Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/13/55/BR/17 Agreement signed
Project: UDRP-RB Package No.: 517 Package Name: UDRP/PWD/13/55/BR/17 Sanction Cost: 833.60  lakhs
District: Haridwar Block: Laksar Constituency: Haridwar Circle:
DEA: DEA Tehri DSC: Yongma Engineering Co. Ltd. DSC Scope: Only Supervision No.of Sub project : 3
Subproject in this package
1  4017   Box culvert near bichpali in akuda khurd connecting akudha khurd to Ismailpur on Pathari river (30.000 M.) (completed)
2  4018   2 Box culvert near village Sindhadu to connect Anthal Bujurg village on Pathri river (46.000 M.) (completed)
3  4019   Box culvert near village Tingri on Pathari river in Vidhan Sabha Lakshar (50.000 M.) (completed)
Procurement:
Package No.: 517        Package Name: UDRP/PWD/13/55/BR/17        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/13/55/BR/17        Contractor Name: Shiv Shankar Construction Company       
Start Date: 09-02-2016        Intended Completion Date: 10-12-2017        Original End Date:  08-10-2016
Total Bond Cost: 66766672.78 (667.67 lakhs)        Variation Cost: 2955142.85 (29.55 lakhs)     Hence Total Bond Cost is   69721815.63 (697.22 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days        LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Crash Barrier224.00 m19.12108.80 m108.80 m2.8719.12
2.Other Allied Works & Finishing Work 4.00 Job24.114.00 Job4.00 Job3.6624.11
3.Foundation RHS4.00 Job77.904.00 Job4.00 Job12.2477.90
4.Foundation LHS4.00 Job77.904.00 Job4.00 Job12.2477.90
5.Abutment Superstructure RHS4.00 Job81.934.00 Job4.00 Job12.881.93
6.Abutment Superstructure LHS4.00 Job81.934.00 Job4.00 Job12.881.93
7.Fixing of chequered Plate/RCC Deck838.96 sqm80.12838.96 sqm838.96 sqm12.780.12
8.Approach Ramp /path 509.00 m87.66611.00 m611.00 m13.8887.66
9.Protection Work4.00 Job102.844.00 Job4.00 Job16.81102.84
Total Amount: 633.51 100   633.51
Remarks: No Remarks       Work Program Made On: 23-06-2016       Updation of work program on: 22-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-February-2017116.04  lakhs
2.25-March-201784.64  lakhs
3.20-May-201755.35  lakhs
4.13-June-20170.01  lakhs
5.17-June-2017103.45  lakhs
6.31-July-201740.57  lakhs
7.27-February-201826.53  lakhs
8.30-May-201845.68  lakhs
9.23-July-201640.68  lakhs
10.27-September-201610.55  lakhs
11.20-December-201681.70  lakhs
12.31-January-201725.82  lakhs
13.30-November-20180.38  lakhs
Total 631.4  lakhs
% Payment 90.56 %
Advance Amount:  65.00  lakhs        Recovered Amount:  65.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1834     No. of Test Done : 1845      No. of Test Passed : 1839      No. of Test Failed : 6   Test report of this package
Number of Pics Available on Web Repository: 174
Number of Notice(s) issued: 70

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Tingri bridge LaksarWorld Bank TeamSudhir Kumar ` ` See Pic
2.06-04-2022Sindharu LaksarWorld Bank TeamSudhir Kumar ` ` See Pic
3.06-04-2022Sindhadu LaksarWorld Bank Team visitSudhir Kumar ` ` See Pic
4.06-04-2022Sidhadu bridge LaksarWorld Bank Team visitSudhir Kumar ` ` See Pic
5.17-05-20180.00Pkg BR 017 Sindhadu Box culvert No 2 work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.17-05-20180.0Pkg BR 017 Sindhdu box culvert No 2 work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.17-05-20180.00Pkg BR 017 Sidhadu box culvert No 2 work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.17-05-20180.00Pkg BR 017 Tigri box culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.17-05-20180.00Pkg BR 017Sudhir Kumar AEAEUDRP R&B Tehri See Pic
10.17-05-20180.00PKG BR 017 Tigri box culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
11.17-05-20180.00BR017 Akoda Box Culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
12.11-05-20180.00Joint inspection with AE PWD laksar n AE WB TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
13.11-05-20180.00BR 017 Akoda brg Work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
14.11-05-20180.00BR 017 Akoda Box culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
15.11-05-20180.00Akoda brg CompleteSudhir Kumar AEAEUDRP R&B Tehri See Pic
16.17-04-20180.00Site inspection by CE Sir, SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
17.17-04-20180.000Joint inspection pkg BR 017 with Civil div LaksarSudhir Kumar AEAEUDRP R&B Tehri See Pic
18.17-04-20180.00Joint inspection with Civil divSudhir Kumar AEAEUDRP R&B Tehri See Pic
19.21-03-20180.00Site inspection by CE Sir, SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
20.21-03-20180.00Site inspection by CE Sir, SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic