Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/37/BR/07 Agreement signed
Project: UDRP-RB Package No.: 507 Package Name: UDRP/PWD/02/37/BR/07 Sanction Cost: 990.40  lakhs
District: Chamoli Block: unknown Constituency: unknown Circle:
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: Design No.of Sub project : 1
Subproject in this package
1  4007   Bridge over Pinder river at Boraghar (100.000 M.) (completed)
Procurement:
Package No.: 507        Package Name: UDRP/PWD/02/37/BR/07        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 20-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/37/BR/07        Contractor Name: M/S.KGL Infrastructure       
Start Date: 27-02-2016        Intended Completion Date: 15-05-2019        Original End Date:  26-05-2017
Total Bond Cost: 81036313.5 (810.36 lakhs)        Variation Cost: 3076099.26 (30.76 lakhs)     Hence Total Bond Cost is   84112412.76 (841.12 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 6158736 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 19367604 for 478 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job4.561.00 Job1.00 Job0.524.56
2.Other Allied Works & Finishing Work 1.00 Job20.871.00 Job1.00 Job2.420.87
3.Foundation RHS1.00 Job31.721.00 Job1.00 Job3.6431.72
4.Foundation LHS1.00 Job95.171.00 Job1.00 Job10.9395.17
5.Abutment Superstructure RHS1.00 Job76.141.00 Job1.00 Job8.7576.14
6.Abutment Superstructure LHS1.00 Job190.351.00 Job1.00 Job21.87190.35
7.Trestle Erection and Bracing of Trestle Tower LHS 1.00 job24.651.00 job1.00 job2.8324.65
8.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job114.211.00 job1.00 job13.12114.21
9.Anchor Block for Wind Cable: Reinforcement, Lewis 4.00 job126.904.00 job4.00 job14.58126.90
10.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no4.602.00 no2.00 no0.534.60
11.Fixing of Saddle pulley along with Rib plate and 4.00 no14.984.00 no4.00 no1.7214.98
12.Main Cable Laying and Stretching 8.00 no33.888.00 no8.00 no3.8933.88
13.Fixing Suspenders to Main cable with clamps and Ha130.00 no3.88130.00 no130.00 no0.453.88
14.Stretching Wind Guy cable, Fixing wind Ties with 68.00 m8.5468.00 m68.00 m0.988.54
15.Fixing longitudinal Stringers/girders80.00 m32.3280.00 m80.00 m3.7132.32
16.Fixing of chequered Plate/RCC Deck250.00 sqm13.26250.00 sqm250.00 sqm1.5213.26
17.Steel Railing/crush barrier200.00 m7.38200.00 m200.00 m0.857.38
18.Approach Ramp /path 100.00 m7.37100.00 m100.00 m0.857.37
19.Protection Work2.00 Job59.742.00 Job2.00 Job6.8659.74
Total Amount: 870.52 100   870.52
Remarks: No Remarks       Work Program Made On: 30-08-2016       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-March-201742.29  lakhs
2.25-May-201727.06  lakhs
3.24-June-201752.85  lakhs
4.28-July-201719.92  lakhs
5.13-October-201741.19  lakhs
6.24-November-201726.82  lakhs
7.29-December-201741.49  lakhs
8.31-January-201838.68  lakhs
9.28-February-201831.96  lakhs
10.28-March-201832.37  lakhs
11.30-May-201864.64  lakhs
12.31-May-201840.46  lakhs
13.08-August-201822.61  lakhs
14.09-August-201826.44  lakhs
15.14-September-201822.64  lakhs
16.28-September-201856.02  lakhs
17.31-October-201830.68  lakhs
18.29-November-201822.33  lakhs
19.29-December-201827.81  lakhs
20.15-February-201926.99  lakhs
21.27-February-201942.36  lakhs
22.30-March-201923.53  lakhs
23.30-April-201924.09  lakhs
24.10-June-201939.91  lakhs
25.12-June-201929.39  lakhs
26.19-June-201916.01  lakhs
Total 870.54  lakhs
% Payment 103.5 %
Advance Amount:  81.00  lakhs        Recovered Amount:  81.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1581     No. of Test Done : 1624      No. of Test Passed : 1603      No. of Test Failed : 21   Test report of this package
Number of Pics Available on Web Repository: 83
Number of Notice(s) issued: 84

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-03-2019Boragad bridgeDeck slab is in progress at boragad bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
2.04-02-2019Boragad bridgeM30 concrete work in progress for anchor cum towar at boragad bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
3.04-02-2019Boragad bridgeM30 concrete work in progress for anchor cum towar at boragad bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
4.13-12-2018A2Plum work in progress in A2 anchor cum abutmentNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
5.30-11-2018Boragad bridgeReinforcement work in progress for wind anchor W3 first lift above Raft at boragad bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
6.23-11-2018A2A2 anchor cum abutment work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
7.23-10-2018Boragad bridgeShuttering work complete A1 main anchor block for top slabAnkit KumarJEUDRP R&B Gopeshwar See Pic
8.23-10-2018Boragad bridgeExcavation work complete for wind anchor at boragad bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
9.23-10-2018Boragad bridgeAnchor cum towar Shuttering work in progress for first lift above gallery slab at boragad bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
10.25-09-2018Boragad Site LabCube Testing at Boragad by CME SirCharu UpadhyayQSBSC R&B WB Chamoli See Pic
11.24-09-2018Boragad BridgeCME Sir Visit Boragad BridgeCharu UpadhyayQSBSC R&B WB Chamoli See Pic
12.24-09-2018Boragad BridgeSE Rudraprayag, EE Karanpryag Visit Boragad BridgeCharu UpadhyayQSBSC R&B WB Chamoli See Pic
13.20-09-2018Boragad BridgeA2 Anchor cum Tower 4 Lift above Dack slab casting in progress.Charu UpadhyayQSBSC R&B WB Chamoli See Pic
14.30-05-2018Wind anchor W-4Anchor Girder fixing in wind anchor block A-1 sideShivam KumarJEUDRP R&B Karnprayag See Pic
15.30-05-2018Anchor block A-1 sideFixing of bed block for anchor Girder in Anchor block A-1 sideShivam KumarJEUDRP R&B Karnprayag See Pic
16.29-04-2018Fabrication yard RamnagarFabrication Checking of BR 07 Boragad Bridge At RamnagarCharu UpadhyayQSBSC R&B WB Chamoli See Pic
17.26-04-2018A-1 Anchor blockReinforcement binding for wall At 6.300/10.00 mtr in Anchor block A-1 sideShivam KumarJEUDRP R&B Karnprayag See Pic
18.26-04-2018Wind anchor W4 at A-1 sideShutting work on progress at W-4 wind anchor blockShivam KumarJEUDRP R&B Karnprayag See Pic
19.14-03-2018W-1 wind anchor block A-1 sideExcavation for wind anchor blockShivam KumarJEUDRP R&B Karnprayag See Pic
20.05-03-2018At Abutment A1 sideAnchor A1side statusRajan NautiyalJEUDRP R&B Chakrata See Pic