Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/03/RD/030b Agreement signed
Project: UDRP-RB Package No.: 59 Package Name: UDRP/PWD/02/03/RD/030b Sanction Cost: 319.99  lakhs
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 2
Subproject in this package
1  1242   Hapla Gudam Motor Road (1.500 KM.) (completed)
2  1257   Nanprayag Devkhal to Gurshal Motor Road (2.250 KM.) (completed)
Procurement:
Package No.: 59        Package Name: UDRP/PWD/02/03/RD/030b        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 07-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/03/RD/030b        Contractor Name: R. B. Construction       
Start Date: 14-07-2015        Intended Completion Date: 25-04-2017        Original End Date:  13-10-2016
Total Bond Cost: 31427309.65 (314.27 lakhs)        Variation Cost: 371761.57 (3.72 lakhs)     Hence Total Bond Cost is   31799071.22 (317.99 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 722844 for 46 days        LD Analysis for Milestone2: calculated LD is Rs 5028480 for 320 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.50 KM4.922.50 KM2.50 KM2.34.92
2.R/Wall, B/ Wall Type Protection works589.00 m47.81589.00 m589.00 m23.2147.81
3.GSB/RBI/G-13.50 KM21.353.50 KM3.50 KM10.2221.35
4.G-23.65 KM23.183.65 KM3.65 KM10.8223.18
5.G-33.65 KM22.693.65 KM3.65 KM10.922.69
6.PC/CC i/c Prime Coat, Tack Coat3.65 KM42.253.55 KM3.55 KM20.2942.25
7.Cause Way0.00 No0.000.00 No0.00 No00.00
8.Culverts/Scupper 11.00 No29.1711.00 No11.00 No13.1329.17
9.longitudinal Drain1500.00 m9.951500.00 m1500.00 m4.329.95
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet50.00 No10.4450.00 No50.00 No4.5310.44
12.Road Furniture26.00 No0.6226.00 No26.00 No0.270.62
Total Amount: 212.38 100   212.38
Remarks: No Remarks       Work Program Made On: 11-08-2015       Updation of work program on: 23-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201531.72  lakhs
2.28-January-201631.04  lakhs
3.30-March-201627.84  lakhs
4.23-March-201761.44  lakhs
5.31-March-201710.43  lakhs
6.28-July-201764.39  lakhs
7.19-December-201763.51  lakhs
8.30-May-201827.62  lakhs
Total 317.99  lakhs
% Payment 100 %
Advance Amount:  36.53  lakhs        Recovered Amount:  6.53  lakhs        Balance to be Recovered  30.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 127     No. of Test Done : 150      No. of Test Passed : 137      No. of Test Failed : 13   Test report of this package
Number of Pics Available on Web Repository: 118
Number of Notice(s) issued: 83

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-09-2017Km 1Checking of road width.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.03-06-2017ch.1+325PC thickness checking found 22 mmSohanbir SinghJEUDRP R&B Chamoli See Pic
3.03-06-2017Ch. 1+375PC work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
4.26-05-20170+600Rectification of catch water drainAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
5.23-05-2017Ch.0+725G-1 Rolling work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
6.23-05-2017Ch. 0+700G-1 Laying work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
7.13-05-2017Chainage 1+435Thickness checking of pc and seal coat by JE and AE WB PWDAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
8.12-05-2017Ch. 1+350WBM G-3 Laying workSohanbir SinghJEUDRP R&B Chamoli See Pic
9.12-05-2017Ch. 1+400WBM G-3 LayerAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
10.10-05-2017Ch. 1+075Seal coat work competeSohanbir SinghJEUDRP R&B Chamoli See Pic
11.10-05-2017Ch.1+025Tack coat work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
12.09-05-2017Ch.0+325PC work rolling in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
13.08-05-20170.400PC Work is in progress thickness found 22 mmAshwani KumarREDSC4 R&B WB Chamoli See Pic
14.08-05-20170.350Seal coat work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
15.04-05-2017Ch.0+925PC Rolling Work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
16.04-05-2017Ch.1+475WBM G-2 Laying work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
17.12-04-2017Ch.1.650Meeting with vilagersManish RanaJEUDRP R&B Gopeshwar See Pic
18.28-03-2017Ch. 0+900KC type drain workSohanbir SinghJEUDRP R&B Chamoli See Pic
19.08-03-2017Ch-1.475Thickness checking G1 G2 G3Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
20.08-03-2017Ch- 0.400Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic