UDRP/PWD/08/06/RD/045
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
45 |
Package Name: |
UDRP/PWD/08/06/RD/045 |
Sanction Cost: |
626.60 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1115 Dhlam Khunoli Motor Road (8.000 KM.) (completed) | 2 1122 Kameridevi Syakot Motor road (9.500 KM.) (completed) |
|
Procurement: |
Package No.: 45
Package Name: UDRP/PWD/08/06/RD/045
Tender Date: 19-04-2014
Current Status: Agreement signed
Achieved on Date: 13-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/045
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 20-11-2014
Intended Completion Date: 31-08-2017
Original End Date: 19-02-2016
|
Total Bond Cost: 41607857.19 (416.08 lakhs)
Variation Cost: 21048924.06 (210.49 lakhs) Hence Total Bond Cost is 62656781.25 (626.57 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 686532 for 33 days
LD Analysis for Milestone2: calculated LD is Rs 2829344 for 136 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.78 KM | 25.07 | 0.78 KM | 0.78 KM | 4.07 | 25.07 | 2. | R/Wall, B/ Wall Type Protection works | 1576.00 m | 67.76 | 1621.00 m | 1621.00 m | 10.72 | 67.76 | 3. | GSB/RBI/G-1 | 6.85 KM | 59.70 | 6.85 KM | 6.85 KM | 9.21 | 59.70 | 4. | G-2 | 5.00 KM | 24.32 | 5.00 KM | 5.00 KM | 5.13 | 24.32 | 5. | G-3 | 6.85 KM | 41.85 | 6.85 KM | 6.85 KM | 7 | 41.85 | 6. | PC/CC i/c Prime Coat, Tack Coat | 8.00 KM | 135.36 | 6.85 KM | 6.85 KM | 23.08 | 135.36 | 7. | Cause Way | 7.00 No | 99.61 | 6.00 No | 6.00 No | 15.54 | 99.61 | 8. | Culverts/Scupper | 25.00 No | 98.50 | 25.00 No | 25.00 No | 14.55 | 98.50 | 9. | longitudinal Drain | 5680.00 m | 9.26 | 7100.00 m | 7100.00 m | 1.43 | 9.26 | 10. | Crash Barrier | 80.00 m | 3.08 | 3514.00 m | 3514.00 m | 0.46 | 3.08 | 11. | Parapet | 150.00 No | 39.18 | 66.00 No | 66.00 No | 4.74 | 39.18 | 12. | Road Furniture | 145.00 No | 4.98 | 58.00 No | 58.00 No | 0.75 | 4.98 | 13. | Other Allied Works & Finishing Work | 7.00 Job | 22.00 | 7.00 Job | 7.00 Job | 3.32 | 22.00 |
Total Amount: |
630.67 |
|
100 |
630.67 |
|
Remarks:
No Remarks
Work Program Made On:
24-02-2015
Updation of work program on:
14-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 56.67 lakhs |
2. | 29-June-2015 | 23.30 lakhs |
3. | 26-August-2015 | 55.69 lakhs |
4. | 30-October-2015 | 63.20 lakhs |
5. | 08-April-2016 | 0.10 lakhs |
6. | 16-May-2016 | 27.18 lakhs |
7. | 31-May-2016 | 33.27 lakhs |
8. | 30-July-2016 | 68.85 lakhs |
9. | 27-October-2016 | 55.48 lakhs |
10. | 29-December-2016 | 49.64 lakhs |
11. | 22-February-2017 | 0.29 lakhs |
12. | 25-March-2017 | 46.99 lakhs |
13. | 30-June-2017 | 61.38 lakhs |
14. | 07-October-2017 | 100.99 lakhs |
15. | 16-November-2018 | 0.72 lakhs |
16. | 08-December-2016 | 0.09 lakhs |
Total |
643.84 lakhs |
% Payment |
102.76 % |
|
Advance Amount: 182.38 lakhs
Recovered Amount: 182.39 lakhs
Balance to be Recovered -0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 100 |
Number of Notice(s) issued: 100 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-01-2017 | Ch 4.700 | Site inspection by EE sir PD PWD bageshwar.and SDM kanda . | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 12-01-2017 | Ch 4.700 | PC thickness checking and found 25 mm. By EE sir PD bageshwar. | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 12-01-2017 | Ch 2.280 | PC thickness checking by EE sir PWD PD bageshwar and EE pmgsy bageshwar. And found 22 mm. | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 08-12-2016 | 7+500 | Pc & seal coat completed, shoulder work yet to be done. | Naresh Mittal | TL | DSC5 R&B WB Bageshwar | See Pic |
5. | 02-12-2016 | At plant | Bitumen extraction test of PC material and found 3.76% | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 02-12-2016 | At plant | Bitumen extraction test of PC material | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 28-11-2016 | At plant | Binder content of PMC and found 3.75 % | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
8. | 22-11-2016 | Ch 5.200 | Rolling over seal coat . | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 16-11-2016 | Ch 5.450 | Spreading of stone dust over G3 layer | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 16-11-2016 | Ch 5.350 | Total crust thickness checking and found 25 cm. Hence as per specification. | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 16-11-2016 | Ch 5.200 | Total Crust thickness checking and found 26 cm. | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 16-11-2016 | Ch 5.200 | Rolling over G3 surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 16-11-2016 | Ch 5.200 | Stone dust over G3 surface. | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 16-11-2016 | Ch 8.00 | End point and project information board. | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 16-11-2016 | Ch 9.500 | End point of road | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 16-11-2016 | Ch 0.000 | Information board , correction required. | Jagdish Narayan Meena | unknown | unknown | See Pic |
17. | 16-11-2016 | 0+000 | Project information board, provision of work PC & seal coat not a BM & SDBC | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 16-11-2016 | End point of the Road | Project information board | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 16-11-2016 | 4+055 | WBM GR 3 ready for PMC | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 26-10-2016 | Ch 8.200 | Dismantling of kharanja , and instruct to do again. | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|