Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/32(BR) Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 604 Package Name: UDRP/AF/32(BR) Sanction Cost: 1182.96  lakhs
District: Almora Block: Bhikiyasain Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4034   Bridge at KM 15 of Balmara Syalde Kedar MR (105.000 M.) (in prorgress)
Procurement:
Package No.: 604        Package Name: UDRP/AF/32(BR)        Tender Date: 24-08-2018        Current Status: Agreement signed        Achieved on Date: 29-11-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/32(BR)        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 07-12-2018        Intended Completion Date: 11-07-2022        Original End Date:  05-03-2020
Total Bond Cost: 134280079.36 (1342.8 lakhs)        Variation Cost: 17918572.70 (179.19 lakhs)     Hence Total Bond Cost is   152198652.06 (1521.99 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 49280760 for 734 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job3.631.00 Job1.00 Job0.293.63
2.Other Allied Works & Finishing Work 1.00 Job115.321.00 Job1.00 Job9.36115.32
3.Foundation RHS1.00 Job32.051.00 Job1.00 Job2.632.05
4.Foundation LHS1.00 Job13.741.00 Job1.00 Job1.1113.74
5.Abutment Superstructure RHS0.00 Job0.000.00 Job0.00 Job00.00
6.Abutment Superstructure LHS0.00 Job0.000.00 Job0.00 Job00.00
7.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no33.791.00 no1.00 no2.7433.79
8.Fixing of chequered Plate/RCC Deck173.00 sqm33.79173.00 sqm173.00 sqm2.7433.79
9.Steel Railing/crush barrier1.00 m4.041.00 m0.00 m00.00
10.Approach Ramp /path 2.00 m218.752.00 m2.00 m17.75218.75
11.Protection Work1.00 Job39.471.00 Job1.00 Job3.239.47
12.Errection Work1.00 Job146.701.00 Job1.00 Job11.9146.70
13.Fabrication Work1.00 job352.801.00 job1.00 job28.62352.80
14.Abutment Substructure RHS1.00 Job143.181.00 Job1.00 Job11.62143.18
15.Abutment Substructure LHS1.00 Job95.461.00 Job1.00 Job7.7495.46
Total Amount: 1232.72 99.67   1228.68
Remarks: No Remarks       Work Program Made On: 29-03-2019       Updation of work program on: 22-05-2022      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-June-201923.28  lakhs
2.31-July-201949.53  lakhs
3.11-October-201950.74  lakhs
4.23-October-201918.25  lakhs
5.30-December-201930.02  lakhs
6.02-March-202072.44  lakhs
7.11-June-202084.37  lakhs
8.09-November-202057.14  lakhs
9.02-December-2020287.99  lakhs
10.15-February-2021124.52  lakhs
11.30-March-202157.65  lakhs
12.18-December-202169.57  lakhs
13.22-February-2022232.27  lakhs
14.31-March-202251.33  lakhs
15.22-August-202259.01  lakhs
16.30-November-2022110.01  lakhs
Total 1378.12  lakhs
% Payment 90.55 %
Advance Amount:  117.56  lakhs        Recovered Amount:  109.67  lakhs        Balance to be Recovered  7.89  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Bridge at KM 15 of Balmara Syalde Kedar MR(4034) water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 2246     No. of Test Done : 2256      No. of Test Passed : 2246      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 387
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022Km 15Deck slab Steel Binding in progressGovind Kumar ` ` See Pic
2.23-06-2022Km 15CampGovind Kumar ` ` See Pic
3.23-06-2022Km 15Health and safety training campGovind Kumar ` ` See Pic
4.23-06-2022Km 15Health checkup campGovind Kumar ` ` See Pic
5.23-06-2022Km 15Steel Binding in deck slab in progressGovind kumar ` ` See Pic
6.21-06-2022KM 15Super structureGovind kumar ` ` See Pic
7.21-06-2022KM -15Bolt torque checkingGovind kumar ` ` See Pic
8.21-06-2022Km 15Checking of bolt torque of bottom chordGovind kumar ` ` See Pic
9.21-06-2022A2Labour Health Checkup camp.Azhar ` ` See Pic
10.21-06-2022A2Labour Health Checkup campAzhar ` ` See Pic
11.15-06-2022BR-32Deck Slab Reinforcement.Azhar ` ` See Pic
12.10-06-2022Km 15Deck slab reinforcement binding in progressGovind kumar ` ` See Pic
13.10-06-2022Km 15Deck slab reinforcement binding work in progressGovind kumar ` ` See Pic
14.03-06-2022Ch 15Super structureGovind ` ` See Pic
15.03-06-2022A1BR-32Azhar ` ` See Pic
16.03-06-2022A2Bearing fixedAzhar ` ` See Pic
17.27-05-2022Bridge BR32Deck slab shuttering work in progress.Rajesh sharma ` ` See Pic
18.26-05-2022A1Shuttering work in progress.Azhar ` ` See Pic
19.26-05-2022Km 15BR -32Govind kumar ` ` See Pic
20.26-05-2022Km 15Super structureGovind kumar ` ` See Pic