UDRP/PWD/03/40/BR/012
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
512 |
Package Name: |
UDRP/PWD/03/40/BR/012 |
Sanction Cost: |
238.00 lakhs |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
No.of Sub project : |
1 |
Subproject in this package |
1 4012 Bridle Bridge at Terveni Sagam (45.000 M.) (completed) |
|
Procurement: |
Package No.: 512
Package Name: UDRP/PWD/03/40/BR/012
Tender Date: 09-04-2015
Current Status: Agreement signed
Achieved on Date: 04-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/BR/012
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 11-03-2016
Intended Completion Date: 28-02-2018
Original End Date: 10-12-2016
|
Total Bond Cost: 20671836 (206.72 lakhs)
Variation Cost: -2126844.37 (-21.27 lakhs) Hence Total Bond Cost is 18544991.63 (185.45 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 950912 for +92 days
LD Analysis for Milestone2: calculated LD is Rs 4661536 for 451 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 0.03 | 1.00 Job | 1.00 Job | 0.01 | 0.03 | 2. | Foundation RHS | 1.00 Job | 18.16 | 1.00 Job | 1.00 Job | 8.78 | 18.16 | 3. | Foundation LHS | 1.00 Job | 18.16 | 1.00 Job | 1.00 Job | 8.78 | 18.16 | 4. | Abutment Superstructure RHS | 1.00 Job | 19.86 | 1.00 Job | 1.00 Job | 9.61 | 19.86 | 5. | Abutment Superstructure LHS | 1.00 Job | 19.86 | 1.00 Job | 1.00 Job | 9.61 | 19.86 | 6. | Fixing of chequered Plate/RCC Deck | 112.00 sqm | 8.51 | 112.00 sqm | 112.00 sqm | 4.12 | 8.51 | 7. | Steel Railing/crush barrier | 93.20 m | 3.12 | 93.20 m | 93.20 m | 1.51 | 3.12 | 8. | Approach Ramp /path | 728.00 m | 80.71 | 728.00 m | 728.00 m | 39.04 | 80.71 | 9. | Errection Work | 1.00 Job | 38.30 | 1.00 Job | 1.00 Job | 18.53 | 38.30 |
Total Amount: |
206.71 |
|
100 |
206.71 |
|
Remarks:
No Remarks
Work Program Made On:
19-11-2016
Updation of work program on:
29-12-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 21-January-2017 | 21.72 lakhs |
2. | 30-March-2017 | 26.68 lakhs |
3. | 13-October-2017 | 23.58 lakhs |
4. | 30-November-2017 | 23.53 lakhs |
5. | 22-December-2017 | 37.28 lakhs |
6. | 23-March-2018 | 20.01 lakhs |
7. | 29-May-2018 | 32.65 lakhs |
Total |
185.45 lakhs |
% Payment |
100 % |
|
Advance Amount: 7.31 lakhs
Recovered Amount: 7.31 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 134 |
Number of Notice(s) issued: 75 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-12-2018 | Triveni sangam bridge | Visit by CE sir. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
2. | 11-07-2018 | | A2 side middle bearing casting | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
3. | 11-07-2018 | | Bearing casting | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
4. | 17-05-2018 | Triveni EE and CME visit | Triveni sangam | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
5. | 17-05-2018 | Triveni EE and CME | Triveni | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
6. | 17-05-2018 | Triveni visit EE and CME | Triveni sangam | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
7. | 14-04-2018 | Triveni | Triveni | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
8. | 14-04-2018 | Triveni sangam | Triveni Bridge | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
9. | 07-04-2018 | Triveni sangam | Triveni sangam | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
10. | 03-04-2018 | Triveni | Triveni | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
11. | 03-04-2018 | SE sir visit | Triveni | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
12. | 20-03-2018 | | Casting of pedestal after fixing of bearing | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
13. | 20-03-2018 | | Checking pedestal steel and erection work by bridge engineer, EE, AE and RE. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
14. | 20-03-2018 | | Checking bearing level .. Checked by bridge engineer, RE, AE, ARE. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
15. | 20-03-2018 | | Site visit by DPM sir,EE sir,AE,RE | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
16. | 13-03-2018 | Triveni DPM sir visit | Triveni | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
17. | 23-02-2018 | Triveni | Triveni | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
18. | 20-02-2018 | Triveni Sangam Erection work in progress | Triveni Sangam Erection work in progress Bottom cross and Stringer are completed Balance SWAY Bracing | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
19. | 17-02-2018 | 9003 | Triveni Sangam Erection work in progress Site Visit By CME, EE, AE WITH RE AND ARE | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
20. | 16-02-2018 | Triveni sangam | Visit CME and EE | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
|
|