Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/39/RD/043 Agreement signed
Project: UDRP-RB Package No.: 43 Package Name: UDRP/PWD/03/39/RD/043 Sanction Cost: 538.57  lakhs
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2531   Kotkhal jagtoli MR (7.000 KM.) (completed)
Procurement:
Package No.: 43        Package Name: UDRP/PWD/03/39/RD/043        Tender Date: 16-06-2014        Current Status: Agreement signed        Achieved on Date: 25-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/39/RD/043        Contractor Name: Sahab Singh Rawat & Brothers       
Start Date: 01-12-2014        Intended Completion Date: 03-05-2017        Original End Date:  29-02-2016
Total Bond Cost: 45857772.73 (458.58 lakhs)        Variation Cost: 10679547.72 (106.8 lakhs)     Hence Total Bond Cost is   56537320.45 (565.37 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 596154 for 26 days        LD Analysis for Milestone2: calculated LD is Rs 412722 for 18 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.87 KM10.130.87 KM0.87 KM1.8510.13
2.R/Wall, B/ Wall Type Protection works663.00 m96.88663.00 m663.00 m17.6696.88
3.GSB/RBI/G-16.91 KM80.756.91 KM6.91 KM14.7280.75
4.G-26.91 KM54.506.91 KM6.91 KM9.9354.50
5.G-36.91 KM54.956.91 KM6.91 KM10.0254.95
6.PC/CC i/c Prime Coat, Tack Coat6.91 KM121.426.91 KM6.91 KM22.13121.42
7.Cause Way3.00 No2.863.00 No3.00 No0.522.86
8.Culverts/Scupper 24.00 No53.6024.00 No24.00 No9.7753.60
9.longitudinal Drain7250.00 m27.037250.00 m7250.00 m4.9327.03
10.Parapet140.00 No4.21140.00 No140.00 No0.774.21
11.Road Furniture36.00 No0.3536.00 No36.00 No0.060.35
12.Other Allied Works & Finishing Work 1.00 Job42.011.00 Job1.00 Job7.6642.01
Total Amount: 548.69 100   548.69
Remarks: Lab not established       Work Program Made On: 28-09-2015       Updation of work program on: 19-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-201523.75  lakhs
2.09-June-20159.48  lakhs
3.13-August-201553.78  lakhs
4.24-September-201547.91  lakhs
5.26-December-201544.82  lakhs
6.30-January-201612.36  lakhs
7.04-May-201658.58  lakhs
8.18-May-201650.32  lakhs
9.29-June-201644.26  lakhs
10.27-October-201637.01  lakhs
11.09-March-201784.32  lakhs
12.22-May-201737.10  lakhs
13.04-August-201737.54  lakhs
Total 541.23  lakhs
% Payment 95.73 %
Advance Amount:  46.71  lakhs        Recovered Amount:  46.71  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 241     No. of Test Done : 240      No. of Test Passed : 229      No. of Test Failed : 11   Test report of this package
Number of Pics Available on Web Repository: 111
Number of Notice(s) issued: 72

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-11-20178+950CME and EE sir site visit observation compliance of CE sir on dated 2-11-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
2.04-11-20179+160CME and EE sir site visit observation compliance of CE on dated 2-11-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
3.19-04-20177+700Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
4.18-04-20177+700Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
5.18-04-20177+600Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
6.18-04-20177+325Compaction of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
7.17-04-20176+975Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
8.17-04-20177+250Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
9.16-04-20177+025Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
10.14-04-20176+650Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
11.14-04-20176+800Premix carpet workNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
12.13-04-20176+600Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
13.13-04-20177+500Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
14.12-04-2017CH 6.800Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
15.12-04-20177+00Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
16.12-04-20177+000Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
17.11-04-20177+300Laying of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
18.11-04-20177+400Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
19.10-04-20178+300Laying seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
20.10-04-20178+420Compaction at premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic