Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/05/53/RD/005 Agreement signed
Project: UDRP-RB Package No.: 5 Package Name: UDRP/PWD/05/53/RD/005 Sanction Cost: 777.35  lakhs
District: Dehradun Block: Raipur Constituency: Doiwala Circle: Tehri WB Circle
DEA: DEA Chakrata DSC: Egis International DSC Scope: only Supervision No.of Sub project : 8
Subproject in this package
1  1423   Thano Bhogpur Road (1.000 KM.) (completed)
2  1440   Basantpur Madsi Motor Road (5.000 KM.) (completed)
3  1445   Bhogpur Gadul Fagsi Motor Road (1.750 KM.) (completed)
4  1465   Dharkot Tali Motor Road (4.000 KM.) (completed)
5  1466   Dharkot Tangoli Badarna Motor Road (7.000 KM.) (completed)
6  1490   Harrawala Nakronda Road (4.500 KM.) (completed)
7  1517   Kunwala to Sainik Colony Road (1.000 KM.) (completed)
8  1587   Suryadhar Sangaoun Motor Road (5.500 KM.) (completed)
Procurement:
Package No.: 5        Package Name: UDRP/PWD/05/53/RD/005        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 25-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/05/53/RD/005        Contractor Name: Vijay Engineering Associates       
Start Date: 01-09-2014        Intended Completion Date: 30-04-2016        Original End Date:  31-12-2015
Total Bond Cost: 54378925.06 (543.79 lakhs)        Variation Cost: 19270279.78 (192.7 lakhs)     Hence Total Bond Cost is   73649204.84 (736.49 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works4369.70 m402.584369.70 m4369.70 m50.58402.58
2.Cause Way12.00 No45.4512.00 No12.00 No3.5845.45
3.G-30.05 KM11.480.05 KM0.05 KM1.6111.48
4.PC/CC i/c Prime Coat, Tack Coat6.50 KM51.396.50 KM6.50 KM7.2151.39
5.Culverts/Scupper 34.00 No169.9434.00 No34.00 No27.37169.94
6.longitudinal Drain5550.00 m40.255200.00 m5200.00 m7.2640.25
7.Crash Barrier106.00 m2.28106.00 m106.00 m0.322.28
8.GSB/RBI/G-13.08 KM14.083.08 KM3.08 KM2.0614.08
Total Amount: 737.45 100   737.45
Remarks: No Remarks       Work Program Made On: 23-09-2014       Updation of work program on: 17-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-February-201552.56  lakhs
2.23-September-201549.33  lakhs
3.06-November-201569.08  lakhs
4.19-December-201546.58  lakhs
5.23-January-201646.76  lakhs
6.08-August-2016113.89  lakhs
7.04-February-201716.10  lakhs
8.30-June-201711.01  lakhs
9.31-December-201426.86  lakhs
10.31-March-201526.12  lakhs
11.22-May-201544.84  lakhs
12.06-July-201521.51  lakhs
13.31-July-201525.50  lakhs
14.29-February-201645.63  lakhs
15.31-March-201626.13  lakhs
16.06-May-201619.63  lakhs
17.28-October-201412.99  lakhs
18.22-June-201526.69  lakhs
Total 681.21  lakhs
% Payment 92.49 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 504     No. of Test Done : 514      No. of Test Passed : 504      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 142
Number of Notice(s) issued: 78

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-03-2017Ch-0/38-0/39General inspection of kuwanwala to sainik colony Motor RoadDhwajvir SinghJEUDRP R&B Karnprayag See Pic
2.04-10-2016Km 7 HM-6Inspection of PC by SE,EE,AE and TLDhwajvir SinghJEUDRP R&B Chakrata See Pic
3.27-08-2016Ch1/16Joint inspection with constant clint & contractor regarding complition of work.Om Prakash SinghSite SupervisorDSC2 R&B WB Dehradun See Pic
4.06-05-2016Ch 2/6Checking of thickness of PCDhwajvir SinghJEUDRP R&B Chakrata See Pic
5.06-05-2016Ch 2/11PC work under progressDhwajvir SinghJEUDRP R&B Chakrata See Pic
6.04-05-2016Km3 under RCC bridgeRepairing of Eroded base of of rcc bridge.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.28-04-2016Ch 3/32PC and seal coat completedLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
8.25-04-2016Ch 3/30Laying of PCDhwajvir SinghJEUDRP R&B Chakrata See Pic
9.25-04-2016Ch 3/35Rolling of PCDhwajvir SinghJEUDRP R&B Chakrata See Pic
10.25-04-2016Km1WB's team visited the site for EMP verificationLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
11.25-04-2016Km 7Undulation checkingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
12.21-04-2016Ch 1/11-1/12Construction of R/W completedDhwajvir SinghJEUDRP R&B Chakrata See Pic
13.12-04-2016Ch 7 th KmSE WB Tehri visit with EE WB Chakrata AE WB Chakrata fo4 checking of Bitumen PC workRajan NautiyalJEUDRP R&B Chakrata See Pic
14.12-04-2016Km 2Site inspection by SE WB PWD TEHRILalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
15.12-04-2016Km 7 ch 6/28Joint Inspection of PC work by SE Sir, EE sir and AE sirDhwajvir SinghJEUDRP R&B Chakrata See Pic
16.05-04-2016Km2Cc drain completeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
17.05-04-2016Km 7Seal coat under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
18.05-04-2016Km 7Premix carpet surfacingLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
19.30-03-2016Km 7Preparation for premix carpet going on.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
20.30-03-20160/37Reconstruction of washed away portionLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic