UDRP/PWD/01/33/BR/016
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
516 |
Package Name: |
UDRP/PWD/01/33/BR/016 |
Sanction Cost: |
351.89 lakhs |
District: |
Uttarkashi |
Block: |
Mori |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
No.of Sub project : |
1 |
Subproject in this package |
1 4016 Bridle Bridge over Power river at Block Mori Village Pandradhu to Duriyara (60.000 M.) (completed) |
|
Procurement: |
Package No.: 516
Package Name: UDRP/PWD/01/33/BR/016
Tender Date: 03-08-2015
Current Status: Agreement signed
Achieved on Date: 08-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/33/BR/016
Contractor Name: Tons Builderes
|
Start Date: 15-03-2016
Intended Completion Date: 31-01-2018
Original End Date: 14-07-2017
|
Total Bond Cost: 24072575.5 (240.73 lakhs)
Variation Cost: 9067532.49 (90.68 lakhs) Hence Total Bond Cost is 33140107.99 (331.4 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1107312 for +92 days
LD Analysis for Milestone2: calculated LD is Rs 1504500 for 125 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 9.28 | 1.00 Job | 1.00 Job | 3.86 | 9.28 | 2. | Foundation RHS | 1.00 Job | 3.25 | 1.00 Job | 1.00 Job | 1.35 | 3.25 | 3. | Foundation LHS | 1.00 Job | 3.50 | 1.00 Job | 1.00 Job | 1.45 | 3.50 | 4. | Abutment Superstructure RHS | 1.00 Job | 7.03 | 1.00 Job | 1.00 Job | 2.92 | 7.03 | 5. | Abutment Superstructure LHS | 1.00 Job | 9.26 | 1.00 Job | 1.00 Job | 3.85 | 9.26 | 6. | Fixing of chequered Plate/RCC Deck | 148.25 sqm | 10.77 | 148.25 sqm | 148.25 sqm | 4.47 | 10.77 | 7. | Steel Railing/crush barrier | 123.00 m | 3.84 | 123.00 m | 123.00 m | 1.59 | 3.84 | 8. | Approach Ramp /path | 130.00 m | 72.44 | 130.00 m | 130.00 m | 30.09 | 72.44 | 9. | Protection Work | 1.00 Job | 30.69 | 1.00 Job | 1.00 Job | 12.75 | 30.69 | 10. | Errection Work | 1.00 Job | 90.67 | 1.00 Job | 1.00 Job | 37.67 | 90.67 |
Total Amount: |
240.73 |
|
100 |
240.73 |
|
Remarks:
No Remarks
Work Program Made On:
17-06-2016
Updation of work program on:
09-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-August-2016 | 22.89 lakhs |
2. | 27-October-2016 | 20.41 lakhs |
3. | 06-January-2017 | 69.64 lakhs |
4. | 18-February-2017 | 29.59 lakhs |
5. | 28-March-2017 | 30.61 lakhs |
6. | 26-May-2017 | 51.02 lakhs |
7. | 22-August-2017 | 20.14 lakhs |
8. | 13-October-2017 | 20.41 lakhs |
9. | 27-November-2017 | 30.61 lakhs |
10. | 23-December-2017 | 0.03 lakhs |
11. | 24-February-2018 | 31.15 lakhs |
12. | 28-July-2018 | 3.61 lakhs |
13. | 15-July-2019 | 6.49 lakhs |
Total |
336.6 lakhs |
% Payment |
101.57 % |
|
Advance Amount: 66.33 lakhs
Recovered Amount: 66.33 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 12 |
Number of Notice(s) issued: 62 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-02-2018 | Pandranu | C. E. Sir, S. E. Sir visited pandranu bridge | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
2. | 15-12-2017 | Pandranu bridge | Pandranu site visit | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
3. | 08-02-2017 | Pandranu truss Bridge visit by Se sir and Ee sir | Erection work in progress | Girish Bobe | QS | BSC R&B WB Uttarkashi | See Pic |
4. | 08-02-2017 | Erection work in progress at Pandranu truss bridge | Erection work in progress | Girish Bobe | QS | BSC R&B WB Uttarkashi | See Pic |
5. | 15-09-2016 | Pandranu bridge | M-30 R.c.c cap work | Prateek Talwar | JE | UDRP R&B Uttarkashi | See Pic |
6. | 06-08-2016 | Pandranu | Abt A1 cap rebar completed ready to pour concrete. | Sunil Kumar | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 02-08-2016 | 0+060 | Raft concrete A1 Abutment | Vipin Chandra Benjwal | AE | UDRP R&B Uttarkashi | See Pic |
8. | 25-06-2016 | 0.01 | Abutment A2 and abutment A1 steel binding | Vipin Chandra Benjwal | AE | UDRP R&B Uttarkashi | See Pic |
9. | 25-06-2016 | 0.01 | Concrete in rafting A2 | Vipin Chandra Benjwal | AE | UDRP R&B Uttarkashi | See Pic |
10. | 25-06-2016 | 0.1 | Setting layout for the construction of bridge at pandranu | Vipin Chandra Benjwal | AE | UDRP R&B Uttarkashi | See Pic |
11. | 20-06-2016 | 2nd lift concrete @ Abutment A2 Truss bridge Pandhranu | Concrete At abutment a2 | Girish Bobe | QS | BSC R&B WB Uttarkashi | See Pic |
12. | 09-10-2015 | 0.0 | Site inspection pandranu bridge | Vipin Chandra Benjwal | AE | UDRP R&B Uttarkashi | See Pic |
|
|