UDRP/PWD/11/12/RD/052
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
52 |
Package Name: |
UDRP/PWD/11/12/RD/052 |
Sanction Cost: |
1623.64 lakhs |
District: |
Nainital |
Block: |
Dhari |
Constituency: |
Bhimtal |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Nanital |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2004 Padampuri Harakhan Kathgodam Motor Road (30.000 KM.) (completed) |
|
Procurement: |
Package No.: 52
Package Name: UDRP/PWD/11/12/RD/052
Tender Date: 19-04-2014
Current Status: Agreement signed
Achieved on Date: 13-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/11/12/RD/052
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 20-08-2014
Intended Completion Date: 25-05-2016
Original End Date: 19-11-2015
|
Total Bond Cost: 140446077 (1404.46 lakhs)
Variation Cost: 19504035.07 (195.04 lakhs) Hence Total Bond Cost is 159950112.07 (1599.5 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1685352 for 24 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.20 KM | 11.27 | 0.20 KM | 0.20 KM | 0.7 | 11.27 | 2. | R/Wall, B/ Wall Type Protection works | 7620.00 m | 407.97 | 7620.00 m | 7620.00 m | 25.51 | 407.97 | 3. | GSB/RBI/G-1 | 0.15 KM | 1.38 | 0.15 KM | 0.15 KM | 0.09 | 1.38 | 4. | G-2 | 1.80 KM | 9.80 | 1.80 KM | 1.80 KM | 0.61 | 9.80 | 5. | G-3 | 2.76 KM | 18.20 | 2.76 KM | 2.76 KM | 1.14 | 18.20 | 6. | BM i/c Prime Coat, Tack Coat | 6.80 KM | 186.46 | 6.80 KM | 6.80 KM | 11.66 | 186.46 | 7. | SDBC i/c Tackcoat | 27.50 KM | 476.18 | 27.50 KM | 27.50 KM | 29.77 | 476.18 | 8. | Cause Way | 8.00 No | 14.43 | 11.00 No | 11.00 No | 0.9 | 14.43 | 9. | Culverts/Scupper | 17.00 No | 170.82 | 17.00 No | 17.00 No | 10.68 | 170.82 | 10. | longitudinal Drain | 25760.00 m | 87.89 | 26500.00 m | 26500.00 m | 5.5 | 87.89 | 11. | Crash Barrier | 4000.00 m | 117.47 | 4000.00 m | 4000.00 m | 7.34 | 117.47 | 12. | Parapet | 3000.00 No | 69.31 | 3000.00 No | 3000.00 No | 4.33 | 69.31 | 13. | Road Furniture | 272.00 No | 11.61 | 272.00 No | 272.00 No | 0.73 | 11.61 | 14. | Other Allied Works & Finishing Work | 5.00 Job | 16.72 | 5.00 Job | 5.00 Job | 1.05 | 16.72 |
Total Amount: |
1599.51 |
|
100 |
1599.51 |
|
Remarks:
No Remarks
Work Program Made On:
09-10-2014
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 20.11 lakhs |
2. | 31-December-2014 | 45.80 lakhs |
3. | 27-February-2015 | 74.80 lakhs |
4. | 17-March-2015 | 55.32 lakhs |
5. | 28-March-2015 | 75.60 lakhs |
6. | 25-May-2015 | 36.83 lakhs |
7. | 08-June-2015 | 17.14 lakhs |
8. | 30-June-2015 | 107.73 lakhs |
9. | 07-August-2015 | 26.65 lakhs |
10. | 28-August-2015 | 44.80 lakhs |
11. | 29-September-2015 | 82.94 lakhs |
12. | 30-September-2015 | 214.80 lakhs |
13. | 01-October-2015 | 15.57 lakhs |
14. | 07-November-2015 | 123.61 lakhs |
15. | 30-November-2015 | 41.40 lakhs |
16. | 31-December-2015 | 27.62 lakhs |
17. | 30-January-2016 | 30.87 lakhs |
18. | 29-February-2016 | 23.90 lakhs |
19. | 18-March-2016 | 122.57 lakhs |
20. | 31-March-2016 | 101.15 lakhs |
21. | 10-May-2016 | 1.10 lakhs |
22. | 11-May-2016 | 172.37 lakhs |
23. | 03-August-2016 | 134.55 lakhs |
Total |
1597.23 lakhs |
% Payment |
99.86 % |
|
Advance Amount: 140.00 lakhs
Recovered Amount: 140.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 285 |
Number of Notice(s) issued: 107 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-05-2016 | 0+675 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
2. | 20-05-2016 | 0+500 | World bank visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
3. | 20-05-2016 | 8+500 | World Bank visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
4. | 20-05-2016 | 4+100 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
5. | 20-05-2016 | 3+580 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
6. | 20-05-2016 | 3+000 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
7. | 20-05-2016 | 0+000 | World Bank Visit | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
8. | 06-05-2016 | 2+580 | Kutcha drain Contraction & Patri Filling | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
9. | 06-05-2016 | 2+900 | Kutcha drain & Patri Filling | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
10. | 02-05-2016 | 21+500 | CE checked by Thickness SDBC | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
11. | 02-05-2016 | 24+180 | CE checked by Causway | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
12. | 02-05-2016 | 8+400 | CE checked by Culvert | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
13. | 02-05-2016 | 7+450 | CE checked by Patri Filling | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
14. | 02-05-2016 | 4+950 | CE checked Core cutting SDBc | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
15. | 02-05-2016 | 3+750 | CE inspection by Drain | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
16. | 02-05-2016 | 2+890 | CE suggest Parapet | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
17. | 02-05-2016 | 1+050 | CE & SE checked by Drain | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
18. | 02-05-2016 | 0+300 | CE Visit Parapet checking | Alok Singh Baghel | MIS Expert | DSC5 R&B WB | See Pic |
19. | 25-04-2016 | 11+400 | Core cutting of sdbc for density test | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
20. | 25-04-2016 | 11+300 | Core cutting of sdbc | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
|
|