UDRP/PWD/02/37/BR/07
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
507 |
Package Name: |
UDRP/PWD/02/37/BR/07 |
Sanction Cost: |
990.40 lakhs |
District: |
Chamoli |
Block: |
unknown |
Constituency: |
unknown |
Circle: |
|
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design |
No.of Sub project : |
1 |
Subproject in this package |
1 4007 Bridge over Pinder river at Boraghar (100.000 M.) (completed) |
|
Procurement: |
Package No.: 507
Package Name: UDRP/PWD/02/37/BR/07
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 20-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/37/BR/07
Contractor Name: M/S.KGL Infrastructure
|
Start Date: 27-02-2016
Intended Completion Date: 15-05-2019
Original End Date: 26-05-2017
|
Total Bond Cost: 81036313.5 (810.36 lakhs)
Variation Cost: 3076099.26 (30.76 lakhs) Hence Total Bond Cost is 84112412.76 (841.12 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6158736 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 19367604 for 478 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 4.56 | 1.00 Job | 1.00 Job | 0.52 | 4.56 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 20.87 | 1.00 Job | 1.00 Job | 2.4 | 20.87 | 3. | Foundation RHS | 1.00 Job | 31.72 | 1.00 Job | 1.00 Job | 3.64 | 31.72 | 4. | Foundation LHS | 1.00 Job | 95.17 | 1.00 Job | 1.00 Job | 10.93 | 95.17 | 5. | Abutment Superstructure RHS | 1.00 Job | 76.14 | 1.00 Job | 1.00 Job | 8.75 | 76.14 | 6. | Abutment Superstructure LHS | 1.00 Job | 190.35 | 1.00 Job | 1.00 Job | 21.87 | 190.35 | 7. | Trestle Erection and Bracing of Trestle Tower LHS | 1.00 job | 24.65 | 1.00 job | 1.00 job | 2.83 | 24.65 | 8. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 114.21 | 1.00 job | 1.00 job | 13.12 | 114.21 | 9. | Anchor Block for Wind Cable: Reinforcement, Lewis | 4.00 job | 126.90 | 4.00 job | 4.00 job | 14.58 | 126.90 | 10. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 4.60 | 2.00 no | 2.00 no | 0.53 | 4.60 | 11. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 14.98 | 4.00 no | 4.00 no | 1.72 | 14.98 | 12. | Main Cable Laying and Stretching | 8.00 no | 33.88 | 8.00 no | 8.00 no | 3.89 | 33.88 | 13. | Fixing Suspenders to Main cable with clamps and Ha | 130.00 no | 3.88 | 130.00 no | 130.00 no | 0.45 | 3.88 | 14. | Stretching Wind Guy cable, Fixing wind Ties with | 68.00 m | 8.54 | 68.00 m | 68.00 m | 0.98 | 8.54 | 15. | Fixing longitudinal Stringers/girders | 80.00 m | 32.32 | 80.00 m | 80.00 m | 3.71 | 32.32 | 16. | Fixing of chequered Plate/RCC Deck | 250.00 sqm | 13.26 | 250.00 sqm | 250.00 sqm | 1.52 | 13.26 | 17. | Steel Railing/crush barrier | 200.00 m | 7.38 | 200.00 m | 200.00 m | 0.85 | 7.38 | 18. | Approach Ramp /path | 100.00 m | 7.37 | 100.00 m | 100.00 m | 0.85 | 7.37 | 19. | Protection Work | 2.00 Job | 59.74 | 2.00 Job | 2.00 Job | 6.86 | 59.74 |
Total Amount: |
870.52 |
|
100 |
870.52 |
|
Remarks:
No Remarks
Work Program Made On:
30-08-2016
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-March-2017 | 42.29 lakhs |
2. | 25-May-2017 | 27.06 lakhs |
3. | 24-June-2017 | 52.85 lakhs |
4. | 28-July-2017 | 19.92 lakhs |
5. | 13-October-2017 | 41.19 lakhs |
6. | 24-November-2017 | 26.82 lakhs |
7. | 29-December-2017 | 41.49 lakhs |
8. | 31-January-2018 | 38.68 lakhs |
9. | 28-February-2018 | 31.96 lakhs |
10. | 28-March-2018 | 32.37 lakhs |
11. | 30-May-2018 | 64.64 lakhs |
12. | 31-May-2018 | 40.46 lakhs |
13. | 08-August-2018 | 22.61 lakhs |
14. | 09-August-2018 | 26.44 lakhs |
15. | 14-September-2018 | 22.64 lakhs |
16. | 28-September-2018 | 56.02 lakhs |
17. | 31-October-2018 | 30.68 lakhs |
18. | 29-November-2018 | 22.33 lakhs |
19. | 29-December-2018 | 27.81 lakhs |
20. | 15-February-2019 | 26.99 lakhs |
21. | 27-February-2019 | 42.36 lakhs |
22. | 30-March-2019 | 23.53 lakhs |
23. | 30-April-2019 | 24.09 lakhs |
24. | 10-June-2019 | 39.91 lakhs |
25. | 12-June-2019 | 29.39 lakhs |
26. | 19-June-2019 | 16.01 lakhs |
Total |
870.54 lakhs |
% Payment |
103.5 % |
|
Advance Amount: 81.00 lakhs
Recovered Amount: 81.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 83 |
Number of Notice(s) issued: 84 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-03-2019 | Boragad bridge | Deck slab is in progress at boragad bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
2. | 04-02-2019 | Boragad bridge | M30 concrete work in progress for anchor cum towar at boragad bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
3. | 04-02-2019 | Boragad bridge | M30 concrete work in progress for anchor cum towar at boragad bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
4. | 13-12-2018 | A2 | Plum work in progress in A2 anchor cum abutment | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
5. | 30-11-2018 | Boragad bridge | Reinforcement work in progress for wind anchor W3 first lift above Raft at boragad bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
6. | 23-11-2018 | A2 | A2 anchor cum abutment work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
7. | 23-10-2018 | Boragad bridge | Shuttering work complete A1 main anchor block for top slab | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
8. | 23-10-2018 | Boragad bridge | Excavation work complete for wind anchor at boragad bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
9. | 23-10-2018 | Boragad bridge | Anchor cum towar Shuttering work in progress for first lift above gallery slab at boragad bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
10. | 25-09-2018 | Boragad Site Lab | Cube Testing at Boragad by CME Sir | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
11. | 24-09-2018 | Boragad Bridge | CME Sir Visit Boragad Bridge | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
12. | 24-09-2018 | Boragad Bridge | SE Rudraprayag, EE Karanpryag Visit Boragad Bridge | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
13. | 20-09-2018 | Boragad Bridge | A2 Anchor cum Tower 4 Lift above Dack slab casting in progress. | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
14. | 30-05-2018 | Wind anchor W-4 | Anchor Girder fixing in wind anchor block A-1 side | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
15. | 30-05-2018 | Anchor block A-1 side | Fixing of bed block for anchor Girder in Anchor block A-1 side | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
16. | 29-04-2018 | Fabrication yard Ramnagar | Fabrication Checking of BR 07 Boragad Bridge At Ramnagar | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
17. | 26-04-2018 | A-1 Anchor block | Reinforcement binding for wall At 6.300/10.00 mtr in Anchor block A-1 side | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
18. | 26-04-2018 | Wind anchor W4 at A-1 side | Shutting work on progress at W-4 wind anchor block | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
19. | 14-03-2018 | W-1 wind anchor block A-1 side | Excavation for wind anchor block | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
20. | 05-03-2018 | At Abutment A1 side | Anchor A1side status | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
|
|