Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/08/BR/19 Agreement signed
Project: UDRP-RB Package No.: 519 Package Name: UDRP/PWD/02/08/BR/19 Sanction Cost: 417.26  lakhs
District: Chamoli Block: Joshimath Constituency: Badrinath Circle:
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined No.of Sub project : 1
Subproject in this package
1  4014   Bridge over Benakuli river near Khiro (45.000 M.) (completed)
Procurement:
Package No.: 519        Package Name: UDRP/PWD/02/08/BR/19        Tender Date: 15-02-2016        Current Status: Agreement signed        Achieved on Date: 05-05-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/BR/19        Contractor Name: Triveni Construction Company       
Start Date: 12-05-2016        Intended Completion Date: 31-07-2018        Original End Date:  11-08-2017
Total Bond Cost: 37791414.82 (377.91 lakhs)        Variation Cost: -4692687.88 (-46.93 lakhs)     Hence Total Bond Cost is   33098726.94 (330.99 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2872192 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 6046720 for 320 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Crash Barrier143.60 m5.44143.60 m143.60 m1.425.44
2.Other Allied Works & Finishing Work 1.00 Job16.291.00 Job1.00 Job4.2516.29
3.Foundation RHS1.00 Job14.271.00 Job1.00 Job3.7214.27
4.Foundation LHS1.00 Job17.311.00 Job1.00 Job4.5217.31
5.Abutment Superstructure RHS1.00 Job16.311.00 Job1.00 Job4.2516.31
6.Abutment Superstructure LHS1.00 Job23.081.00 Job1.00 Job6.0223.08
7.Fixing of chequered Plate/RCC Deck227.50 sqm18.52227.50 sqm227.50 sqm4.8318.52
8.Steel Railing/crush barrier143.60 m5.44143.60 m143.60 m1.425.44
9.Approach Ramp /path 140.00 m20.41140.00 m140.00 m5.3320.41
10.Protection Work1.00 Job96.621.00 Job1.00 Job25.296.62
11.Errection Work1.00 Job149.671.00 Job1.00 Job39.04149.67
Total Amount: 383.36 100   383.36
Remarks: No Remarks       Work Program Made On: 24-08-2016       Updation of work program on: 05-09-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201710.22  lakhs
2.25-May-201731.64  lakhs
3.28-July-201716.35  lakhs
4.30-November-2017100.28  lakhs
5.17-February-201841.95  lakhs
6.26-March-201826.30  lakhs
7.30-May-201831.56  lakhs
8.13-August-201814.78  lakhs
9.30-August-201827.43  lakhs
10.20-October-201812.53  lakhs
11.31-December-201817.28  lakhs
Total 330.32  lakhs
% Payment 99.8 %
Advance Amount:  79.29  lakhs        Recovered Amount:  79.29  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 183     No. of Test Done : 218      No. of Test Passed : 214      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 65
Number of Notice(s) issued: 59

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-10-2018Ch/00Bridge protection work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
2.06-07-2018Benakuli bridgeErection work in progressVikash SinghJEUDRP R&B Gopeshwar See Pic
3.18-06-20189019 Benakuli bridgeErection work in progress at Benakuli bridge 9019Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
4.15-06-2018Benakuli bridge site A2 sidePavement Quality concrete work in progressVikash SinghJEUDRP R&B Gopeshwar See Pic
5.15-06-2018Benakuli bridge A2 side approach workPavement quality concrete workVikash SinghJEUDRP R&B Gopeshwar See Pic
6.05-06-2018Benakuli bridge siteTree plantation at benakuli bridge siteVikash SinghJEUDRP R&B Gopeshwar See Pic
7.05-06-2018Benakuli bridge siteTree Plantation at benakuli bridgeVikash SinghJEUDRP R&B Gopeshwar See Pic
8.05-06-2018Benakuli bridge siteErection work in progress at benakuli bridge siteVikash SinghJEUDRP R&B Gopeshwar See Pic
9.29-05-20189019 BenakuliVertical members erection in progress at Benakuli bridge 9019Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
10.29-05-20189019 BenakmuliVertical members erection in progress at BenamuliJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
11.18-04-2018Erection work in progress Benakuli bridge 9019Erection work in progress of Benakuli bridge 9019Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
12.19-03-2018Erection tower of 9019Benakuli bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
13.09-03-2018Benakuli bridge erection towerA1 side erection towerSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
14.21-02-20189019 Benakuli BridgeProtection work with Gabion box in progressJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
15.01-02-2018Abutment A1 pedestal lift castBenakuli bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
16.01-02-2018A2 side protection workBenakuli bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
17.01-02-2018Abutment A2 protection workBenakuli bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
18.01-02-2018Abutment A1 protection workBenakuli bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
19.20-01-2018A2 bridge sideGabion protection work at benakuli bridge A2 sideVikash SinghJEUDRP R&B Gopeshwar See Pic
20.20-01-2018A2 abutment protection workBenakuli bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic