Package Profile Report

UDRP/PWD/01/31/BR/03 Agreement signed
Project: UDRP-RB Package No.: 503 Package Name: UDRP/PWD/01/31/BR/03 Sanction Cost: 904.32  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: design No.of Sub project : 1
Subproject in this package
1  4002   Nalura Bridge (120.000 M.) (completed)
Procurement:
Package No.: 503        Package Name: UDRP/PWD/01/31/BR/03        Tender Date: 11-03-2016        Current Status: Agreement signed        Achieved on Date: 15-06-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/BR/03        Contractor Name: Border Builders       
Start Date: 22-06-2016        Intended Completion Date: 31-12-2018        Original End Date:  21-09-2017
Total Bond Cost: 67353701 (673.54 lakhs)        Variation Cost: 6288983.28 (62.89 lakhs)     Hence Total Bond Cost is   73642684.28 (736.43 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5792444 for 172 days        LD Analysis for Milestone2: calculated LD is Rs 10507224 for 312 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Other Allied Works & Finishing Work 1.00 Job67.931.00 Job1.00 Job10.0867.93
2.Foundation LHS1.00 Job6.151.00 Job1.00 Job0.916.15
3.Abutment Superstructure RHS1.00 Job9.231.00 Job1.00 Job1.379.23
4.Abutment Superstructure LHS1.00 Job7.381.00 Job1.00 Job1.17.38
5.Fixing of chequered Plate/RCC Deck369.60 sqm34.79369.60 sqm369.60 sqm5.1634.79
6.Steel Railing/crush barrier224.00 m4.48224.00 m224.00 m0.674.48
7.Approach Ramp /path 100.00 m5.25100.00 m100.00 m0.785.25
8.Protection Work1.00 Job101.541.00 Job1.00 Job15.06101.54
9.Errection Work1.00 Job437.291.00 Job1.00 Job64.88437.29
Total Amount: 674.04 100   674.04
Remarks: No Remarks       Work Program Made On: 17-08-2016       Updation of work program on: 26-05-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-October-201630.61  lakhs
2.21-January-20172.01  lakhs
3.28-March-20172.31  lakhs
4.31-March-201756.12  lakhs
5.31-May-201763.02  lakhs
6.13-October-201751.17  lakhs
7.23-November-20170.71  lakhs
8.27-November-201751.02  lakhs
9.23-December-20170.07  lakhs
10.31-March-2018134.93  lakhs
11.25-October-201827.08  lakhs
12.03-November-201860.00  lakhs
13.14-December-201810.20  lakhs
14.15-February-2019113.34  lakhs
15.07-March-201959.79  lakhs
16.14-June-20192.81  lakhs
17.15-July-20192.67  lakhs
Total 667.86  lakhs
% Payment 90.69 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 262     No. of Test Done : 262      No. of Test Passed : 262      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 63
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-01-2019Naluna bridgePanting work in Progress .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
2.05-01-2019Naluna bridgeCheckered plate work in progress.Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
3.05-01-2019Naluna bridgeFixing of checkered plate and painting work is in progressAbhishek TiwariAEUDRP AF SL&B Uttarkashi See Pic
4.04-01-2019Naluna bridge in uttarkashiFixing of checkered plate is in progress at naluna bridge.Abhishek TiwariAEUDRP AF SL&B Uttarkashi See Pic
5.03-01-2019NalunaCheckered plate fixing at Naluna bride. Work in progress .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
6.27-12-2018Naluna bridgeFixing of nut boltChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.25-12-2018Naluna bridgeErection of all members completed.Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
8.12-12-2018Naluna bridge in UttarkashiErection work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
9.09-05-2018SE sir visit at Naluna bridge at A1 sideSE sir visit at Naluna bridgeAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
10.15-03-2018Naluna Bridge (BR-03)Excavation for Protection WorkManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
11.23-02-2018Naluna Bridge (BR-03)Joint measurements of Slope Protection for running bill.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
12.23-02-2018Back of A2 abutmentNaluna bridge plum work BR/03Ankit KuriyalJEUDRP R&B Uttarkashi See Pic
13.20-02-2018Naluna Bridge (BR-03)Preparation for erectionManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
14.15-02-2018A1 side Naluna bridge BR/03CE sir, SE sir, EE sir visit at bridge site.Ankit KuriyalJEUDRP R&B Uttarkashi See Pic
15.06-02-2018Naluna BridgeSlope stabilization work on Abutment A-2 sideManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
16.06-01-2018NalunaView of Naluna Bridge under constructionManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
17.18-12-2017A1Erection tower in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
18.05-12-2017A2Approach road in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
19.02-12-2017Naluna bridge at uttarkashiApproach road work is in progress at naluna bridge in uttarkashiAbhishek TiwariAEUDRP AF SL&B Uttarkashi See Pic
20.18-11-2017Rishikesh Shyampur Naluna T/B UID no 9032.Inspection of ground erection work in progress Naluna BridgeAnurag SinghTLBSC R&B WB Rudraprayag See Pic