UDRP/PWD/1/3/59/RD/006b
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
56 |
Package Name: |
UDRP/PWD/1/3/59/RD/006b |
Sanction Cost: |
323.36 lakhs |
District: |
Haridwar |
Block: |
Bhagwanpur |
Constituency: |
Bhagwanpur |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 1760 Hasanpur-Madanpur road (1.650 KM.) (completed) | 2 1782 Latifpur-Khubbanpur road (0.610 KM.) (completed) | 3 1818 Raipur link road (1.200 KM.) (completed) |
|
Procurement: |
Package No.: 56
Package Name: UDRP/PWD/1/3/59/RD/006b
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006b
Contractor Name: Link Enterprises
|
Start Date: 01-09-2014
Intended Completion Date: 31-12-2015
|
Total Bond Cost: 25287112.5 (252.87 lakhs)
Variation Cost: 4847628.80 (48.48 lakhs) Hence Total Bond Cost is 30134741.3 (301.35 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 986232 for 78 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.18 KM | 9.72 | 2.18 KM | 2.18 KM | 3.81 | 9.72 | 2. | R/Wall, B/ Wall Type Protection works | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 3. | GSB/RBI/G-1 | 1.72 KM | 25.38 | 1.72 KM | 1.72 KM | 9.94 | 25.38 | 4. | PC/CC i/c Prime Coat, Tack Coat | 2.52 KM | 252.60 | 2.52 KM | 2.52 KM | 84.98 | 252.60 | 5. | longitudinal Drain | 100.00 m | 3.49 | 100.00 m | 100.00 m | 1.07 | 3.49 | 6. | Road Furniture | 6.00 No | 0.49 | 6.00 No | 6.00 No | 0.2 | 0.49 | 7. | G-2 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 8. | G-3 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 |
Total Amount: |
291.68 |
|
100 |
291.68 |
|
Remarks:
No Remarks
Work Program Made On:
15-11-2014
Updation of work program on:
09-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-December-2014 | 21.30 lakhs |
2. | 23-April-2015 | 27.48 lakhs |
3. | 16-July-2015 | 40.96 lakhs |
4. | 22-September-2015 | 45.28 lakhs |
5. | 27-July-2016 | 21.73 lakhs |
6. | 11-August-2015 | 39.02 lakhs |
7. | 08-November-2016 | 5.16 lakhs |
8. | 30-May-2015 | 11.97 lakhs |
9. | 25-June-2015 | 34.55 lakhs |
10. | 30-September-2015 | 28.10 lakhs |
11. | 06-November-2015 | 12.16 lakhs |
12. | 22-December-2015 | 9.84 lakhs |
13. | 30-January-2016 | 6.76 lakhs |
14. | 06-November-2016 | -2.96 lakhs |
Total |
301.35 lakhs |
% Payment |
100 % |
|
Advance Amount: 25.28 lakhs
Recovered Amount: 25.28 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 17 |
Number of Notice(s) issued: 64 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-10-2016 | Ch 0/14-0/16 | Core cutting of raipur link road | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
2. | 04-10-2016 | Ch 0/7 | Inspection of raipur link road after completion | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
3. | 06-08-2015 | Ch. 0.370 | Expansion/ Construction joint in CC Road | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
4. | 21-07-2015 | Km1 hm1 | Camber checking | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
5. | 24-06-2015 | Ch. 0.300km | C. C pavement under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
6. | 12-06-2015 | Km1 near akona engineering Co. | Cc road under construction | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
7. | 31-05-2015 | Ch. - 0.850 | CC work in Raipur link Road at Roorkee, Bhagwanpur | D S Tomar | JE | DEA WB Chakrata | See Pic |
8. | 31-05-2015 | Ch 0.825 | C C in Raipur Link Road | D S Tomar | JE | DEA WB Chakrata | See Pic |
9. | 18-05-2015 | Km1 raipur link rd | DLC concrete under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 06-05-2015 | End of km 1 near unisef cable industry | Compaction of gsb | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
11. | 05-05-2015 | Ch 8.025 | GSB in Raipur M/R | D S Tomar | JE | DEA WB Chakrata | See Pic |
12. | 19-04-2015 | Km 1 hasanpur | Cc pavement complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
13. | 19-04-2015 | Km1 dense industrial area | Test conducted to find out the percentage of clay in Gsb. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 29-03-2015 | Km o.450 Raipur Rd industrial estate. | sprinkling of water for consolidation of GSB work | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 25-03-2015 | Km o.450 Raipur Rd industrial estate. | sprinkling of water for consolidation of GSB work | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
16. | 25-03-2015 | Km1 raipur | GSB in progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
17. | 05-11-2014 | Km 0.550 | Mss on kubbanpur rd | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|