Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/06/RD/045 Agreement signed
Project: UDRP-RB Package No.: 45 Package Name: UDRP/PWD/08/06/RD/045 Sanction Cost: 626.60  lakhs
District: Bageshwar Block: Bageshwar Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  1115   Dhlam Khunoli Motor Road (8.000 KM.) (completed)
2  1122   Kameridevi Syakot Motor road (9.500 KM.) (completed)
Procurement:
Package No.: 45        Package Name: UDRP/PWD/08/06/RD/045        Tender Date: 19-04-2014        Current Status: Agreement signed        Achieved on Date: 13-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/045        Contractor Name: ESPAN Infrastructure Ltd       
Start Date: 20-11-2014        Intended Completion Date: 31-08-2017        Original End Date:  19-02-2016
Total Bond Cost: 41607857.19 (416.08 lakhs)        Variation Cost: 21048924.06 (210.49 lakhs)     Hence Total Bond Cost is   62656781.25 (626.57 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 686532 for 33 days        LD Analysis for Milestone2: calculated LD is Rs 2829344 for 136 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.78 KM25.070.78 KM0.78 KM4.0725.07
2.R/Wall, B/ Wall Type Protection works1576.00 m67.761621.00 m1621.00 m10.7267.76
3.GSB/RBI/G-16.85 KM59.706.85 KM6.85 KM9.2159.70
4.G-25.00 KM24.325.00 KM5.00 KM5.1324.32
5.G-36.85 KM41.856.85 KM6.85 KM741.85
6.PC/CC i/c Prime Coat, Tack Coat8.00 KM135.366.85 KM6.85 KM23.08135.36
7.Cause Way7.00 No99.616.00 No6.00 No15.5499.61
8.Culverts/Scupper 25.00 No98.5025.00 No25.00 No14.5598.50
9.longitudinal Drain5680.00 m9.267100.00 m7100.00 m1.439.26
10.Crash Barrier80.00 m3.083514.00 m3514.00 m0.463.08
11.Parapet150.00 No39.1866.00 No66.00 No4.7439.18
12.Road Furniture145.00 No4.9858.00 No58.00 No0.754.98
13.Other Allied Works & Finishing Work 7.00 Job22.007.00 Job7.00 Job3.3222.00
Total Amount: 630.67 100   630.67
Remarks: No Remarks       Work Program Made On: 24-02-2015       Updation of work program on: 14-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-May-201556.67  lakhs
2.29-June-201523.30  lakhs
3.26-August-201555.69  lakhs
4.30-October-201563.20  lakhs
5.08-April-20160.10  lakhs
6.16-May-201627.18  lakhs
7.31-May-201633.27  lakhs
8.30-July-201668.85  lakhs
9.27-October-201655.48  lakhs
10.29-December-201649.64  lakhs
11.22-February-20170.29  lakhs
12.25-March-201746.99  lakhs
13.30-June-201761.38  lakhs
14.07-October-2017100.99  lakhs
15.16-November-20180.72  lakhs
16.08-December-20160.09  lakhs
Total 643.84  lakhs
% Payment 102.76 %
Advance Amount:  182.38  lakhs        Recovered Amount:  182.39  lakhs        Balance to be Recovered  -0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 615     No. of Test Done : 570      No. of Test Passed : 544      No. of Test Failed : 26   Test report of this package
Number of Pics Available on Web Repository: 100
Number of Notice(s) issued: 100

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-01-2017Ch 4.700Site inspection by EE sir PD PWD bageshwar.and SDM kanda .Jagdish Narayan Meenaunknownunknown See Pic
2.12-01-2017Ch 4.700PC thickness checking and found 25 mm. By EE sir PD bageshwar.Jagdish Narayan Meenaunknownunknown See Pic
3.12-01-2017Ch 2.280PC thickness checking by EE sir PWD PD bageshwar and EE pmgsy bageshwar. And found 22 mm.Jagdish Narayan Meenaunknownunknown See Pic
4.08-12-20167+500Pc & seal coat completed, shoulder work yet to be done.Naresh MittalTLDSC5 R&B WB Bageshwar See Pic
5.02-12-2016At plantBitumen extraction test of PC material and found 3.76%Jagdish Narayan Meenaunknownunknown See Pic
6.02-12-2016At plantBitumen extraction test of PC materialJagdish Narayan Meenaunknownunknown See Pic
7.28-11-2016At plantBinder content of PMC and found 3.75 %Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
8.22-11-2016Ch 5.200Rolling over seal coat .Jagdish Narayan Meenaunknownunknown See Pic
9.16-11-2016Ch 5.450Spreading of stone dust over G3 layerJagdish Narayan Meenaunknownunknown See Pic
10.16-11-2016Ch 5.350Total crust thickness checking and found 25 cm. Hence as per specification.Jagdish Narayan Meenaunknownunknown See Pic
11.16-11-2016Ch 5.200Total Crust thickness checking and found 26 cm.Jagdish Narayan Meenaunknownunknown See Pic
12.16-11-2016Ch 5.200Rolling over G3 surfaceJagdish Narayan Meenaunknownunknown See Pic
13.16-11-2016Ch 5.200Stone dust over G3 surface.Jagdish Narayan Meenaunknownunknown See Pic
14.16-11-2016Ch 8.00End point and project information board.Jagdish Narayan Meenaunknownunknown See Pic
15.16-11-2016Ch 9.500End point of roadJagdish Narayan Meenaunknownunknown See Pic
16.16-11-2016Ch 0.000Information board , correction required.Jagdish Narayan Meenaunknownunknown See Pic
17.16-11-20160+000Project information board, provision of work PC & seal coat not a BM & SDBCMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
18.16-11-2016End point of the RoadProject information boardMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
19.16-11-20164+055WBM GR 3 ready for PMCMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
20.26-10-2016Ch 8.200Dismantling of kharanja , and instruct to do again.Jagdish Narayan Meenaunknownunknown See Pic