UDRP/PWD/10/19/RD/047
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
47 |
Package Name: |
UDRP/PWD/10/19/RD/047 |
Sanction Cost: |
429.21 lakhs |
District: |
Champawat |
Block: |
Champawat |
Constituency: |
Champawat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Champawat |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1355 Punav-Sipty Nayari Motor Road (8.000 KM.) (completed) |
|
Procurement: |
Package No.: 47
Package Name: UDRP/PWD/10/19/RD/047
Tender Date: 19-04-2014
Current Status: Agreement signed
Achieved on Date: 13-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/10/19/RD/047
Contractor Name: Panchghati Constructions
|
Start Date: 20-08-2014
Intended Completion Date: 11-01-2016
Original End Date: 19-11-2015
|
Total Bond Cost: 46317208.08 (463.17 lakhs)
Variation Cost: -6781420.28 (-67.81 lakhs) Hence Total Bond Cost is 39535787.8 (395.36 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1157950 for 50 days
LD Analysis for Milestone2: calculated LD is Rs 2176946 for 94 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.29 KM | 5.23 | 0.29 KM | 0.29 KM | 1.32 | 5.23 | 2. | R/Wall, B/ Wall Type Protection works | 1843.00 m | 172.64 | 1843.00 m | 1843.00 m | 43.67 | 172.64 | 3. | GSB/RBI/G-1 | 5.40 KM | 37.35 | 5.40 KM | 5.40 KM | 9.45 | 37.35 | 4. | G-2 | 5.40 KM | 27.83 | 5.40 KM | 5.40 KM | 7.04 | 27.83 | 5. | G-3 | 5.40 KM | 29.32 | 5.40 KM | 5.40 KM | 7.42 | 29.32 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.40 KM | 58.36 | 5.40 KM | 5.40 KM | 14.76 | 58.36 | 7. | Cause Way | 1.00 No | 2.40 | 1.00 No | 1.00 No | 0.61 | 2.40 | 8. | Culverts/Scupper | 16.00 No | 23.38 | 16.00 No | 16.00 No | 5.91 | 23.38 | 9. | longitudinal Drain | 5250.00 m | 9.63 | 5250.00 m | 5250.00 m | 2.44 | 9.63 | 10. | Crash Barrier | 404.00 m | 8.39 | 404.00 m | 404.00 m | 2.12 | 8.39 | 11. | Parapet | 260.00 No | 6.56 | 260.00 No | 260.00 No | 1.66 | 6.56 | 12. | Road Furniture | 101.00 No | 1.89 | 101.00 No | 101.00 No | 0.48 | 1.89 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 12.39 | 1.00 Job | 1.00 Job | 3.13 | 12.39 |
Total Amount: |
395.37 |
|
100 |
395.37 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2014
Updation of work program on:
20-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-February-2015 | 58.11 lakhs |
2. | 31-March-2015 | 37.53 lakhs |
3. | 16-June-2015 | 25.00 lakhs |
4. | 30-June-2015 | 28.00 lakhs |
5. | 31-July-2015 | 6.50 lakhs |
6. | 29-September-2015 | 39.18 lakhs |
7. | 31-October-2015 | 42.00 lakhs |
8. | 31-August-2016 | 155.98 lakhs |
Total |
392.3 lakhs |
% Payment |
99.23 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 195 |
Number of Notice(s) issued: 58 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-08-2016 | 4+200 | Tree Plantation | Manjeet Saini | JE | UDRP R&B Champawat | See Pic |
2. | 12-08-2016 | 4+900 | Tree plantation | Manjeet Saini | JE | UDRP R&B Champawat | See Pic |
3. | 12-08-2016 | 4+900 | Tree Plantation | Manjeet Saini | JE | UDRP R&B Champawat | See Pic |
4. | 11-08-2016 | 5+400 | Tree plantation | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
5. | 20-05-2016 | 4+100 | Catchpit | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
6. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
7. | 19-05-2016 | 0+400 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
8. | 19-05-2016 | 0+400 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
9. | 19-05-2016 | 0+100 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
10. | 19-05-2016 | 0+100 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
11. | 19-05-2016 | 0+080 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
12. | 19-05-2016 | 0+070 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
13. | 19-05-2016 | 0+040 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
14. | 19-05-2016 | 0+050 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
15. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
16. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
17. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
18. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
19. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
20. | 10-05-2016 | 0+150 | Site inspection by CE Sir with SE/EE With TL/RE DSC4 | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
|
|