Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/40/BR/012 Agreement signed
Project: UDRP-RB Package No.: 512 Package Name: UDRP/PWD/03/40/BR/012 Sanction Cost: 238.00  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined No.of Sub project : 1
Subproject in this package
1  4012   Bridle Bridge at Terveni Sagam (45.000 M.) (completed)
Procurement:
Package No.: 512        Package Name: UDRP/PWD/03/40/BR/012        Tender Date: 09-04-2015        Current Status: Agreement signed        Achieved on Date: 04-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/BR/012        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 11-03-2016        Intended Completion Date: 28-02-2018        Original End Date:  10-12-2016
Total Bond Cost: 20671836 (206.72 lakhs)        Variation Cost: -2126844.37 (-21.27 lakhs)     Hence Total Bond Cost is   18544991.63 (185.45 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 950912 for +92 days        LD Analysis for Milestone2: calculated LD is Rs 4661536 for 451 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job0.031.00 Job1.00 Job0.010.03
2.Foundation RHS1.00 Job18.161.00 Job1.00 Job8.7818.16
3.Foundation LHS1.00 Job18.161.00 Job1.00 Job8.7818.16
4.Abutment Superstructure RHS1.00 Job19.861.00 Job1.00 Job9.6119.86
5.Abutment Superstructure LHS1.00 Job19.861.00 Job1.00 Job9.6119.86
6.Fixing of chequered Plate/RCC Deck112.00 sqm8.51112.00 sqm112.00 sqm4.128.51
7.Steel Railing/crush barrier93.20 m3.1293.20 m93.20 m1.513.12
8.Approach Ramp /path 728.00 m80.71728.00 m728.00 m39.0480.71
9.Errection Work1.00 Job38.301.00 Job1.00 Job18.5338.30
Total Amount: 206.71 100   206.71
Remarks: No Remarks       Work Program Made On: 19-11-2016       Updation of work program on: 29-12-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.21-January-201721.72  lakhs
2.30-March-201726.68  lakhs
3.13-October-201723.58  lakhs
4.30-November-201723.53  lakhs
5.22-December-201737.28  lakhs
6.23-March-201820.01  lakhs
7.29-May-201832.65  lakhs
Total 185.45  lakhs
% Payment 100 %
Advance Amount:  7.31  lakhs        Recovered Amount:  7.31  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 378     No. of Test Done : 380      No. of Test Passed : 377      No. of Test Failed : 3   Test report of this package
Number of Pics Available on Web Repository: 134
Number of Notice(s) issued: 75

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-12-2018Triveni sangam bridgeVisit by CE sir.Anurag DevJEUDRP R&B Guptkashi See Pic
2.11-07-2018A2 side middle bearing castingAnurag DevJEUDRP R&B Guptkashi See Pic
3.11-07-2018Bearing castingAnurag DevJEUDRP R&B Guptkashi See Pic
4.17-05-2018Triveni EE and CME visitTriveni sangamDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
5.17-05-2018Triveni EE and CMETriveniDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
6.17-05-2018Triveni visit EE and CMETriveni sangamDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
7.14-04-2018TriveniTriveniDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
8.14-04-2018Triveni sangamTriveni BridgeDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
9.07-04-2018Triveni sangamTriveni sangamDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
10.03-04-2018TriveniTriveniDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
11.03-04-2018SE sir visitTriveniDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
12.20-03-2018Casting of pedestal after fixing of bearingAnurag DevJEUDRP R&B Guptkashi See Pic
13.20-03-2018Checking pedestal steel and erection work by bridge engineer, EE, AE and RE.Anurag DevJEUDRP R&B Guptkashi See Pic
14.20-03-2018Checking bearing level .. Checked by bridge engineer, RE, AE, ARE.Anurag DevJEUDRP R&B Guptkashi See Pic
15.20-03-2018Site visit by DPM sir,EE sir,AE,REAnurag DevJEUDRP R&B Guptkashi See Pic
16.13-03-2018Triveni DPM sir visitTriveniDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
17.23-02-2018TriveniTriveniDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
18.20-02-2018Triveni Sangam Erection work in progressTriveni Sangam Erection work in progress Bottom cross and Stringer are completed Balance SWAY BracingSuresh PrasadREBSC R&B WB Rudraprayag See Pic
19.17-02-20189003Triveni Sangam Erection work in progress Site Visit By CME, EE, AE WITH RE AND ARESuresh PrasadREBSC R&B WB Rudraprayag See Pic
20.16-02-2018Triveni sangamVisit CME and EEDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic