UDRP/PWD/03/39/RD/042
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
42 |
Package Name: |
UDRP/PWD/03/39/RD/042 |
Sanction Cost: |
612.37 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2540 Rudraprayag- gandhar- Garhidhar-dasjula MR (19.500 KM.) (completed) |
|
Procurement: |
Package No.: 42
Package Name: UDRP/PWD/03/39/RD/042
Tender Date: 21-10-2014
Current Status: Agreement signed
Achieved on Date: 21-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/39/RD/042
Contractor Name: Crystal Infrastructure
|
Start Date: 28-04-2015
Intended Completion Date: 30-11-2018
Original End Date: 27-07-2016
|
Total Bond Cost: 44954521.83 (449.55 lakhs)
Variation Cost: 11761912.88 (117.62 lakhs) Hence Total Bond Cost is 56716434.71 (567.16 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1910545 for 85 days
LD Analysis for Milestone2: calculated LD is Rs 2719717 for 121 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.23 KM | 71.80 | 4.23 KM | 4.23 KM | 12.66 | 71.80 | 2. | R/Wall, B/ Wall Type Protection works | 5850.00 m | 80.28 | 5850.00 m | 5850.00 m | 14.16 | 80.28 | 3. | GSB/RBI/G-1 | 7.00 KM | 42.98 | 7.00 KM | 7.00 KM | 7.58 | 42.98 | 4. | G-2 | 7.00 KM | 39.57 | 7.00 KM | 7.00 KM | 6.98 | 39.57 | 5. | G-3 | 7.50 KM | 58.27 | 7.00 KM | 7.00 KM | 10.27 | 58.27 | 6. | PC/CC i/c Prime Coat, Tack Coat | 12.50 KM | 147.28 | 12.50 KM | 12.50 KM | 25.97 | 147.28 | 7. | Cause Way | 7.00 No | 14.82 | 5.00 No | 5.00 No | 2.61 | 14.82 | 8. | Culverts/Scupper | 8.00 No | 19.15 | 8.00 No | 8.00 No | 3.38 | 19.15 | 9. | longitudinal Drain | 12500.00 m | 32.53 | 12500.00 m | 12500.00 m | 5.74 | 32.53 | 10. | Crash Barrier | 910.00 m | 23.77 | 910.00 m | 910.00 m | 4.19 | 23.77 | 11. | Parapet | 568.00 No | 16.49 | 568.00 No | 568.00 No | 2.91 | 16.49 | 12. | Road Furniture | 62.00 No | 4.05 | 62.00 No | 62.00 No | 0.72 | 4.05 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 16.16 | 1.00 Job | 1.00 Job | 2.85 | 16.16 |
Total Amount: |
567.15 |
|
100 |
567.15 |
|
Remarks:
no remark
Work Program Made On:
06-10-2015
Updation of work program on:
12-11-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-June-2015 | 19.25 lakhs |
2. | 13-August-2015 | 11.40 lakhs |
3. | 10-September-2015 | 13.84 lakhs |
4. | 10-October-2015 | 12.84 lakhs |
5. | 07-November-2015 | 16.35 lakhs |
6. | 11-December-2015 | 10.62 lakhs |
7. | 30-December-2015 | 8.73 lakhs |
8. | 28-January-2016 | 11.31 lakhs |
9. | 17-March-2016 | 17.51 lakhs |
10. | 20-May-2016 | 39.98 lakhs |
11. | 06-June-2016 | 20.79 lakhs |
12. | 28-June-2016 | 44.28 lakhs |
13. | 11-September-2016 | 9.49 lakhs |
14. | 07-October-2016 | 14.20 lakhs |
15. | 28-February-2017 | 29.16 lakhs |
16. | 18-April-2017 | 23.92 lakhs |
17. | 24-June-2017 | 21.98 lakhs |
18. | 04-August-2017 | 14.45 lakhs |
19. | 23-September-2017 | 18.89 lakhs |
20. | 18-October-2017 | 18.14 lakhs |
21. | 09-November-2017 | 21.47 lakhs |
22. | 15-December-2017 | 20.13 lakhs |
23. | 06-April-2018 | 14.90 lakhs |
24. | 30-August-2018 | 20.78 lakhs |
25. | 24-December-2018 | 27.21 lakhs |
26. | 31-May-2019 | 37.87 lakhs |
Total |
519.49 lakhs |
% Payment |
91.59 % |
|
Advance Amount: 85.69 lakhs
Recovered Amount: 85.69 lakhs
Balance to be Recovered -0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 174 |
Number of Notice(s) issued: 136 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-02-2019 | Starting point | Joint inspection with AE Guptkashi | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 16-03-2018 | 28+000 | Se sir visit | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
3. | 13-03-2018 | 25+700 | Se. Sir and A. e. Mam site visit | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
4. | 04-02-2018 | 27+900 | Gram sabha held for grievance discussion at gadhidhar dated 04/02/2018 | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
5. | 21-11-2017 | | Wbm g3 water sprinkling | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
6. | 16-11-2017 | 27+200 | Wbm g3 gradation test, results found by ok | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
7. | 04-11-2017 | 27+800 | Pc laying | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
8. | 26-10-2017 | 23+750 | Pc work | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
9. | 06-10-2017 | 27+900 | R. E. Sir instructions to contractor for subgrade preparation, rectification of undulation and subgrade preparations, road wirth rectification | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
10. | 20-09-2017 | 0+000 | S. E. Sir visit | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
11. | 22-08-2017 | 14+300 | Aam sabha along with R.E. pradhan, chopda, J. E. | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
12. | 01-08-2017 | 23+500 | Srmd | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
13. | 11-05-2017 | 24+400 | Stone collect for WBM | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
14. | 14-03-2017 | 25+900 | Hill side cutting | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
15. | 14-03-2017 | 13+350 | Construction of parapet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
16. | 16-02-2017 | Chainage 24+300 | Hill side cutting | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
17. | 13-02-2017 | 17+800 site lab AIV test | AIV test of G1,G2 | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
18. | 13-02-2017 | 16+800 | Construction of parapet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
19. | 13-02-2017 | At site lab | AIV test | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
20. | 09-02-2017 | 24+060 | Hill side cutting | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
|
|