Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/32(BR) Agreement signed
Project: UDRP-AF(Bridge/Slope) Package No.: 604 Package Name: UDRP/AF/32(BR) Sanction Cost: 1182.96  lakhs
District: Almora Block: Bhikiyasain Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  4034   Bridge at KM 15 of Balmara Syalde Kedar MR (105.000 M.) (in prorgress)
Procurement:
Package No.: 604        Package Name: UDRP/AF/32(BR)        Tender Date: 24-08-2018        Current Status: Agreement signed        Achieved on Date: 29-11-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/32(BR)        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 07-12-2018        Intended Completion Date: 20-04-2021        Original End Date:  05-03-2020
Total Bond Cost: 134280079.36 (1342.8 lakhs)        Variation Cost: 2936087.31 (29.36 lakhs)     Hence Total Bond Cost is   137216166.67 (1372.16 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 49280760 for 734 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job3.631.00 Job0.80 Job0.242.90
2.Other Allied Works & Finishing Work 1.00 Job115.321.00 Job0.75 Job7.0286.49
3.Foundation RHS1.00 Job32.051.00 Job1.00 Job2.632.05
4.Foundation LHS1.00 Job13.741.00 Job1.00 Job1.1113.74
5.Abutment Superstructure RHS0.00 Job0.000.00 Job0.00 Job00.00
6.Abutment Superstructure LHS0.00 Job0.000.00 Job0.00 Job00.00
7.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no33.791.00 no1.00 no2.7433.79
8.Fixing of chequered Plate/RCC Deck173.00 sqm33.79173.00 sqm0.00 sqm00.00
9.Steel Railing/crush barrier1.00 m4.041.00 m0.00 m00.00
10.Approach Ramp /path 2.00 m218.752.00 m1.65 m14.64180.47
11.Protection Work1.00 Job39.471.00 Job0.85 Job2.7233.55
12.Errection Work1.00 Job146.701.00 Job0.00 Job00.00
13.Fabrication Work1.00 job352.801.00 job1.00 job28.62352.80
14.Abutment Substructure RHS1.00 Job143.181.00 Job1.00 Job11.62143.18
15.Abutment Substructure LHS1.00 Job95.461.00 Job0.95 Job7.3690.68
Total Amount: 1232.72 78.66   969.65
Remarks: No Remarks       Work Program Made On: 29-03-2019       Updation of work program on: 20-11-2020      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-June-201923.28  lakhs
2.31-July-201949.53  lakhs
3.11-October-201950.74  lakhs
4.23-October-201918.25  lakhs
5.30-December-201930.02  lakhs
6.02-March-202072.44  lakhs
7.11-June-202084.37  lakhs
8.09-November-202057.14  lakhs
9.02-December-2020287.99  lakhs
10.15-February-2021124.52  lakhs
11.30-March-202157.65  lakhs
Total 855.93  lakhs
% Payment 62.38 %
Advance Amount:  109.67  lakhs        Recovered Amount:  81.15  lakhs        Balance to be Recovered  28.52  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Bridge at KM 15 of Balmara Syalde Kedar MR(4034) water sprinkling
Detailed report of this Package
Quality
No. of Test Required : 2163     No. of Test Done : 2173      No. of Test Passed : 2163      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 356
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-11-2021BR-32Abutment A-1 &A-2Govind kumar ss ` ` See Pic
2.27-11-2021BR-32Abutment A-1Govind kumar ss ` ` See Pic
3.22-11-2021Km 15 kedarAbutment A-2Govind kumar ss ` ` See Pic
4.22-11-2021Km 15 kedarAbutment A-2Govind kumar ss ` ` See Pic
5.14-10-2021Km 15ErectionGovind kumar ` ` See Pic
6.14-10-2021Km 15Erection workGovind kumar ` ` See Pic
7.11-09-2021Bridge BR32Erection work started.Rajesh sharma ` ` See Pic
8.11-08-2021Km 15Box culvertDeepak Rawatunknownunknown See Pic
9.11-08-2021Km 15Masonary workDeepak Rawatunknownunknown See Pic
10.09-08-2021Km 15Box culvert base slabGovind kumar ` ` See Pic
11.09-08-2021Km 15Box culvert concreteGovind kumar ` ` See Pic
12.07-08-2021Km 15A-2 abutment gabion boxGovind kumar ` ` See Pic
13.07-08-2021Km 15Pouring of Pcc of box culvertGovind kumar ` ` See Pic
14.03-08-2021Km 15PCC of box culvertGovind kumar ` ` See Pic
15.03-08-2021Km 15Stone masonary SH-12Govind kumar ` ` See Pic
16.03-08-2021Km 15Excavation for box culvertGovind kumar ` ` See Pic
17.22-07-2021BR32 kedarLHS information boardRajesh sharma ` ` See Pic
18.22-07-2021BR32 kedarLHS information boardRajesh sharma ` ` See Pic
19.13-07-2021Km15Abutment A1 & A2Govind kumar ` ` See Pic
20.05-07-2021Km 15Abutment A-1Govind kumar ` ` See Pic