UDRP/PWD/05/53/RD/005
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
5 |
Package Name: |
UDRP/PWD/05/53/RD/005 |
Sanction Cost: |
777.35 lakhs |
District: |
Dehradun |
Block: |
Raipur |
Constituency: |
Doiwala |
Circle: |
Tehri WB Circle |
DEA: |
DEA Chakrata |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
8 |
Subproject in this package |
1 1423 Thano Bhogpur Road (1.000 KM.) (completed) | 2 1440 Basantpur Madsi Motor Road (5.000 KM.) (completed) | 3 1445 Bhogpur Gadul Fagsi Motor Road (1.750 KM.) (completed) | 4 1465 Dharkot Tali Motor Road (4.000 KM.) (completed) | 5 1466 Dharkot Tangoli Badarna Motor Road (7.000 KM.) (completed) | 6 1490 Harrawala Nakronda Road (4.500 KM.) (completed) | 7 1517 Kunwala to Sainik Colony Road (1.000 KM.) (completed) | 8 1587 Suryadhar Sangaoun Motor Road (5.500 KM.) (completed) |
|
Procurement: |
Package No.: 5
Package Name: UDRP/PWD/05/53/RD/005
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/05/53/RD/005
Contractor Name: Vijay Engineering Associates
|
Start Date: 01-09-2014
Intended Completion Date: 30-04-2016
Original End Date: 31-12-2015
|
Total Bond Cost: 54378925.06 (543.79 lakhs)
Variation Cost: 19270279.78 (192.7 lakhs) Hence Total Bond Cost is 73649204.84 (736.49 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 4369.70 m | 402.58 | 4369.70 m | 4369.70 m | 50.58 | 402.58 | 2. | Cause Way | 12.00 No | 45.45 | 12.00 No | 12.00 No | 3.58 | 45.45 | 3. | G-3 | 0.05 KM | 11.48 | 0.05 KM | 0.05 KM | 1.61 | 11.48 | 4. | PC/CC i/c Prime Coat, Tack Coat | 6.50 KM | 51.39 | 6.50 KM | 6.50 KM | 7.21 | 51.39 | 5. | Culverts/Scupper | 34.00 No | 169.94 | 34.00 No | 34.00 No | 27.37 | 169.94 | 6. | longitudinal Drain | 5550.00 m | 40.25 | 5200.00 m | 5200.00 m | 7.26 | 40.25 | 7. | Crash Barrier | 106.00 m | 2.28 | 106.00 m | 106.00 m | 0.32 | 2.28 | 8. | GSB/RBI/G-1 | 3.08 KM | 14.08 | 3.08 KM | 3.08 KM | 2.06 | 14.08 |
Total Amount: |
737.45 |
|
100 |
737.45 |
|
Remarks:
No Remarks
Work Program Made On:
23-09-2014
Updation of work program on:
17-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-February-2015 | 52.56 lakhs |
2. | 23-September-2015 | 49.33 lakhs |
3. | 06-November-2015 | 69.08 lakhs |
4. | 19-December-2015 | 46.58 lakhs |
5. | 23-January-2016 | 46.76 lakhs |
6. | 08-August-2016 | 113.89 lakhs |
7. | 04-February-2017 | 16.10 lakhs |
8. | 30-June-2017 | 11.01 lakhs |
9. | 31-December-2014 | 26.86 lakhs |
10. | 31-March-2015 | 26.12 lakhs |
11. | 22-May-2015 | 44.84 lakhs |
12. | 06-July-2015 | 21.51 lakhs |
13. | 31-July-2015 | 25.50 lakhs |
14. | 29-February-2016 | 45.63 lakhs |
15. | 31-March-2016 | 26.13 lakhs |
16. | 06-May-2016 | 19.63 lakhs |
17. | 28-October-2014 | 12.99 lakhs |
18. | 22-June-2015 | 26.69 lakhs |
Total |
681.21 lakhs |
% Payment |
92.49 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 142 |
Number of Notice(s) issued: 78 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-03-2017 | Ch-0/38-0/39 | General inspection of kuwanwala to sainik colony Motor Road | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
2. | 04-10-2016 | Km 7 HM-6 | Inspection of PC by SE,EE,AE and TL | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
3. | 27-08-2016 | Ch1/16 | Joint inspection with constant clint & contractor regarding complition of work. | Om Prakash Singh | Site Supervisor | DSC2 R&B WB Dehradun | See Pic |
4. | 06-05-2016 | Ch 2/6 | Checking of thickness of PC | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
5. | 06-05-2016 | Ch 2/11 | PC work under progress | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
6. | 04-05-2016 | Km3 under RCC bridge | Repairing of Eroded base of of rcc bridge. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
7. | 28-04-2016 | Ch 3/32 | PC and seal coat completed | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
8. | 25-04-2016 | Ch 3/30 | Laying of PC | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
9. | 25-04-2016 | Ch 3/35 | Rolling of PC | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
10. | 25-04-2016 | Km1 | WB's team visited the site for EMP verification | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
11. | 25-04-2016 | Km 7 | Undulation checking | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
12. | 21-04-2016 | Ch 1/11-1/12 | Construction of R/W completed | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
13. | 12-04-2016 | Ch 7 th Km | SE WB Tehri visit with EE WB Chakrata AE WB Chakrata fo4 checking of Bitumen PC work | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
14. | 12-04-2016 | Km 2 | Site inspection by SE WB PWD TEHRI | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 12-04-2016 | Km 7 ch 6/28 | Joint Inspection of PC work by SE Sir, EE sir and AE sir | Dhwajvir Singh | JE | UDRP R&B Chakrata | See Pic |
16. | 05-04-2016 | Km2 | Cc drain complete | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
17. | 05-04-2016 | Km 7 | Seal coat under progress | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
18. | 05-04-2016 | Km 7 | Premix carpet surfacing | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
19. | 30-03-2016 | Km 7 | Preparation for premix carpet going on. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
20. | 30-03-2016 | 0/37 | Reconstruction of washed away portion | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|