Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/1/3/59/RD/006b Agreement signed
Project: UDRP-RB Package No.: 56 Package Name: UDRP/PWD/1/3/59/RD/006b Sanction Cost: 323.36  lakhs
District: Haridwar Block: Bhagwanpur Constituency: Bhagwanpur Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision No.of Sub project : 3
Subproject in this package
1  1760   Hasanpur-Madanpur road (1.650 KM.) (completed)
2  1782   Latifpur-Khubbanpur road (0.610 KM.) (completed)
3  1818   Raipur link road (1.200 KM.) (completed)
Procurement:
Package No.: 56        Package Name: UDRP/PWD/1/3/59/RD/006b        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/1/3/59/RD/006b        Contractor Name: Link Enterprises       
Start Date: 01-09-2014        Intended Completion Date: 31-12-2015       
Total Bond Cost: 25287112.5 (252.87 lakhs)        Variation Cost: 4847628.80 (48.48 lakhs)     Hence Total Bond Cost is   30134741.3 (301.35 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 986232 for 78 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.18 KM9.722.18 KM2.18 KM3.819.72
2.R/Wall, B/ Wall Type Protection works0.00 m0.000.00 m0.00 m00.00
3.GSB/RBI/G-11.72 KM25.381.72 KM1.72 KM9.9425.38
4.PC/CC i/c Prime Coat, Tack Coat2.52 KM252.602.52 KM2.52 KM84.98252.60
5.longitudinal Drain100.00 m3.49100.00 m100.00 m1.073.49
6.Road Furniture6.00 No0.496.00 No6.00 No0.20.49
7.G-20.00 KM0.000.00 KM0.00 KM00.00
8.G-30.00 KM0.000.00 KM0.00 KM00.00
Total Amount: 291.68 100   291.68
Remarks: No Remarks       Work Program Made On: 15-11-2014       Updation of work program on: 09-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-December-201421.30  lakhs
2.23-April-201527.48  lakhs
3.16-July-201540.96  lakhs
4.22-September-201545.28  lakhs
5.27-July-201621.73  lakhs
6.11-August-201539.02  lakhs
7.08-November-20165.16  lakhs
8.30-May-201511.97  lakhs
9.25-June-201534.55  lakhs
10.30-September-201528.10  lakhs
11.06-November-201512.16  lakhs
12.22-December-20159.84  lakhs
13.30-January-20166.76  lakhs
14.06-November-2016-2.96  lakhs
Total 301.35  lakhs
% Payment 100 %
Advance Amount:  25.28  lakhs        Recovered Amount:  25.28  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 273     No. of Test Done : 274      No. of Test Passed : 273      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 17
Number of Notice(s) issued: 64

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-10-2016Ch 0/14-0/16Core cutting of raipur link roadDhwajvir SinghJEUDRP R&B Chakrata See Pic
2.04-10-2016Ch 0/7Inspection of raipur link road after completionDhwajvir SinghJEUDRP R&B Chakrata See Pic
3.06-08-2015Ch. 0.370Expansion/ Construction joint in CC RoadDhwajvir SinghJEUDRP R&B Chakrata See Pic
4.21-07-2015Km1 hm1Camber checkingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
5.24-06-2015Ch. 0.300kmC. C pavement under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
6.12-06-2015Km1 near akona engineering Co.Cc road under constructionLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.31-05-2015Ch. - 0.850CC work in Raipur link Road at Roorkee, BhagwanpurD S TomarJEDEA WB Chakrata See Pic
8.31-05-2015Ch 0.825C C in Raipur Link RoadD S TomarJEDEA WB Chakrata See Pic
9.18-05-2015Km1 raipur link rdDLC concrete under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.06-05-2015End of km 1 near unisef cable industryCompaction of gsbLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.05-05-2015Ch 8.025GSB in Raipur M/RD S TomarJEDEA WB Chakrata See Pic
12.19-04-2015Km 1 hasanpurCc pavement completeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
13.19-04-2015Km1 dense industrial areaTest conducted to find out the percentage of clay in Gsb.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.29-03-2015Km o.450 Raipur Rd industrial estate.sprinkling of water for consolidation of GSB workLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
15.25-03-2015Km o.450 Raipur Rd industrial estate.sprinkling of water for consolidation of GSB workLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
16.25-03-2015Km1 raipurGSB in progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
17.05-11-2014Km 0.550Mss on kubbanpur rdLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic