Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/13/92/BR/26 Agreement signed
Project: UDRP-RB Package No.: 525 Package Name: UDRP/PWD/13/92/BR/26 Sanction Cost: 227.00  lakhs
District: Haridwar Block: Constituency: Circle:
DEA: DEA Chakrata DSC: Yongma Engineering Co. Ltd. DSC Scope: Only Supervision No.of Sub project : 1
Subproject in this package
1  4021   Box Type culvert near Garhmirpur (32.000 M.) (completed)
Procurement:
Package No.: 525        Package Name: UDRP/PWD/13/92/BR/26        Tender Date: 05-11-2015        Current Status: Agreement signed        Achieved on Date: 29-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/13/92/BR/26        Contractor Name: Anil Mehta       
Start Date: 07-03-2016        Intended Completion Date: 05-11-2016        Original End Date:  06-09-2016
Total Bond Cost: 18606615.54 (186.07 lakhs)        Variation Cost: 1617769.40 (16.18 lakhs)     Hence Total Bond Cost is   20224384.94 (202.24 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 148848 for 16 days        LD Analysis for Milestone2: calculated LD is Rs 139545 for 15 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job26.051.00 Job1.00 Job1426.05
2.Foundation RHS1.00 Job27.761.00 Job1.00 Job14.9227.76
3.Foundation LHS1.00 Job27.761.00 Job1.00 Job14.9227.76
4.Abutment Superstructure RHS1.00 Job11.851.00 Job1.00 Job6.3711.85
5.Abutment Superstructure LHS1.00 Job11.851.00 Job1.00 Job6.3711.85
6.Fixing of chequered Plate/RCC Deck252.45 sqm26.06252.45 sqm252.45 sqm14.0126.06
7.Steel Railing/crush barrier85.40 m4.4885.40 m85.40 m2.414.48
8.Approach Ramp /path 150.00 m18.17150.00 m150.00 m9.7718.17
9.Protection Work1.00 Job32.081.00 Job1.00 Job17.2432.08
Total Amount: 186.06 100   186.06
Remarks: Work complete.       Work Program Made On: 13-05-2016       Updation of work program on: 05-11-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-May-201628.06  lakhs
2.20-June-201629.88  lakhs
3.13-July-201625.79  lakhs
4.30-August-201649.37  lakhs
5.24-September-201618.38  lakhs
6.17-November-201613.70  lakhs
7.16-January-201711.61  lakhs
8.25-March-201724.32  lakhs
9.06-June-20171.00  lakhs
Total 202.11  lakhs
% Payment 99.93 %
Advance Amount:  18.61  lakhs        Recovered Amount:  18.61  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 374     No. of Test Done : 388      No. of Test Passed : 387      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 87
Number of Notice(s) issued: 41

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Garhmeerpur Bridge HaridwarSite inspection World Bank Team, CE Sir,EE sirSudhir Kumar ` ` See Pic
2.06-04-2022Garhmeerpur bridge HaridwarWorld Bank Team visitSudhir Kumar ` ` See Pic
3.21-03-20180.00Site inspection by CE Sir, SE Sir, EE Mam WB PWD Tehri n TL SirSudhir Kumar AEAEUDRP R&B Tehri See Pic
4.20-12-20170.00Joint inspection with AAE PWD HaridwarSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.06-06-2017At Garhmirpur Bridge SiteInspection of bridge by CE, DPM with WB Did.PWD chakrata and BSC-1Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
6.23-05-2017Main bridge with approach.Inspection of bridge while liability period.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.23-05-2017Main bridgeSite visit by WB teamLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.03-03-2017Main part of the BridgeExcavation and dewatering Under progress.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
9.27-01-2017At Garhmirpur approachChecking of Bridge work after rain with AE sirRajan NautiyalJEUDRP R&B Chakrata See Pic
10.25-11-2016Main bridgeApproach road and all other works complete.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.16-11-2016At gadhmirpur box culvertTechnical information Board at pkg BR/26 Box culvert GadhmirpurAshish KaluraAEUDRP R&B Chakrata See Pic
12.14-11-2016At Approach towards AurangabaadApproach protection work with parapet whitewashing completeRajan NautiyalJEUDRP R&B Chakrata See Pic
13.14-11-2016At Aurangabaad aproachInformation board and parapet whitewashing completeRajan NautiyalJEUDRP R&B Chakrata See Pic
14.14-11-2016At Box culvert towards AurangabaadApproach slab and Crush barrier painting completeRajan NautiyalJEUDRP R&B Chakrata See Pic
15.14-11-2016At Garhmirpur approachParapet whitewashing completeRajan NautiyalJEUDRP R&B Chakrata See Pic
16.22-10-2016D/s side of Box culvert gadhmirpurPlum work in progress at box culvert gadhmirpurAshish KaluraAEUDRP R&B Chakrata See Pic
17.22-10-2016Plum concrete in approach Towards Aurangabaad D/s sidePlum concrete work in approach work D/s side balance portionRajan NautiyalJEUDRP R&B Chakrata See Pic
18.22-10-2016Approach slab towards GarhmirpurApproach slab castingRajan NautiyalJEUDRP R&B Chakrata See Pic
19.22-10-2016At Approach towards GarhmirpurWMM work in progress some correction requiredRajan NautiyalJEUDRP R&B Chakrata See Pic
20.17-10-2016At Garhmirpur approach U/sPlum concrete at Corner to protect approachRajan NautiyalJEUDRP R&B Chakrata See Pic