UDRP/PWD/13/55/BR/17
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
517 |
Package Name: |
UDRP/PWD/13/55/BR/17 |
Sanction Cost: |
833.60 lakhs |
District: |
Haridwar |
Block: |
Laksar |
Constituency: |
Haridwar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 4017 Box culvert near bichpali in akuda khurd connecting akudha khurd to Ismailpur on Pathari river (30.000 M.) (completed) | 2 4018 2 Box culvert near village Sindhadu to connect Anthal Bujurg village on Pathri river (46.000 M.) (completed) | 3 4019 Box culvert near village Tingri on Pathari river in Vidhan Sabha Lakshar (50.000 M.) (completed) |
|
Procurement: |
Package No.: 517
Package Name: UDRP/PWD/13/55/BR/17
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 02-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/13/55/BR/17
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 09-02-2016
Intended Completion Date: 10-12-2017
Original End Date: 08-10-2016
|
Total Bond Cost: 66766672.78 (667.67 lakhs)
Variation Cost: 2955142.85 (29.55 lakhs) Hence Total Bond Cost is 69721815.63 (697.22 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days
LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Crash Barrier | 224.00 m | 19.12 | 108.80 m | 108.80 m | 2.87 | 19.12 | 2. | Other Allied Works & Finishing Work | 4.00 Job | 24.11 | 4.00 Job | 4.00 Job | 3.66 | 24.11 | 3. | Foundation RHS | 4.00 Job | 77.90 | 4.00 Job | 4.00 Job | 12.24 | 77.90 | 4. | Foundation LHS | 4.00 Job | 77.90 | 4.00 Job | 4.00 Job | 12.24 | 77.90 | 5. | Abutment Superstructure RHS | 4.00 Job | 81.93 | 4.00 Job | 4.00 Job | 12.8 | 81.93 | 6. | Abutment Superstructure LHS | 4.00 Job | 81.93 | 4.00 Job | 4.00 Job | 12.8 | 81.93 | 7. | Fixing of chequered Plate/RCC Deck | 838.96 sqm | 80.12 | 838.96 sqm | 838.96 sqm | 12.7 | 80.12 | 8. | Approach Ramp /path | 509.00 m | 87.66 | 611.00 m | 611.00 m | 13.88 | 87.66 | 9. | Protection Work | 4.00 Job | 102.84 | 4.00 Job | 4.00 Job | 16.81 | 102.84 |
Total Amount: |
633.51 |
|
100 |
633.51 |
|
Remarks:
No Remarks
Work Program Made On:
23-06-2016
Updation of work program on:
22-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-February-2017 | 116.04 lakhs |
2. | 25-March-2017 | 84.64 lakhs |
3. | 20-May-2017 | 55.35 lakhs |
4. | 13-June-2017 | 0.01 lakhs |
5. | 17-June-2017 | 103.45 lakhs |
6. | 31-July-2017 | 40.57 lakhs |
7. | 27-February-2018 | 26.53 lakhs |
8. | 30-May-2018 | 45.68 lakhs |
9. | 23-July-2016 | 40.68 lakhs |
10. | 27-September-2016 | 10.55 lakhs |
11. | 20-December-2016 | 81.70 lakhs |
12. | 31-January-2017 | 25.82 lakhs |
13. | 30-November-2018 | 0.38 lakhs |
Total |
631.4 lakhs |
% Payment |
90.56 % |
|
Advance Amount: 65.00 lakhs
Recovered Amount: 65.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 174 |
Number of Notice(s) issued: 70 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Tingri bridge Laksar | World Bank Team | Sudhir Kumar | ` | ` | See Pic |
2. | 06-04-2022 | Sindharu Laksar | World Bank Team | Sudhir Kumar | ` | ` | See Pic |
3. | 06-04-2022 | Sindhadu Laksar | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
4. | 06-04-2022 | Sidhadu bridge Laksar | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
5. | 17-05-2018 | 0.00 | Pkg BR 017 Sindhadu Box culvert No 2 work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
6. | 17-05-2018 | 0.0 | Pkg BR 017 Sindhdu box culvert No 2 work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
7. | 17-05-2018 | 0.00 | Pkg BR 017 Sidhadu box culvert No 2 work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
8. | 17-05-2018 | 0.00 | Pkg BR 017 Tigri box culvert work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
9. | 17-05-2018 | 0.00 | Pkg BR 017 | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
10. | 17-05-2018 | 0.00 | PKG BR 017 Tigri box culvert work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
11. | 17-05-2018 | 0.00 | BR017 Akoda Box Culvert work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
12. | 11-05-2018 | 0.00 | Joint inspection with AE PWD laksar n AE WB Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
13. | 11-05-2018 | 0.00 | BR 017 Akoda brg Work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
14. | 11-05-2018 | 0.00 | BR 017 Akoda Box culvert work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
15. | 11-05-2018 | 0.00 | Akoda brg Complete | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
16. | 17-04-2018 | 0.00 | Site inspection by CE Sir, SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
17. | 17-04-2018 | 0.000 | Joint inspection pkg BR 017 with Civil div Laksar | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
18. | 17-04-2018 | 0.00 | Joint inspection with Civil div | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
19. | 21-03-2018 | 0.00 | Site inspection by CE Sir, SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
20. | 21-03-2018 | 0.00 | Site inspection by CE Sir, SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
|
|