UDRP/PWD/02/08/BR/19a
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
526 |
Package Name: |
UDRP/PWD/02/08/BR/19a |
Sanction Cost: |
710.97 lakhs |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
No.of Sub project : |
1 |
Subproject in this package |
1 4013 Bridge at Kalpeshwar on Helang-Urgam-Kalkeshuar Bridle Road (80.000 M.) (completed) |
|
Procurement: |
Package No.: 526
Package Name: UDRP/PWD/02/08/BR/19a
Tender Date: 15-12-2015
Current Status: Agreement signed
Achieved on Date: 17-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/BR/19a
Contractor Name: Ram Kumar Contractor
|
Start Date: 25-03-2016
Intended Completion Date: 30-07-2018
Original End Date: 24-06-2017
|
Total Bond Cost: 57143358 (571.43 lakhs)
Variation Cost: 12345810.62 (123.46 lakhs) Hence Total Bond Cost is 69489168.62 (694.89 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4342944 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 8714460 for 305 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Foundation RHS | 1.00 Job | 19.93 | 1.00 Job | 1.00 Job | 3.74 | 19.93 | 2. | Foundation LHS | 1.00 Job | 12.24 | 1.00 Job | 1.00 Job | 2.3 | 12.24 | 3. | Abutment Superstructure RHS | 1.00 Job | 221.25 | 1.00 Job | 1.00 Job | 41.51 | 221.25 | 4. | Abutment Superstructure LHS | 1.00 Job | 58.55 | 1.00 Job | 1.00 Job | 10.99 | 58.55 | 5. | Trestle Erection and Bracing of Trestle Tower LHS | 4.00 job | 68.43 | 4.00 job | 4.00 job | 12.84 | 68.43 | 6. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 56.05 | 1.00 job | 1.00 job | 10.52 | 56.05 | 7. | Anchor Block for Wind Cable: Reinforcement, Lewis | 2.00 job | 25.90 | 2.00 job | 2.00 job | 4.86 | 25.90 | 8. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 13.72 | 2.00 no | 2.00 no | 2.57 | 13.72 | 9. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 13.86 | 4.00 no | 4.00 no | 2.6 | 13.86 | 10. | Main Cable Laying and Stretching | 6.00 no | 30.96 | 6.00 no | 6.00 no | 5.81 | 30.96 | 11. | Fixing Suspenders to Main cable with clamps and Ha | 104.00 no | 12.08 | 104.00 no | 104.00 no | 2.27 | 12.08 |
Total Amount: |
532.97 |
|
100 |
532.97 |
|
Remarks:
No Remarks
Work Program Made On:
09-11-2016
Updation of work program on:
27-08-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-August-2016 | 12.35 lakhs |
2. | 24-December-2016 | 28.74 lakhs |
3. | 24-April-2017 | 39.68 lakhs |
4. | 20-May-2017 | 44.15 lakhs |
5. | 28-July-2017 | 28.94 lakhs |
6. | 16-October-2017 | 27.20 lakhs |
7. | 30-November-2017 | 120.31 lakhs |
8. | 31-January-2018 | 54.09 lakhs |
9. | 26-March-2018 | 72.70 lakhs |
10. | 28-April-2018 | 43.34 lakhs |
11. | 30-May-2018 | 67.19 lakhs |
12. | 02-July-2018 | 16.10 lakhs |
13. | 13-August-2018 | 19.57 lakhs |
14. | 30-August-2018 | 28.24 lakhs |
15. | 29-September-2018 | 61.66 lakhs |
16. | 20-February-2019 | 30.63 lakhs |
Total |
694.89 lakhs |
% Payment |
100 % |
|
Advance Amount: 85.00 lakhs
Recovered Amount: 85.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 46 |
Number of Notice(s) issued: 60 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-12-2018 | 4+850 | Environment interview. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
2. | 15-06-2018 | Helang urgam kalpeshwar bridge A2 side | Tower Ereaction work in progress | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
3. | 05-06-2018 | Helang urgam klpeshwar site lab | Compresive strength test | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
4. | 05-06-2018 | A1 side helang urgam bridge site | Wind anchor M25 work progress | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
5. | 27-04-2018 | Helong urgam bridge 9017 | Checking of erection of Tower of Helong urgam bridge 9017 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
6. | 27-04-2018 | 9017 Helong urgam bridge | Cube testing of Helong urgam bridge 9017 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
7. | 11-03-2018 | Helong urgam bridge 9017 | Abutment A2 side Gabion protection work in progress | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
8. | 11-03-2018 | Helong urgam bridge 9017 | Main anchor A2 Reinforcement and shuttering work above inspection gallery in progress | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
9. | 24-02-2018 | 9017 Helong urgam bridge | Main Anchor A2 side column section 2nd Lift concrete & Plum | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
10. | 03-02-2018 | Cube test result 17 days | Urgam Bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
11. | 03-02-2018 | Cube test | Urgam Bridge test by EE sir | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
12. | 03-02-2018 | Aiv test | Urgam Bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
13. | 03-02-2018 | Aiv test | Aiv test at urgam bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
14. | 03-02-2018 | Urgam bridge | First aid inspection | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
15. | 03-02-2018 | Helong urgam Bridge | Site lab and seftey | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
16. | 03-02-2018 | Inspection of 9017 | Urgam Bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
17. | 20-01-2018 | Main Anchor A2 2nd slab concrete slump testing found 95mm | At urgam bridge site | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
18. | 20-01-2018 | Gabion box protection work in progress (A2) Heong- urgam | Urgam Bridge | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
19. | 30-10-2017 | Urgam kalpeshwar bridge | Urgam kalpeshwar bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
20. | 27-06-2017 | Abutment A2 | Column abutment A2 | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
|
|