UDRP/PWD/02/08/BR/19a Agreement signed
Project: UDRP-RB Package No.: 526 Package Name: UDRP/PWD/02/08/BR/19a Sanction Cost: 710.97  lakhs
District: Chamoli Block: Joshimath Constituency: Badrinath Circle:
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined No.of Sub project : 1
Subproject in this package
1  4013   Bridge at Kalpeshwar on Helang-Urgam-Kalkeshuar Bridle Road (80.000 M.) (completed)
Procurement:
Package No.: 526        Package Name: UDRP/PWD/02/08/BR/19a        Tender Date: 15-12-2015        Current Status: Agreement signed        Achieved on Date: 17-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/BR/19a        Contractor Name: Ram Kumar Contractor       
Start Date: 25-03-2016        Intended Completion Date: 30-07-2018        Original End Date:  24-06-2017
Total Bond Cost: 57143358 (571.43 lakhs)        Variation Cost: 12345810.62 (123.46 lakhs)     Hence Total Bond Cost is   69489168.62 (694.89 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4342944 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 8714460 for 305 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Foundation RHS1.00 Job19.931.00 Job1.00 Job3.7419.93
2.Foundation LHS1.00 Job12.241.00 Job1.00 Job2.312.24
3.Abutment Superstructure RHS1.00 Job221.251.00 Job1.00 Job41.51221.25
4.Abutment Superstructure LHS1.00 Job58.551.00 Job1.00 Job10.9958.55
5.Trestle Erection and Bracing of Trestle Tower LHS 4.00 job68.434.00 job4.00 job12.8468.43
6.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job56.051.00 job1.00 job10.5256.05
7.Anchor Block for Wind Cable: Reinforcement, Lewis 2.00 job25.902.00 job2.00 job4.8625.90
8.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no13.722.00 no2.00 no2.5713.72
9.Fixing of Saddle pulley along with Rib plate and 4.00 no13.864.00 no4.00 no2.613.86
10.Main Cable Laying and Stretching 6.00 no30.966.00 no6.00 no5.8130.96
11.Fixing Suspenders to Main cable with clamps and Ha104.00 no12.08104.00 no104.00 no2.2712.08
Total Amount: 532.97 100   532.97
Remarks: No Remarks       Work Program Made On: 09-11-2016       Updation of work program on: 27-08-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-August-201612.35  lakhs
2.24-December-201628.74  lakhs
3.24-April-201739.68  lakhs
4.20-May-201744.15  lakhs
5.28-July-201728.94  lakhs
6.16-October-201727.20  lakhs
7.30-November-2017120.31  lakhs
8.31-January-201854.09  lakhs
9.26-March-201872.70  lakhs
10.28-April-201843.34  lakhs
11.30-May-201867.19  lakhs
12.02-July-201816.10  lakhs
13.13-August-201819.57  lakhs
14.30-August-201828.24  lakhs
15.29-September-201861.66  lakhs
16.20-February-201930.63  lakhs
Total 694.89  lakhs
% Payment 100 %
Advance Amount:  85.00  lakhs        Recovered Amount:  85.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 718     No. of Test Done : 815      No. of Test Passed : 796      No. of Test Failed : 19   Test report of this package
Number of Pics Available on Web Repository: 46
Number of Notice(s) issued: 60

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-12-20184+850Environment interview.Anurag DevJEUDRP R&B Guptkashi See Pic
2.15-06-2018Helang urgam kalpeshwar bridge A2 sideTower Ereaction work in progressVikash SinghJEUDRP R&B Gopeshwar See Pic
3.05-06-2018Helang urgam klpeshwar site labCompresive strength testVikash SinghJEUDRP R&B Gopeshwar See Pic
4.05-06-2018A1 side helang urgam bridge siteWind anchor M25 work progressVikash SinghJEUDRP R&B Gopeshwar See Pic
5.27-04-2018Helong urgam bridge 9017Checking of erection of Tower of Helong urgam bridge 9017Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
6.27-04-20189017 Helong urgam bridgeCube testing of Helong urgam bridge 9017Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
7.11-03-2018Helong urgam bridge 9017Abutment A2 side Gabion protection work in progressJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
8.11-03-2018Helong urgam bridge 9017Main anchor A2 Reinforcement and shuttering work above inspection gallery in progressJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
9.24-02-20189017 Helong urgam bridgeMain Anchor A2 side column section 2nd Lift concrete & PlumJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
10.03-02-2018Cube test result 17 daysUrgam BridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
11.03-02-2018Cube testUrgam Bridge test by EE sirSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
12.03-02-2018Aiv testUrgam BridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
13.03-02-2018Aiv testAiv test at urgam bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
14.03-02-2018Urgam bridgeFirst aid inspectionSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
15.03-02-2018Helong urgam BridgeSite lab and sefteySanjeev SinghAREDSC4 R&B WB Chamoli See Pic
16.03-02-2018Inspection of 9017Urgam BridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
17.20-01-2018Main Anchor A2 2nd slab concrete slump testing found 95mmAt urgam bridge siteVikash SinghJEUDRP R&B Gopeshwar See Pic
18.20-01-2018Gabion box protection work in progress (A2) Heong- urgamUrgam BridgeJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
19.30-10-2017Urgam kalpeshwar bridgeUrgam kalpeshwar bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
20.27-06-2017Abutment A2Column abutment A2Sanjeev SinghAREDSC4 R&B WB Chamoli See Pic