UDRP/PWD/10/12/RD/053
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
53 |
Package Name: |
UDRP/PWD/10/12/RD/053 |
Sanction Cost: |
271.08 lakhs |
District: |
Nainital |
Block: |
Ramgarh |
Constituency: |
Bhimtal |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Nanital |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2039 Talla Ramgarh Ratighat MR (8.000 KM.) (completed) |
|
Procurement: |
Package No.: 53
Package Name: UDRP/PWD/10/12/RD/053
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 21-05-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/10/12/RD/053
Contractor Name: Jeena Enterprises
|
Start Date: 27-05-2015
Intended Completion Date: 26-08-2016
|
Total Bond Cost: 18257078.51 (182.57 lakhs)
Variation Cost: 6881701.48 (68.82 lakhs) Hence Total Bond Cost is 25138779.99 (251.39 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.23 KM | 5.09 | 0.23 KM | 0.23 KM | 2.03 | 5.09 | 2. | R/Wall, B/ Wall Type Protection works | 797.00 m | 87.98 | 797.00 m | 797.00 m | 35 | 87.98 | 3. | GSB/RBI/G-1 | 0.53 KM | 4.06 | 0.53 KM | 0.53 KM | 1.61 | 4.06 | 4. | G-2 | 0.53 KM | 3.02 | 0.53 KM | 0.53 KM | 1.2 | 3.02 | 5. | G-3 | 1.14 KM | 6.86 | 1.14 KM | 1.14 KM | 2.73 | 6.86 | 6. | PC/CC i/c Prime Coat, Tack Coat | 8.00 KM | 94.18 | 8.00 KM | 8.00 KM | 37.46 | 94.18 | 7. | Cause Way | 3.00 No | 3.25 | 3.00 No | 3.00 No | 1.29 | 3.25 | 8. | longitudinal Drain | 8000.00 m | 21.07 | 8000.00 m | 8000.00 m | 8.38 | 21.07 | 9. | Crash Barrier | 400.00 m | 9.72 | 400.00 m | 400.00 m | 3.87 | 9.72 | 10. | Parapet | 500.00 No | 10.11 | 500.00 No | 500.00 No | 4.02 | 10.11 | 11. | Road Furniture | 63.00 No | 1.02 | 63.00 No | 63.00 No | 0.41 | 1.02 | 12. | Other Allied Works & Finishing Work | 4.00 Job | 5.02 | 4.00 Job | 4.00 Job | 2 | 5.02 |
Total Amount: |
251.38 |
|
100 |
251.38 |
|
Remarks:
No Remarks
Work Program Made On:
08-10-2015
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-July-2015 | 8.46 lakhs |
2. | 05-August-2015 | 16.25 lakhs |
3. | 31-August-2015 | 9.28 lakhs |
4. | 30-September-2015 | 40.31 lakhs |
5. | 01-October-2015 | 11.09 lakhs |
6. | 07-November-2015 | 29.37 lakhs |
7. | 30-November-2015 | 4.92 lakhs |
8. | 31-December-2015 | 4.44 lakhs |
9. | 30-January-2016 | 2.66 lakhs |
10. | 29-February-2016 | 2.13 lakhs |
11. | 31-March-2016 | 3.02 lakhs |
12. | 22-April-2016 | 6.27 lakhs |
13. | 11-May-2016 | 16.06 lakhs |
14. | 31-May-2016 | 29.14 lakhs |
15. | 24-June-2016 | 29.35 lakhs |
16. | 29-August-2016 | 4.71 lakhs |
17. | 25-October-2016 | 32.53 lakhs |
Total |
249.99 lakhs |
% Payment |
99.44 % |
|
Advance Amount: 18.25 lakhs
Recovered Amount: 18.25 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 63 |
Number of Notice(s) issued: 80 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-05-2016 | 8+000 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
2. | 21-05-2016 | 2+500 | Debris Disposal | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
3. | 21-05-2016 | 2+650 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
4. | 21-05-2016 | 2+500 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
5. | 21-05-2016 | 0+000 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
6. | 04-05-2016 | 2+300 | Hill cuttingr | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
7. | 30-04-2016 | 2+300 | Hill cutting | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
8. | 13-04-2016 | 2+600 | Profile correction by wbm | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
9. | 14-03-2016 | 6+500 | Land slide clearance | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
10. | 14-03-2016 | 6+500 | Land slide | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
11. | 02-03-2016 | Ch 3+100 | Topo survey | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
12. | 29-02-2016 | 0+725 | Topo survey | Naseem Ansari | Site Supervisor | DSC5 R&B WB Nainital | See Pic |
13. | 29-02-2016 | 0+200 | Topo survey | Naseem Ansari | Site Supervisor | DSC5 R&B WB Nainital | See Pic |
14. | 26-02-2016 | 3+100 | Top pucca of. B/w | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
15. | 26-02-2016 | 2+300 | E.e& to site visit | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
16. | 26-02-2016 | 1+650 | Putcca drain | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
17. | 08-02-2016 | 5+080 | C/P | Naseem Ansari | Site Supervisor | DSC5 R&B WB Nainital | See Pic |
18. | 08-02-2016 | 2+200 | Transit walk for variation | Naseem Ansari | Site Supervisor | DSC5 R&B WB Nainital | See Pic |
19. | 24-12-2015 | 0+600 | Causeway | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
20. | 04-11-2015 | 2+800 | K.C Drain | Akash Choudhary | JE | UDRP R&B Nainital | See Pic |
|
|