Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/33/BR/016 Agreement signed
Project: UDRP-RB Package No.: 516 Package Name: UDRP/PWD/01/33/BR/016 Sanction Cost: 351.89  lakhs
District: Uttarkashi Block: Mori Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined No.of Sub project : 1
Subproject in this package
1  4016   Bridle Bridge over Power river at Block Mori Village Pandradhu to Duriyara (60.000 M.) (completed)
Procurement:
Package No.: 516        Package Name: UDRP/PWD/01/33/BR/016        Tender Date: 03-08-2015        Current Status: Agreement signed        Achieved on Date: 08-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/33/BR/016        Contractor Name: Tons Builderes       
Start Date: 15-03-2016        Intended Completion Date: 31-01-2018        Original End Date:  14-07-2017
Total Bond Cost: 24072575.5 (240.73 lakhs)        Variation Cost: 9067532.49 (90.68 lakhs)     Hence Total Bond Cost is   33140107.99 (331.4 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1107312 for +92 days        LD Analysis for Milestone2: calculated LD is Rs 1504500 for 125 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job9.281.00 Job1.00 Job3.869.28
2.Foundation RHS1.00 Job3.251.00 Job1.00 Job1.353.25
3.Foundation LHS1.00 Job3.501.00 Job1.00 Job1.453.50
4.Abutment Superstructure RHS1.00 Job7.031.00 Job1.00 Job2.927.03
5.Abutment Superstructure LHS1.00 Job9.261.00 Job1.00 Job3.859.26
6.Fixing of chequered Plate/RCC Deck148.25 sqm10.77148.25 sqm148.25 sqm4.4710.77
7.Steel Railing/crush barrier123.00 m3.84123.00 m123.00 m1.593.84
8.Approach Ramp /path 130.00 m72.44130.00 m130.00 m30.0972.44
9.Protection Work1.00 Job30.691.00 Job1.00 Job12.7530.69
10.Errection Work1.00 Job90.671.00 Job1.00 Job37.6790.67
Total Amount: 240.73 100   240.73
Remarks: No Remarks       Work Program Made On: 17-06-2016       Updation of work program on: 09-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-August-201622.89  lakhs
2.27-October-201620.41  lakhs
3.06-January-201769.64  lakhs
4.18-February-201729.59  lakhs
5.28-March-201730.61  lakhs
6.26-May-201751.02  lakhs
7.22-August-201720.14  lakhs
8.13-October-201720.41  lakhs
9.27-November-201730.61  lakhs
10.23-December-20170.03  lakhs
11.24-February-201831.15  lakhs
12.28-July-20183.61  lakhs
13.15-July-20196.49  lakhs
Total 336.6  lakhs
% Payment 101.57 %
Advance Amount:  66.33  lakhs        Recovered Amount:  66.33  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 160     No. of Test Done : 160      No. of Test Passed : 160      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 12
Number of Notice(s) issued: 62

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-02-2018PandranuC. E. Sir, S. E. Sir visited pandranu bridgeRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
2.15-12-2017Pandranu bridgePandranu site visitRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
3.08-02-2017Pandranu truss Bridge visit by Se sir and Ee sirErection work in progressGirish BobeQSBSC R&B WB Uttarkashi See Pic
4.08-02-2017Erection work in progress at Pandranu truss bridgeErection work in progressGirish BobeQSBSC R&B WB Uttarkashi See Pic
5.15-09-2016Pandranu bridgeM-30 R.c.c cap workPrateek TalwarJEUDRP R&B Uttarkashi See Pic
6.06-08-2016PandranuAbt A1 cap rebar completed ready to pour concrete.Sunil KumarREDSC1 R&B WB Uttarkashi See Pic
7.02-08-20160+060Raft concrete A1 AbutmentVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
8.25-06-20160.01Abutment A2 and abutment A1 steel bindingVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
9.25-06-20160.01Concrete in rafting A2Vipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
10.25-06-20160.1Setting layout for the construction of bridge at pandranuVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
11.20-06-20162nd lift concrete @ Abutment A2 Truss bridge PandhranuConcrete At abutment a2Girish BobeQSBSC R&B WB Uttarkashi See Pic
12.09-10-20150.0Site inspection pandranu bridgeVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic