Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/BR/05(N) Agreement signed
Project: UDRP-RB Package No.: 528 Package Name: UDRP/PWD/BR/05(N) Sanction Cost: 685.44  lakhs
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design No.of Sub project : 1
Subproject in this package
1  4005   Ratura Suspension Bridge (80.000 M.) (completed)
Procurement:
Package No.: 528        Package Name: UDRP/PWD/BR/05(N)        Tender Date: 03-08-2018        Current Status: Agreement signed        Achieved on Date: 22-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/BR/05(N)        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 30-10-2018        Intended Completion Date: 29-06-2019       
Total Bond Cost: 39317818.74 (393.18 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job34.291.00 Job1.00 Job8.7234.29
2.Abutment Superstructure LHS1.00 Job16.301.00 Job1.00 Job4.1516.30
3.Trestle Erection and Bracing of Trestle Tower LHS 1.00 job8.001.00 job1.00 job2.048.00
4.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job246.431.00 job1.00 job62.68246.43
5.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no1.002.00 no2.00 no0.251.00
6.Fixing of Saddle pulley along with Rib plate and 4.00 no6.544.00 no4.00 no1.666.54
7.Main Cable Laying and Stretching 6.00 no3.006.00 no6.00 no0.763.00
8.Fixing Suspenders to Main cable with clamps and Ha160.00 no10.00160.00 no160.00 no2.5410.00
9.Fixing of chequered Plate/RCC Deck200.00 sqm43.12200.00 sqm200.00 sqm10.9743.12
10.Approach Ramp /path 480.00 m13.47480.00 m480.00 m3.4313.47
11.Protection Work1.00 Job11.031.00 Job1.00 Job2.8111.03
Total Amount: 393.18 100   393.18
Remarks: No Remarks       Work Program Made On: 20-11-2018       Updation of work program on: 30-05-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-December-201812.33  lakhs
2.22-February-201962.81  lakhs
3.30-March-201999.04  lakhs
4.31-May-201957.42  lakhs
5.19-June-201925.43  lakhs
6.30-June-201948.03  lakhs
7.18-July-20199.95  lakhs
8.28-August-201930.74  lakhs
9.16-October-201917.06  lakhs
Total 362.81  lakhs
% Payment 92.28 %
Advance Amount:  35.77  lakhs        Recovered Amount:  35.77  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 164     No. of Test Done : 164      No. of Test Passed : 164      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 166
Number of Notice(s) issued: 3

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-05-2019A1 sideSite visit of MR. Mark, Mr. Harish sir, SE, EE, AEVineet KumarJEUDRP R&B Guptkashi See Pic
2.30-05-2019A1 sideSite visit of world bankVineet KumarJEUDRP R&B Guptkashi See Pic
3.30-05-2019Road sideDeck plate and channel arrived at siteVineet KumarJEUDRP R&B Guptkashi See Pic
4.30-05-2019Site lab7 days cube testingVineet KumarJEUDRP R&B Guptkashi See Pic
5.03-05-2019A2 sideAwerness program of the occasion of Labour Day distribution of fruitsVineet KumarJEUDRP R&B Guptkashi See Pic
6.03-05-2019A2 side anchorcum towerA2 side anchorcum tower casting work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
7.03-05-2019A1 side towerA1 side tower erection startVineet KumarJEUDRP R&B Guptkashi See Pic
8.27-04-2019A2 side anchorcum towerA2 side anchorcum tower castingVineet KumarJEUDRP R&B Guptkashi See Pic
9.27-04-2019A2 side anchorcum tower wall castingA2 side anchorcum tower casting work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
10.04-04-2019Site labCube testing checking by CE and SE sirVineet KumarJEUDRP R&B Guptkashi See Pic
11.04-04-2019A1 sideA1 abutmentVineet KumarJEUDRP R&B Guptkashi See Pic
12.04-04-2019Site labCE and SE sir site visit lab register checkingVineet KumarJEUDRP R&B Guptkashi See Pic
13.02-04-2019Site officeSite visit SE, EE and AEVineet KumarJEUDRP R&B Guptkashi See Pic
14.29-03-2019Site labSite lab documents check by AE memVineet KumarJEUDRP R&B Guptkashi See Pic
15.29-03-2019A1 sideSteel checking by AE memVineet KumarJEUDRP R&B Guptkashi See Pic
16.29-03-2019A1 sideSteel wire mesh checking of abutment under base plateVineet KumarJEUDRP R&B Guptkashi See Pic
17.26-02-2019Site labSite lab cube testing in presence of SE sir during visitVineet KumarJEUDRP R&B Guptkashi See Pic
18.26-02-2019A1 sideUtility trolley shifting A1 side anchor block cadtingVineet KumarJEUDRP R&B Guptkashi See Pic
19.26-02-2019Sure labSite lab record checking by SE sir site visitVineet KumarJEUDRP R&B Guptkashi See Pic
20.17-01-2019Site labCube testing 7 days result passVineet KumarJEUDRP R&B Guptkashi See Pic