Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/39/RD/042 Agreement signed
Project: UDRP-RB Package No.: 42 Package Name: UDRP/PWD/03/39/RD/042 Sanction Cost: 612.37  lakhs
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2540   Rudraprayag- gandhar- Garhidhar-dasjula MR (19.500 KM.) (completed)
Procurement:
Package No.: 42        Package Name: UDRP/PWD/03/39/RD/042        Tender Date: 21-10-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/39/RD/042        Contractor Name: Crystal Infrastructure       
Start Date: 28-04-2015        Intended Completion Date: 30-11-2018        Original End Date:  27-07-2016
Total Bond Cost: 44954521.83 (449.55 lakhs)        Variation Cost: 11761912.88 (117.62 lakhs)     Hence Total Bond Cost is   56716434.71 (567.16 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1910545 for 85 days        LD Analysis for Milestone2: calculated LD is Rs 2719717 for 121 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.23 KM71.804.23 KM4.23 KM12.6671.80
2.R/Wall, B/ Wall Type Protection works5850.00 m80.285850.00 m5850.00 m14.1680.28
3.GSB/RBI/G-17.00 KM42.987.00 KM7.00 KM7.5842.98
4.G-27.00 KM39.577.00 KM7.00 KM6.9839.57
5.G-37.50 KM58.277.00 KM7.00 KM10.2758.27
6.PC/CC i/c Prime Coat, Tack Coat12.50 KM147.2812.50 KM12.50 KM25.97147.28
7.Cause Way7.00 No14.825.00 No5.00 No2.6114.82
8.Culverts/Scupper 8.00 No19.158.00 No8.00 No3.3819.15
9.longitudinal Drain12500.00 m32.5312500.00 m12500.00 m5.7432.53
10.Crash Barrier910.00 m23.77910.00 m910.00 m4.1923.77
11.Parapet568.00 No16.49568.00 No568.00 No2.9116.49
12.Road Furniture62.00 No4.0562.00 No62.00 No0.724.05
13.Other Allied Works & Finishing Work 1.00 Job16.161.00 Job1.00 Job2.8516.16
Total Amount: 567.15 100   567.15
Remarks: no remark       Work Program Made On: 06-10-2015       Updation of work program on: 12-11-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-June-201519.25  lakhs
2.13-August-201511.40  lakhs
3.10-September-201513.84  lakhs
4.10-October-201512.84  lakhs
5.07-November-201516.35  lakhs
6.11-December-201510.62  lakhs
7.30-December-20158.73  lakhs
8.28-January-201611.31  lakhs
9.17-March-201617.51  lakhs
10.20-May-201639.98  lakhs
11.06-June-201620.79  lakhs
12.28-June-201644.28  lakhs
13.11-September-20169.49  lakhs
14.07-October-201614.20  lakhs
15.28-February-201729.16  lakhs
16.18-April-201723.92  lakhs
17.24-June-201721.98  lakhs
18.04-August-201714.45  lakhs
19.23-September-201718.89  lakhs
20.18-October-201718.14  lakhs
21.09-November-201721.47  lakhs
22.15-December-201720.13  lakhs
23.06-April-201814.90  lakhs
24.30-August-201820.78  lakhs
25.24-December-201827.21  lakhs
26.31-May-201937.87  lakhs
Total 519.49  lakhs
% Payment 91.59 %
Advance Amount:  85.69  lakhs        Recovered Amount:  85.69  lakhs        Balance to be Recovered  -0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 643     No. of Test Done : 693      No. of Test Passed : 628      No. of Test Failed : 65   Test report of this package
Number of Pics Available on Web Repository: 174
Number of Notice(s) issued: 136

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-02-2019Starting pointJoint inspection with AE GuptkashiLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.16-03-201828+000Se sir visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
3.13-03-201825+700Se. Sir and A. e. Mam site visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
4.04-02-201827+900Gram sabha held for grievance discussion at gadhidhar dated 04/02/2018Prashant KumarQCDSC WB SPW Rudraprayag See Pic
5.21-11-2017Wbm g3 water sprinklingPrashant KumarQCDSC WB SPW Rudraprayag See Pic
6.16-11-201727+200Wbm g3 gradation test, results found by okPrashant KumarQCDSC WB SPW Rudraprayag See Pic
7.04-11-201727+800Pc layingPrashant KumarQCDSC WB SPW Rudraprayag See Pic
8.26-10-201723+750Pc workPrashant KumarQCDSC WB SPW Rudraprayag See Pic
9.06-10-201727+900R. E. Sir instructions to contractor for subgrade preparation, rectification of undulation and subgrade preparations, road wirth rectificationPrashant KumarQCDSC WB SPW Rudraprayag See Pic
10.20-09-20170+000S. E. Sir visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
11.22-08-201714+300Aam sabha along with R.E. pradhan, chopda, J. E.Prashant KumarQCDSC WB SPW Rudraprayag See Pic
12.01-08-201723+500SrmdPrashant KumarQCDSC WB SPW Rudraprayag See Pic
13.11-05-201724+400Stone collect for WBMNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
14.14-03-201725+900Hill side cuttingParvindar SinghJEUDRP R&B Guptkashi See Pic
15.14-03-201713+350Construction of parapetParvindar SinghJEUDRP R&B Guptkashi See Pic
16.16-02-2017Chainage 24+300Hill side cuttingParvindar SinghJEUDRP R&B Guptkashi See Pic
17.13-02-201717+800 site lab AIV testAIV test of G1,G2Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
18.13-02-201716+800Construction of parapetParvindar SinghJEUDRP R&B Guptkashi See Pic
19.13-02-2017At site labAIV testParvindar SinghJEUDRP R&B Guptkashi See Pic
20.09-02-201724+060Hill side cuttingParvindar SinghJEUDRP R&B Guptkashi See Pic