00 m240.00 m1.158.93
15.Approach Ramp /path 100.00 m18.63100.00 m100.00 m2.418.63
16.Protection Work1.00 Job35.191.00 Job1.00 Job4.5435.19
17.Errection Work1.00 Job23.401.00 Job1.00 Job3.0223.40
18.Gabion work2400.00 m65.202400.00 m2400.00 m8.4265.20
19.PCC in Foundation261.00 cum8.50261.00 cum261.00 cum1.18.50
20.Excavation in soil5734.00 cum13.195734.00 cum5734.00 cum1.713.19
21.Fabrication Work1.00 job130.751.00 job1.00 job16.88130.75
Total Amount: 774.74 100   774.74
Remarks: No Remarks       Work Program Made On: 15-05-2019       Updation of work program on: 03-04-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-March-2020212.36  lakhs
2.11-November-2020208.17  lakhs
3.19-December-202043.64  lakhs
4.04-February-202142.14  lakhs
5.19-February-202117.54  lakhs
6.30-March-202195.09  lakhs
7.31-May-202170.78  lakhs
8.09-July-202159.20  lakhs
9.28-October-202132.07  lakhs
10.31-March-202220.59  lakhs
Total 801.58  lakhs
% Payment 92.38 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 746     No. of Test Done : 746      No. of Test Passed : 745      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 51
Number of Notice(s) issued: 1

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-01-2022Piplogi BR-29Top viewSuresh Prasad ` ` See Pic
2.21-01-2022Piplogi BR-29Top view from Piplogi gaonSuresh Prasad ` ` See Pic
3.21-01-2022Piplogi BR-29Side view from approach Piplogi gaon to suspension bridge LambgaonSuresh Prasad ` ` See Pic
4.21-01-2022Piplogi BR-29Piplogi ganow view from center of suspension bridgeSuresh Prasad ` ` See Pic
5.21-01-2022Piplogi BR-29Lambgaon view from center of suspension bridgeSuresh Prasad ` ` See Pic
6.21-01-2022Piplogi BR-29Project completed final view. Open the public.Suresh Prasad ` ` See Pic
7.21-01-2022Piplogi BR-29LHS side Approach road with Temple from Lambgaon t to PiplogiSuresh Prasad ` ` See Pic
8.21-01-2022Piplogi BR-29Approach road LHS side Lambgaon to PiplogiSuresh Prasad ` ` See Pic
9.21-01-2022Piplogi BR-29Top View of suspension bridgeSURESH PRASAD ` ` See Pic
10.07-07-2021Piplogi BR-29Piplogi BR-29Suresh Prasad ` ` See Pic
11.07-07-2021Piplogi BR-29Piplogi BR-29 Suspension Bridge over Jalkur river CompletedSuresh Prasad ` ` See Pic
12.03-07-2021Piplogi BR-29 Helth CampPiplogi BR-29 Helth CampSuresh Prasad ` ` See Pic
13.03-07-2021Piplogi BR-29 Abutment A1 SideAbutment A1 Side Tower and Anchor completedSuresh Prasad ` ` See Pic
14.26-06-2021A2 side Anchor block white washing wipA2 Side Anchor block white washing wipPARAMBEER SINGH RAWAT ` ` See Pic
15.26-06-2021Tower erection work and decking work completedTower erection and decking work completedPARAMBEER SINGH RAWAT ` ` See Pic
16.19-02-2021A1 side tower erection wip.Tower erection wip.PARAMBEER SINGH RAWAT ` ` See Pic
17.21-01-2021PIPLOGI Abutment A1 side Tower Erection work in progress.Piplogi Suspension bridge Abutment A1 side tower erection wipDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
18.08-09-2020Abutment A1Anutment RCC and approach road wallAE Saurab ChauhanAssistant EngineerUDRP R&B Tehri See Pic
19.13-08-2020A1 side anchor block 2nd lift wall shuttering wipAnchor block 2nd lift wall shuttering wipPARAMBEER SINGH RAWATunknownunknown See Pic
20.29-07-2020Anchor block A1 side 2nd lift wall steel binding wipAnchor block 2nd lift wall steel binding wipPARAMBEER SINGH RAWATunknownunknown See Pic