UDRP/PWD/04/46/RD/004
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
4 |
Package Name: |
UDRP/PWD/04/46/RD/004 |
Sanction Cost: |
333.00 lakhs |
District: |
Tehri |
Block: |
Kouldhar |
Constituency: |
Dhanaulti |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
9 |
Subproject in this package |
1 2704 Ghugti Dhunga Dhamari Maindkhal Motor road (8.000 KM.) (completed) | 2 2716 Indra goan Katkhet Motor road (2.000 KM.) (completed) | 3 2733 kamand Jawarna Motor road (8.000 KM.) (completed) | 4 2762 Laluri Ghiya Koti kayrda challi Motor road (2.750 KM.) (completed) | 5 2763 Laluri Koti Mahoron Ki Manjkhet Motor road (5.000 KM.) (completed) | 6 2771 Maindkhal Bangiyal Jawarna Motor road (6.000 KM.) (completed) | 7 2772 Maindkhal Gair Nagun Motor road (6.000 KM.) (completed) | 8 2852 Syansu pul to Ratwari Nakot Kholi Motor road (4.000 KM.) (completed) | 9 2871 Uniyal goan Nagraja dhar Motor road (5.000 KM.) (completed) |
|
Procurement: |
Package No.: 4
Package Name: UDRP/PWD/04/46/RD/004
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 12-06-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/46/RD/004
Contractor Name: Vijay Engineering Associates
|
Start Date: 19-06-2014
Intended Completion Date: 15-03-2016
Original End Date: 18-09-2015
|
Total Bond Cost: 37077339.47 (370.77 lakhs)
Variation Cost: -2929148.67 (-29.29 lakhs) Hence Total Bond Cost is 34148190.8 (341.48 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 2156.00 m | 182.93 | 2562.24 m | 2562.24 m | 54.59 | 182.93 | 2. | Culverts/Scupper | 34.00 No | 94.66 | 37.00 No | 37.00 No | 26.94 | 94.66 | 3. | longitudinal Drain | 3685.50 m | 53.84 | 4260.00 m | 4260.00 m | 15.95 | 53.84 | 4. | Hill side Cutting & Slip clearence | 1.81 KM | 2.61 | 2.34 KM | 2.34 KM | 0.72 | 2.61 | 5. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 6. | G-2 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 7. | G-3 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 8. | PC/CC i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 9. | Cause Way | 2.00 No | 7.83 | 2.00 No | 2.00 No | 1.79 | 7.83 | 10. | Road Furniture | 1.00 No | 0.12 | 1.00 No | 1.00 No | 0.02 | 0.12 |
Total Amount: |
341.99 |
|
100 |
341.99 |
|
Remarks:
Package Completed
Work Program Made On:
27-06-2014
Updation of work program on:
17-11-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 36.93 lakhs |
2. | 31-December-2014 | 39.81 lakhs |
3. | 24-February-2015 | 58.50 lakhs |
4. | 31-March-2015 | 58.14 lakhs |
5. | 30-May-2015 | 37.45 lakhs |
6. | 28-August-2015 | 65.21 lakhs |
7. | 28-March-2016 | 14.88 lakhs |
8. | 29-March-2017 | 9.64 lakhs |
9. | 06-November-2015 | 20.44 lakhs |
Total |
341 lakhs |
% Payment |
99.86 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.25 lakhs
Balance to be Recovered -0.25 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 120 |
Number of Notice(s) issued: 84 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-07-2016 | Ch.1+800 | R wall bended | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
2. | 30-07-2016 | Ch.4+000 to 4+100 | Wire crates | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
3. | 30-07-2016 | Ch. 2+150 | Scupper | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
4. | 30-07-2016 | Ch.0+100 | Slip on the road | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
5. | 30-07-2016 | Ch.0+200 | Road damaged due to heavy rain | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
6. | 30-07-2016 | Ch.0+250 | Wire crates sliding | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
7. | 30-07-2016 | Ch.0+150 | R wall | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
8. | 30-07-2016 | Ch.0+100 | Cut of road side | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
9. | 30-07-2016 | Ch.0+050 | R wall | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
10. | 30-07-2016 | Ch.0+000 | Start point of this road | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
11. | 30-07-2016 | Ch.2+200 | Wire crates | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
12. | 30-07-2016 | Ch.2+250 | Wire crates | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
13. | 30-07-2016 | Ch. 2+225 | Scupper | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
14. | 30-07-2016 | Ch.2+050 | Wire crates | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
15. | 30-07-2016 | Ch.0+000 | Information baoard | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
16. | 30-07-2016 | Ch.1+800 | Not Matar able this road in rainy season | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
17. | 30-07-2016 | Ch.2+650 | R wall | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
18. | 30-07-2016 | 4+200 | Water stock in road | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
19. | 30-07-2016 | 0+075 | R wall at ch 0+075 | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
20. | 01-04-2016 | Ch.0.950 | Laying of pipe line | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
|
|