Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/37/BR/01 Agreement signed
Project: UDRP-RB Package No.: 501 Package Name: UDRP/PWD/02/37/BR/01 Sanction Cost: 1073.00  lakhs
District: Chamoli Block: unknown Constituency: unknown Circle:
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: design No.of Sub project : 1
Subproject in this package
1  4004   Chepado Bridge (120.000 M.) (completed)
Procurement:
Package No.: 501        Package Name: UDRP/PWD/02/37/BR/01        Tender Date: 06-01-2015        Current Status: Agreement signed        Achieved on Date: 01-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/37/BR/01        Contractor Name: M/S.KGL Infrastructure       
Start Date: 08-07-2015        Intended Completion Date: 28-02-2019        Original End Date:  07-10-2016
Total Bond Cost: 68202553.94 (682.03 lakhs)        Variation Cost: 20260513.23 (202.61 lakhs)     Hence Total Bond Cost is   88463067.17 (884.63 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2557575 for +75 days        LD Analysis for Milestone2: calculated LD is Rs 6956604 for 204 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan1.00 Job5.361.00 Job1.00 Job0.595.36
2.Other Allied Works & Finishing Work 1.00 Job39.811.00 Job1.00 Job4.3839.81
3.Foundation RHS1.00 Job80.001.00 Job1.00 Job8.8180.00
4.Foundation LHS1.00 Job43.081.00 Job1.00 Job4.7443.08
5.Abutment Superstructure RHS1.00 Job184.611.00 Job1.00 Job20.33184.61
6.Abutment Superstructure LHS1.00 Job73.841.00 Job1.00 Job8.1373.84
7.Trestle Erection and Bracing of Trestle Tower LHS 1.00 job31.431.00 job1.00 job3.4631.43
8.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job110.761.00 job1.00 job12.2110.76
9.Anchor Block for Wind Cable: Reinforcement, Lewis 4.00 job123.074.00 job4.00 job13.55123.07
10.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no5.242.00 no2.00 no0.585.24
11.Fixing of Saddle pulley along with Rib plate and 4.00 no15.074.00 no4.00 no1.6615.07
12.Main Cable Laying and Stretching 8.00 no42.408.00 no8.00 no4.6742.40
13.Fixing Suspenders to Main cable with clamps and Ha158.00 no5.32158.00 no158.00 no0.595.32
14.Stretching Wind Guy cable, Fixing wind Ties with 80.00 m9.5780.00 m80.00 m1.059.57
15.Fixing longitudinal Stringers/girders120.00 m41.52120.00 m120.00 m4.5741.52
16.Fixing of chequered Plate/RCC Deck297.00 sqm16.21297.00 sqm297.00 sqm1.7916.21
17.Steel Railing/crush barrier255.00 m8.73255.00 m255.00 m0.968.73
18.Approach Ramp /path 100.00 m3.05100.00 m100.00 m0.343.05
19.Protection Work2.00 Job69.122.00 Job2.00 Job7.6169.12
Total Amount: 908.19 100   908.19
Remarks: No Remarks       Work Program Made On: 02-01-2016       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-March-201723.25  lakhs
2.30-March-201745.79  lakhs
3.31-March-201710.00  lakhs
4.25-May-201738.01  lakhs
5.24-June-201740.29  lakhs
6.08-August-201786.53  lakhs
7.13-October-201768.85  lakhs
8.24-November-201712.60  lakhs
9.30-November-201738.15  lakhs
10.29-December-201747.28  lakhs
11.31-January-201844.85  lakhs
12.06-March-201820.00  lakhs
13.28-March-201831.31  lakhs
14.28-April-201826.14  lakhs
15.31-May-201832.76  lakhs
16.08-August-201823.23  lakhs
17.09-August-201858.98  lakhs
18.28-September-201820.61  lakhs
19.31-October-201841.84  lakhs
20.29-November-201814.38  lakhs
21.29-December-201822.69  lakhs
22.15-February-201950.74  lakhs
23.27-February-201928.15  lakhs
24.30-March-201919.55  lakhs
25.30-April-201921.05  lakhs
26.22-May-20199.18  lakhs
27.10-June-201917.61  lakhs
28.12-June-201914.36  lakhs
Total 908.18  lakhs
% Payment 102.66 %
Advance Amount:  68.20  lakhs        Recovered Amount:  68.20  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1785     No. of Test Done : 1831      No. of Test Passed : 1789      No. of Test Failed : 42   Test report of this package
Number of Pics Available on Web Repository: 72
Number of Notice(s) issued: 97

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-02-2019Main bridgeErection {camber}work under progress .Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.07-01-2019Chepdo bridgeErection work in progress at chepdo bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
3.07-01-2019Chepso bridgeDeck erection work in progress at chepdo bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
4.30-11-2018Chepdo bridgeAnchor cum towar M30 concrete work in progress for first lift above cable galleryAnkit KumarJEUDRP R&B Gopeshwar See Pic
5.25-09-2018Chepdo BridgeCME Sir Visit Chepdo BridgeCharu UpadhyayQSBSC R&B WB Chamoli See Pic
6.15-07-2018Chepdo BridgePCC of Wind Anchor 1 & Wind Anchor 4 CompleteCharu UpadhyayQSBSC R&B WB Chamoli See Pic
7.12-07-2018Chepdo BridgeExcavation of Wind Anchor 1 is in progressCharu UpadhyayQSBSC R&B WB Chamoli See Pic
8.23-06-2018Chepdo BridgeCasting of wall A1 Anchor Cum Tower is in progressCharu UpadhyayQSBSC R&B WB Chamoli See Pic
9.11-06-2018Chepdo BridgeWind Anchor completed A2 side at Chepdo BridgeCharu UpadhyayQSBSC R&B WB Chamoli See Pic
10.11-06-2018Chepdo BridgeProtection work is in progress at Chepdo BridgeCharu UpadhyayQSBSC R&B WB Chamoli See Pic
11.04-04-2018At Abutment A1 sideCE sir visit and instructions given for balance work complete on timeRajan NautiyalJEUDRP R&B Chakrata See Pic
12.16-02-2018Chepro Suspension bridge 120 m, UID no 9025Site inspection of ChapedoAnurag SinghTLBSC R&B WB Rudraprayag See Pic
13.15-02-2018At BR-01 LaboratoryChecking of ESMF and laboratory equipments by DPM sirRajan NautiyalJEUDRP R&B Chakrata See Pic
14.15-02-2018At Abutment A2 sideVisit by DPM sir and instructions given for balance work to complete on time.Rajan NautiyalJEUDRP R&B Chakrata See Pic
15.17-01-2018Chepdo bridgeAnchor cum towar M30 concrete work in progress for 2nd lift above deck slab at chepdo bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
16.10-01-2018Chepdo bridgeM30 concrete work in progress for anchor cum towar RHS 1st lift above deck slab at chepdo bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
17.04-12-2017Chepdo BridgeReinforcement Binding work is in Progress for Top raft A2 AbutmentCharu UpadhyayQSBSC R&B WB Chamoli See Pic
18.02-12-2017Didsari bridgeDeck erection work is in progress at didsari in uttarkashiAbhishek TiwariAEUDRP AF SL&B Uttarkashi See Pic
19.29-11-2017Chepdo bridgeRHS Anchor cum towar M30 concrete work in progress for first lift above 4th slab at chepdo bridgeAnkit KumarJEUDRP R&B Gopeshwar See Pic
20.18-11-2017Abutment cum anchor block A-1 sideAbutment cum anchor block A -1 sideShivam KumarJEUDRP R&B Karnprayag See Pic