Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/08/BR/015 Agreement signed
Project: UDRP-RB Package No.: 515 Package Name: UDRP/PWD/02/08/BR/015 Sanction Cost: 766.01  lakhs
District: Chamoli Block: Ghat Constituency: Tharali Circle:
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined No.of Sub project : 1
Subproject in this package
1  4015   Bridge at Jokhna Laga Bura (70.000 M.) (completed)
Procurement:
Package No.: 515        Package Name: UDRP/PWD/02/08/BR/015        Tender Date: 03-08-2015        Current Status: Agreement signed        Achieved on Date: 23-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/BR/015        Contractor Name: M/S.KGL Infrastructure       
Start Date: 30-12-2015        Intended Completion Date: 28-01-2019        Original End Date:  29-03-2017
Total Bond Cost: 68383252 (683.83 lakhs)        Variation Cost: 879416.12 (8.79 lakhs)     Hence Total Bond Cost is   69262668.12 (692.63 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5162992 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 14497408 for 424 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job2.601.00 Job1.00 Job0.372.60
2.Other Allied Works & Finishing Work 1.00 Job15.571.00 Job1.00 Job2.1915.57
3.Foundation RHS1.00 Job49.141.00 Job1.00 Job6.9249.14
4.Foundation LHS1.00 Job49.141.00 Job1.00 Job6.9249.14
5.Abutment Superstructure RHS1.00 Job58.961.00 Job1.00 Job8.358.96
6.Abutment Superstructure LHS1.00 Job58.961.00 Job1.00 Job8.358.96
7.Trestle Erection and Bracing of Trestle Tower LHS 1.00 job40.801.00 job1.00 job5.7540.80
8.Anchor Block Main Cable Reinforcement (3-4 Times) 2.00 job176.892.00 job2.00 job24.91176.89
9.Anchor Block for Wind Cable: Reinforcement, Lewis 4.00 job98.274.00 job4.00 job13.8498.27
10.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no3.732.00 no2.00 no0.533.73
11.Fixing of Saddle pulley along with Rib plate and 4.00 no14.854.00 no4.00 no2.0914.85
12.Main Cable Laying and Stretching 6.00 no26.136.00 no6.00 no3.6826.13
13.Fixing Suspenders to Main cable with clamps and Ha102.00 no3.47102.00 no102.00 no0.493.47
14.Stretching Wind Guy cable, Fixing wind Ties with 52.00 m7.6852.00 m52.00 m1.087.68
15.Fixing longitudinal Stringers/girders80.00 m15.1380.00 m80.00 m2.1315.13
16.Fixing of chequered Plate/RCC Deck204.95 sqm10.55204.95 sqm204.95 sqm1.4910.55
17.Steel Railing/crush barrier172.00 m5.58172.00 m172.00 m0.795.58
18.Approach Ramp /path 100.00 m6.75100.00 m100.00 m0.956.75
19.Protection Work2.00 Job65.982.00 Job2.00 Job9.2965.98
Total Amount: 710.18 100   710.18
Remarks: No Remarks       Work Program Made On: 21-05-2016       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-March-201748.80  lakhs
2.25-May-201762.46  lakhs
3.24-June-201748.61  lakhs
4.08-August-201787.07  lakhs
5.13-October-201758.09  lakhs
6.24-November-201716.23  lakhs
7.29-December-201720.88  lakhs
8.31-January-201813.45  lakhs
9.28-February-201819.38  lakhs
10.28-March-201819.17  lakhs
11.31-May-201828.25  lakhs
12.09-August-201869.06  lakhs
13.31-October-201864.20  lakhs
14.29-November-201814.79  lakhs
15.31-December-20181.82  lakhs
16.15-February-201950.55  lakhs
17.28-February-201920.95  lakhs
18.30-March-201930.64  lakhs
19.30-April-201912.70  lakhs
20.11-June-20195.54  lakhs
21.12-June-201917.56  lakhs
Total 710.2  lakhs
% Payment 102.54 %
Advance Amount:  68.38  lakhs        Recovered Amount:  68.38  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1837     No. of Test Done : 1862      No. of Test Passed : 1837      No. of Test Failed : 25   Test report of this package
Number of Pics Available on Web Repository: 67
Number of Notice(s) issued: 78

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2019A1General inspection of Completed bridgeNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
2.17-11-2018A2Erection of bridge in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.15-10-2018A1 side wind GuyBinding of wind guy slab reinforcementDhwajvir SinghJEUDRP R&B Karnprayag See Pic
4.19-09-2018A1side wind anchorChecking of slump found satisfactoryDhwajvir SinghJEUDRP R&B Karnprayag See Pic
5.19-09-2018A1 side wind GuyCasting of wind anchor slab A1 sideDhwajvir SinghJEUDRP R&B Karnprayag See Pic
6.06-09-2018A1 side wind Guy u/sShuttering work of wind guy under progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic
7.06-09-2018A1 side Erection of tower under progress today stop due to rain.Erection of Tower under progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic
8.03-09-2018Jokhna Lagga Bura BridgeTower Erection A2 side is in progressCharu UpadhyayQSBSC R&B WB Chamoli See Pic
9.08-08-2018A1 side Tower ErectionTower Erection is under progress.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
10.02-08-2018Jokhna Lagga Bura BridgeErection of Tower A1 Abutment is in progress.Charu UpadhyayQSBSC R&B WB Chamoli See Pic
11.02-08-2018Jokhna Lagga Bura BridgeSE Rudrapryag and ExEn Sunil Kumar sir visitCharu UpadhyayQSBSC R&B WB Chamoli See Pic
12.01-08-2018A1 sideSite visit by SE R K Jain and EE Sunil Kumar Sir.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
13.01-08-2018A1 side at Jokhna Bridge siteSite visit by SE and EEDhwajvir SinghJEUDRP R&B Karnprayag See Pic
14.01-08-2018LHS wire crate protectionLaying of wire crate under progress satisfactorilyDhwajvir SinghJEUDRP R&B Karnprayag See Pic
15.01-08-2018A2 side Anchor BlockBinding of reinforcement of wind anchor under progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic
16.05-07-2018A1 side abutmentImportant Instruction given by EE at the time of visit.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
17.05-07-2018A1 side abutmentInstruction given by EE for aligning and fixing of Wire crateDhwajvir SinghJEUDRP R&B Karnprayag See Pic
18.05-07-2018A2 side abutmentChecking of reinforcement at level of 1752 m need to rectification.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
19.18-05-2018A1 side AbutmentBinding of reinforcement of abutment.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
20.18-05-2018A2 side RHS wind block at Jokhna LaggaShuttering work and binding of reinforcement satisfactorily in progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic