Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/40/BR/010 Agreement signed
Project: UDRP-RB Package No.: 510 Package Name: UDRP/PWD/03/40/BR/010 Sanction Cost: 382.00  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined No.of Sub project : 1
Subproject in this package
1  4010   Bridge at Kotma Chilon Bridle Road (70.000 M.) (completed)
Procurement:
Package No.: 510        Package Name: UDRP/PWD/03/40/BR/010        Tender Date: 09-04-2015        Current Status: Agreement signed        Achieved on Date: 20-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/BR/010        Contractor Name: Prayag Construction       
Start Date: 27-02-2016        Intended Completion Date: 31-07-2018        Original End Date:  26-11-2016
Total Bond Cost: 35016779.15 (350.17 lakhs)        Variation Cost: -5797264.40 (-57.97 lakhs)     Hence Total Bond Cost is   29219514.75 (292.2 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1593228 for +91 days        LD Analysis for Milestone2: calculated LD is Rs 9541860 for 545 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job41.461.00 Job1.00 Job11.8441.46
2.Foundation RHS1.00 Job7.001.00 Job1.00 Job27.00
3.Foundation LHS1.00 Job7.001.00 Job1.00 Job27.00
4.Abutment Superstructure RHS1.00 Job10.901.00 Job1.00 Job3.1110.90
5.Abutment Superstructure LHS1.00 Job10.901.00 Job1.00 Job3.1110.90
6.Fixing of chequered Plate/RCC Deck210.00 sqm16.36210.00 sqm210.00 sqm4.6716.36
7.Steel Railing/crush barrier140.00 m8.13140.00 m140.00 m2.328.13
8.Approach Ramp /path 246.00 m58.39246.00 m246.00 m16.6858.39
9.Protection Work1.00 Job51.741.00 Job1.00 Job14.7851.74
10.Errection Work1.00 Job138.271.00 Job1.00 Job39.49138.27
Total Amount: 350.15 100   350.15
Remarks: No Remarks       Work Program Made On: 17-08-2016       Updation of work program on: 20-06-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-February-201713.08  lakhs
2.30-March-20179.37  lakhs
3.07-July-201720.67  lakhs
4.26-August-201728.89  lakhs
5.22-December-201717.60  lakhs
6.21-March-2018120.13  lakhs
7.28-April-201831.90  lakhs
8.29-August-201876.33  lakhs
Total 317.97  lakhs
% Payment 108.82 %
Advance Amount:  63.89  lakhs        Recovered Amount:  63.89  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 408     No. of Test Done : 410      No. of Test Passed : 405      No. of Test Failed : 5   Test report of this package
Number of Pics Available on Web Repository: 127
Number of Notice(s) issued: 85

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-02-2019Km3Anchor wall concreteAnurag DevJEUDRP R&B Guptkashi See Pic
2.29-01-2019Km3Concrete work for anchor wallAnurag DevJEUDRP R&B Guptkashi See Pic
3.07-08-2018Kotma chilon bridge erection on progressAnurag DevJEUDRP R&B Guptkashi See Pic
4.02-08-2018Kotma bridgeAnurag DevJEUDRP R&B Guptkashi See Pic
5.18-07-2018Kotma chilonL.h.s apporach pathAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
6.11-07-2018Marking bearing level by TSAnurag DevJEUDRP R&B Guptkashi See Pic
7.11-07-2018Doing T.S. survey for as built drawing.Anurag DevJEUDRP R&B Guptkashi See Pic
8.11-07-2018Erection work at Kotma chilon bridgeAnurag DevJEUDRP R&B Guptkashi See Pic
9.11-07-2018Site visit by CME sir with EE sir & RE sirAnurag DevJEUDRP R&B Guptkashi See Pic
10.17-05-2018Kotmachilone visit EE and CMEKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
11.17-05-2018Kotma visit EE and CMEKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
12.17-05-2018KotmachiloneVisit EE and AEDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
13.14-04-2018KotmachiloneKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
14.07-04-2018KotnachiloneKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
15.03-04-2018KotmachiloneKotmachilone se Sir visitDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
16.03-04-2018Se Sir visitKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
17.30-03-2018Kotmachilone erectionKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
18.30-03-2018KotmachiloneKotmachiloneDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
19.20-03-2018Site visit by DPM, EE, AE,JE, RE and AREAnurag DevJEUDRP R&B Guptkashi See Pic
20.20-03-2018Ground erection checking by EE, RE, AE, and Bridge engineer.Anurag DevJEUDRP R&B Guptkashi See Pic