UDRP/PWD/02/03/RD/030b
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
59 |
Package Name: |
UDRP/PWD/02/03/RD/030b |
Sanction Cost: |
319.99 lakhs |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1242 Hapla Gudam Motor Road (1.500 KM.) (completed) | 2 1257 Nanprayag Devkhal to Gurshal Motor Road (2.250 KM.) (completed) |
|
Procurement: |
Package No.: 59
Package Name: UDRP/PWD/02/03/RD/030b
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/03/RD/030b
Contractor Name: R. B. Construction
|
Start Date: 14-07-2015
Intended Completion Date: 25-04-2017
Original End Date: 13-10-2016
|
Total Bond Cost: 31427309.65 (314.27 lakhs)
Variation Cost: 371761.57 (3.72 lakhs) Hence Total Bond Cost is 31799071.22 (317.99 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 722844 for 46 days
LD Analysis for Milestone2: calculated LD is Rs 5028480 for 320 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.50 KM | 4.92 | 2.50 KM | 2.50 KM | 2.3 | 4.92 | 2. | R/Wall, B/ Wall Type Protection works | 589.00 m | 47.81 | 589.00 m | 589.00 m | 23.21 | 47.81 | 3. | GSB/RBI/G-1 | 3.50 KM | 21.35 | 3.50 KM | 3.50 KM | 10.22 | 21.35 | 4. | G-2 | 3.65 KM | 23.18 | 3.65 KM | 3.65 KM | 10.82 | 23.18 | 5. | G-3 | 3.65 KM | 22.69 | 3.65 KM | 3.65 KM | 10.9 | 22.69 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.65 KM | 42.25 | 3.55 KM | 3.55 KM | 20.29 | 42.25 | 7. | Cause Way | 0.00 No | 0.00 | 0.00 No | 0.00 No | 0 | 0.00 | 8. | Culverts/Scupper | 11.00 No | 29.17 | 11.00 No | 11.00 No | 13.13 | 29.17 | 9. | longitudinal Drain | 1500.00 m | 9.95 | 1500.00 m | 1500.00 m | 4.32 | 9.95 | 10. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 50.00 No | 10.44 | 50.00 No | 50.00 No | 4.53 | 10.44 | 12. | Road Furniture | 26.00 No | 0.62 | 26.00 No | 26.00 No | 0.27 | 0.62 |
Total Amount: |
212.38 |
|
100 |
212.38 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015
Updation of work program on:
23-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-October-2015 | 31.72 lakhs |
2. | 28-January-2016 | 31.04 lakhs |
3. | 30-March-2016 | 27.84 lakhs |
4. | 23-March-2017 | 61.44 lakhs |
5. | 31-March-2017 | 10.43 lakhs |
6. | 28-July-2017 | 64.39 lakhs |
7. | 19-December-2017 | 63.51 lakhs |
8. | 30-May-2018 | 27.62 lakhs |
Total |
317.99 lakhs |
% Payment |
100 % |
|
Advance Amount: 36.53 lakhs
Recovered Amount: 6.53 lakhs
Balance to be Recovered 30.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 118 |
Number of Notice(s) issued: 83 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-09-2017 | Km 1 | Checking of road width. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 03-06-2017 | ch.1+325 | PC thickness checking found 22 mm | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
3. | 03-06-2017 | Ch. 1+375 | PC work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
4. | 26-05-2017 | 0+600 | Rectification of catch water drain | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
5. | 23-05-2017 | Ch.0+725 | G-1 Rolling work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
6. | 23-05-2017 | Ch. 0+700 | G-1 Laying work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
7. | 13-05-2017 | Chainage 1+435 | Thickness checking of pc and seal coat by JE and AE WB PWD | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
8. | 12-05-2017 | Ch. 1+350 | WBM G-3 Laying work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
9. | 12-05-2017 | Ch. 1+400 | WBM G-3 Layer | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
10. | 10-05-2017 | Ch. 1+075 | Seal coat work compete | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
11. | 10-05-2017 | Ch.1+025 | Tack coat work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
12. | 09-05-2017 | Ch.0+325 | PC work rolling in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
13. | 08-05-2017 | 0.400 | PC Work is in progress thickness found 22 mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
14. | 08-05-2017 | 0.350 | Seal coat work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
15. | 04-05-2017 | Ch.0+925 | PC Rolling Work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
16. | 04-05-2017 | Ch.1+475 | WBM G-2 Laying work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
17. | 12-04-2017 | Ch.1.650 | Meeting with vilagers | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
18. | 28-03-2017 | Ch. 0+900 | KC type drain work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
19. | 08-03-2017 | Ch-1.475 | Thickness checking G1 G2 G3 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
20. | 08-03-2017 | Ch- 0.400 | Site visit | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|