Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/50/BR/24 Agreement signed
Project: UDRP-RB Package No.: 524 Package Name: UDRP/PWD/07/50/BR/24 Sanction Cost: 406.44  lakhs
District: Pithoragarh Block: Dharchula Constituency: Dharchula Circle:
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Only Supervision No.of Sub project : 1
Subproject in this package
1  4025   Bridge over Ailgad river at Lithingkot (60.000 M.) (completed)
Procurement:
Package No.: 524        Package Name: UDRP/PWD/07/50/BR/24        Tender Date: 18-12-2015        Current Status: Agreement signed        Achieved on Date: 29-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/50/BR/24        Contractor Name: Z H Industries Pvt. Ltd.       
Start Date: 06-05-2016        Intended Completion Date: 11-05-2019        Original End Date:  05-02-2017
Total Bond Cost: 31770495.27 (317.7 lakhs)        Variation Cost: 6572725.76 (65.73 lakhs)     Hence Total Bond Cost is   38343221.03 (383.43 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2716335 for 171 days        LD Analysis for Milestone2: calculated LD is Rs 8736750 for 550 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job4.391.00 Job1.00 Job1.144.39
2.Foundation RHS1.00 Job1.861.00 Job1.00 Job0.481.86
3.Foundation LHS1.00 Job1.911.00 Job1.00 Job0.51.91
4.Abutment Superstructure RHS1.00 Job23.221.00 Job1.00 Job6.0523.22
5.Abutment Superstructure LHS1.00 Job23.221.00 Job1.00 Job6.0523.22
6.Fixing of chequered Plate/RCC Deck250.95 sqm16.86250.95 sqm250.95 sqm4.3916.86
7.Steel Railing/crush barrier143.60 m2.22143.60 m143.60 m0.582.22
8.Approach Ramp /path 2850.00 m102.442850.00 m2850.00 m26.71102.44
9.Protection Work1.00 Job25.841.00 Job1.00 Job6.7425.84
10.Errection Work1.00 Job181.661.00 Job1.00 Job47.36181.66
Total Amount: 383.62 100   383.62
Remarks: No Remarks       Work Program Made On: 24-08-2016       Updation of work program on: 07-03-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-July-2017108.92  lakhs
2.10-November-201716.55  lakhs
3.16-February-201813.77  lakhs
4.28-March-20188.50  lakhs
5.01-May-20185.42  lakhs
6.23-May-201815.75  lakhs
7.31-May-20188.96  lakhs
8.17-July-20184.63  lakhs
9.28-August-201819.14  lakhs
10.25-September-201831.47  lakhs
11.31-December-20184.65  lakhs
12.30-March-201924.09  lakhs
13.30-April-201972.33  lakhs
14.07-June-201926.61  lakhs
15.18-June-201915.00  lakhs
16.25-June-201921.44  lakhs
Total 397.23  lakhs
% Payment 103.6 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 278     No. of Test Done : 279      No. of Test Passed : 278      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 66
Number of Notice(s) issued: 82

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-05-2019Bro 24 starting point of approach roadPost construction water sampleVinodunknownunknown See Pic
2.16-05-2019Br 24Post construction soil samplingVinodunknownunknown See Pic
3.16-05-2019Br 24Post construction air quality monitoringVinodunknownunknown See Pic
4.16-05-2019Br 24Post construction noise quality monitoringVinodunknownunknown See Pic
5.01-12-2018Bridge siteChief Engineer UDRP visit.Arun Kumar PandeyEEUDRP R&B Askot See Pic
6.26-10-2018Bridge ErectionErection of bridge is going on.Arun Kumar PandeyEEUDRP R&B Askot See Pic
7.09-08-2018Ch 1+250Slip cleareance in approach road or BR 24Vinod Prakash SinghJEUDRP R&B Askot See Pic
8.19-07-2018Bridge site.Starting field erection/launching activity.Arun Kumar PandeyEEUDRP R&B Askot See Pic
9.09-05-2018LHS side abutment foundation for lithingkot bridge over the ailagadh river in pithoragadh district.Inspection during concreting for LHS foundation of lithingkot bridge over the ailagadh river in pithoragadh district.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
10.09-05-2018Lithingkot bridge over the ailagadh river in pithoragadh district.Current status of the RHS abutment for lithingkot bridge over the ailagadh river in pithoragadh district.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
11.09-05-2018Lithingkot bridge.Current status of approach road for lithingkot bridge over the ailagadh river.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
12.01-05-2018Sampling of HSFG ?? Bolt and but from menufactrors factory at ludiyana.Sampling of HSFG ?? Bolt and nut from menufactrors for third party testing from shriram institute for industrial research New Delhi.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
13.20-03-2018Lithingkote bridge siteSite visit of Mr Rajesh Pant CME along with DEA and BSC.Arun Kumar PandeyEEUDRP R&B Askot See Pic
14.04-03-2018Approch road of the lithingkot bridge over the ailagadh river in pithoragadh district.Current status of approach road for the lithingkot bridge over the ailagadh river in pithoragadh district.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
15.04-03-2018Foundation of LHS of the lithingkot bridge over the ailagadh river in pithoragadh district.Current status of the foundation LHS of the lithingkot bridge over the ailagadh river in pithoragadh district.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
16.04-03-2018RHS foundation of lithingkot bridge over the ailagadh river in pithoragadh district.Current status of the abutment , RHS of the lithingkot bridge over the ailagadh river in pithoragadh district.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
17.04-03-2018Field laboratory at Lithingkot bridge over the ailagadh river.Cube test witnessed and found satisfactory.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
18.16-02-2018Lithingkot bridge over the ailagadh river.Current status of foundation LHS side of A1foundation.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
19.16-02-2018Status of the approach road for lithingkot bridge.Current status of the approach road for lithingkot bridge over the ailagadh river in pithoragadh district.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic
20.05-02-2018FPIU, AskotMonthly Management Meeting at FPIU Askot for 70 Mtr steel truss bridge over the ailagadh river at lithingkot.Dhananjay Kumar SinghREBSC R&B WB Pithoragarh See Pic