UDRP/PWD/02/37/BR/02
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
502 |
Package Name: |
UDRP/PWD/02/37/BR/02 |
Sanction Cost: |
882.72 lakhs |
District: |
Chamoli |
Block: |
unknown |
Constituency: |
unknown |
Circle: |
|
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
design |
No.of Sub project : |
1 |
Subproject in this package |
1 4001 Narayanbagar Bridge (90.000 M.) (completed) |
|
Procurement: |
Package No.: 502
Package Name: UDRP/PWD/02/37/BR/02
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 02-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/37/BR/02
Contractor Name: D S Construction
|
Start Date: 09-02-2016
Intended Completion Date: 21-04-2018
Original End Date: 08-05-2017
|
Total Bond Cost: 82419689.55 (824.2 lakhs)
Variation Cost: 2525080.65 (25.25 lakhs) Hence Total Bond Cost is 84944770.2 (849.45 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6263920 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 7871110 for 191 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 1.00 Job | 4.01 | 1.00 Job | 1.00 Job | 0.45 | 4.01 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 18.98 | 1.00 Job | 1.00 Job | 2.15 | 18.98 | 3. | Foundation RHS | 1.00 Job | 83.56 | 1.00 Job | 1.00 Job | 9.48 | 83.56 | 4. | Foundation LHS | 1.00 Job | 27.85 | 1.00 Job | 1.00 Job | 3.16 | 27.85 | 5. | Abutment Superstructure RHS | 1.00 Job | 89.13 | 1.00 Job | 1.00 Job | 10.11 | 89.13 | 6. | Abutment Superstructure LHS | 1.00 Job | 44.56 | 1.00 Job | 1.00 Job | 5.06 | 44.56 | 7. | Trestle Erection and Bracing of Trestle Tower LHS | 2.00 job | 46.95 | 2.00 job | 2.00 job | 5.33 | 46.95 | 8. | Anchor Block Main Cable Reinforcement (3-4 Times) | 2.00 job | 200.54 | 2.00 job | 2.00 job | 22.75 | 200.54 | 9. | Anchor Block for Wind Cable: Reinforcement, Lewis | 4.00 job | 111.41 | 4.00 job | 4.00 job | 12.64 | 111.41 | 10. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 4.35 | 2.00 no | 2.00 no | 0.49 | 4.35 | 11. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 6.59 | 4.00 no | 4.00 no | 0.75 | 6.59 | 12. | Main Cable Laying and Stretching | 8.00 no | 32.82 | 8.00 no | 8.00 no | 3.72 | 32.82 | 13. | Fixing Suspenders to Main cable with clamps and Ha | 122.00 no | 2.27 | 122.00 no | 122.00 no | 0.26 | 2.27 | 14. | Stretching Wind Guy cable, Fixing wind Ties with | 439.00 m | 6.45 | 439.00 m | 439.00 m | 0.73 | 6.45 | 15. | Fixing longitudinal Stringers/girders | 110.00 m | 37.77 | 110.00 m | 110.00 m | 4.29 | 37.77 | 16. | Fixing of chequered Plate/RCC Deck | 227.48 sqm | 11.35 | 227.48 sqm | 227.48 sqm | 1.29 | 11.35 | 17. | Steel Railing/crush barrier | 192.00 m | 2.74 | 192.00 m | 192.00 m | 0.31 | 2.74 | 18. | Approach Ramp /path | 100.00 m | 7.81 | 100.00 m | 100.00 m | 0.89 | 7.81 | 19. | Protection Work | 2.00 Job | 142.25 | 2.00 Job | 2.00 Job | 16.14 | 142.25 |
Total Amount: |
881.39 |
|
100 |
881.39 |
|
Remarks:
No Remarks
Work Program Made On:
17-08-2016
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-June-2016 | 18.75 lakhs |
2. | 23-August-2016 | 30.90 lakhs |
3. | 30-September-2016 | 30.00 lakhs |
4. | 27-October-2016 | 45.90 lakhs |
5. | 23-December-2016 | 24.40 lakhs |
6. | 30-December-2016 | 53.13 lakhs |
7. | 08-March-2017 | 25.94 lakhs |
8. | 09-March-2017 | 61.91 lakhs |
9. | 30-March-2017 | 44.42 lakhs |
10. | 31-March-2017 | 27.00 lakhs |
11. | 25-May-2017 | 29.54 lakhs |
12. | 24-June-2017 | 25.82 lakhs |
13. | 13-October-2017 | 105.55 lakhs |
14. | 16-October-2017 | 40.97 lakhs |
15. | 30-November-2017 | 51.29 lakhs |
16. | 29-December-2017 | 40.71 lakhs |
17. | 31-January-2018 | 60.11 lakhs |
18. | 28-February-2018 | 30.41 lakhs |
19. | 28-March-2018 | 17.87 lakhs |
20. | 22-June-2018 | 48.49 lakhs |
21. | 29-November-2018 | 47.79 lakhs |
22. | 13-February-2019 | 20.47 lakhs |
Total |
881.37 lakhs |
% Payment |
103.76 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 108 |
Number of Notice(s) issued: 82 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-06-2018 | Narayanbagar Bridge | Checking of Bridge for World Bank visit | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
2. | 07-04-2018 | At Narayanbagad civil hospital | General health check up on occasion of World health week | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
3. | 07-04-2018 | At Narayanbagad civil hospital | General checkups of labour on world health week occasion | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
4. | 04-04-2018 | At Narayanbargh A1 side | Visit of CE sir and instructions given for balance work complete on time | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
5. | 04-04-2018 | At Abutment A1 side Narayanbagad | CE visit at Narayanbagad BR-02 and instructions given for complete work on time | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
6. | 15-02-2018 | At Anchor block A1 side | Checking of Anchor girder by DPM sir found satisfactory | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
7. | 15-02-2018 | At Abutment A1 | Checking of Site work by DPM sir and found satisfactory | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
8. | 15-02-2018 | At Abutment A1 side | Visit by DPM sir and instructions given for balance work complete on time. | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
9. | 15-02-2018 | At A1 side | Status of Erection work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
10. | 15-02-2018 | PaInspection of Narayan Bagar Suspension Bridge 95m UID no 9026 wite DPM Dayanand Sir,XEN Mr. R. Chauhan, RE RK Mishra, | Site inspection of Narayan Bagar UID no 9026.DPM Dayanand Sir, | Anurag Singh | TL | BSC R&B WB Rudraprayag | See Pic |
11. | 11-01-2018 | At A1 side | Visit of EE sir and instructions has given for balance work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
12. | 24-12-2017 | At Abutment A1 side erection of Tower has been started | Abutment A1 side tower erection in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
13. | 24-12-2017 | At Abutment A1 side | Information board Grivence Number corrected as instructed | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
14. | 24-12-2017 | At Abutment A1 | Fixing of Tower base in progress at Abutment A1 side D/s | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
15. | 12-12-2017 | At A2 side | Abutment of A2 side completed | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
16. | 12-12-2017 | At Wind anchor A2 side D/s | Excavation of wind Anchor in progress in hard rock | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
17. | 12-12-2017 | At Abutment A1 | Deck level checking | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
18. | 12-12-2017 | At anchor A1 | Fixing of Anchor girder in progress | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
19. | 12-12-2017 | At Abutment A1 Casting completed | Abutment A1 Completed | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
20. | 07-12-2017 | Nara Jadoda Muzaffar Nagar | Inspection of ground erection UID no 9026, suspension bridge Narayanbagar | Anurag Singh | TL | BSC R&B WB Rudraprayag | See Pic |
|
|