UDRP/PWD/04/36/RD/039
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
39 |
Package Name: |
UDRP/PWD/04/36/RD/039 |
Sanction Cost: |
1409.76 lakhs |
District: |
Tehri |
Block: |
Jakhanidhar |
Constituency: |
Tehri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2630 Anjanisain to Punanu MR (9.500 KM.) (completed) | 2 2727 Jakhanidhar Garakot Paurikhal MR (24.500 KM.) (completed) |
|
Procurement: |
Package No.: 39
Package Name: UDRP/PWD/04/36/RD/039
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 12-06-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/36/RD/039
Contractor Name: Puran Chandra Ramola and Brothers
|
Start Date: 19-06-2014
Intended Completion Date: 18-12-2015
Original End Date: 18-09-2015
|
Total Bond Cost: 125298423.85 (1252.98 lakhs)
Variation Cost: 15604981.66 (156.05 lakhs) Hence Total Bond Cost is 140903405.51 (1409.03 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2693907 for 43 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.08 KM | 9.94 | 2.82 KM | 2.82 KM | 0.8 | 9.94 | 2. | R/Wall, B/ Wall Type Protection works | 2119.50 m | 183.43 | 2361.00 m | 2361.00 m | 14.71 | 183.43 | 3. | GSB/RBI/G-1 | 0.59 KM | 4.31 | 0.62 KM | 0.62 KM | 0.34 | 4.31 | 4. | G-2 | 2.25 KM | 10.09 | 2.91 KM | 2.91 KM | 0.81 | 10.09 | 5. | G-3 | 10.59 KM | 62.53 | 11.19 KM | 11.19 KM | 5.02 | 62.53 | 6. | PC/CC i/c Prime Coat, Tack Coat | 34.00 KM | 356.53 | 33.87 KM | 33.87 KM | 28.64 | 356.53 | 7. | Cause Way | 18.00 No | 141.66 | 19.00 No | 19.00 No | 11.36 | 141.66 | 8. | Culverts/Scupper | 36.00 No | 85.87 | 33.00 No | 33.00 No | 6.89 | 85.87 | 9. | longitudinal Drain | 23182.00 m | 334.30 | 32800.00 m | 32800.00 m | 26.85 | 334.30 | 10. | Crash Barrier | 2173.00 m | 47.55 | 2188.00 m | 2188.00 m | 3.82 | 47.55 | 11. | Road Furniture | 34.50 No | 9.41 | 186.50 No | 186.50 No | 0.75 | 9.41 |
Total Amount: |
1245.62 |
|
100 |
1245.62 |
|
Remarks:
Project completed
Work Program Made On:
12-08-2014
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 100.00 lakhs |
2. | 30-November-2014 | 27.70 lakhs |
3. | 24-February-2015 | 166.57 lakhs |
4. | 31-March-2015 | 242.04 lakhs |
5. | 19-May-2015 | 187.37 lakhs |
6. | 09-June-2015 | 74.13 lakhs |
7. | 03-July-2015 | 121.67 lakhs |
8. | 05-August-2015 | 155.00 lakhs |
9. | 26-September-2015 | 144.10 lakhs |
10. | 07-November-2015 | 82.78 lakhs |
11. | 08-December-2015 | 30.89 lakhs |
12. | 31-March-2017 | 16.25 lakhs |
13. | 31-December-2014 | 32.00 lakhs |
14. | 18-August-2015 | 19.33 lakhs |
Total |
1399.83 lakhs |
% Payment |
99.35 % |
|
Advance Amount: 193.58 lakhs
Recovered Amount: 193.58 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 143 |
Number of Notice(s) issued: 66 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-08-2016 | 15.200 | Skip clearance n road opening | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 20-08-2016 | 9.500 | Joint inspection with Civil div. | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 19-08-2016 | 0.00 | Plantation | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
4. | 13-08-2016 | Ch.4+200 | Joint inspection | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
5. | 13-08-2016 | Ch.2+500 | Join inspection of completed road | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
6. | 13-08-2016 | Ch.0+000 | Plantation in pkg 39 Jakhnidhar garakot motor road | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
7. | 13-08-2016 | Ch.0+010 | Plantation | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
8. | 13-08-2016 | Start of road | Plantation in pkg 39 Anjanisen punanu motor road | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
9. | 10-08-2016 | 0.00 | Plantation by AE | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
10. | 10-03-2016 | 0.900 | Inspection of C/Way by Malik sir WB | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
11. | 24-12-2015 | Km3.500 | Village path yet to be repair | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
12. | 24-12-2015 | Km4.025 | Old suppers yet to be clean | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
13. | 24-12-2015 | Km3.675 | Suppers yet to be clean on pkg 039 | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
14. | 24-12-2015 | Km3.250 | Suppers yet to be clean on pkg 039 | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
15. | 24-12-2015 | Km0.00 | Pkg 039Jakhanidhar Garakot Motor Road had been completed | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
16. | 22-10-2015 | Km1.000_4.000 | Work completed on Anjanisain Punanu Motor Road | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
17. | 22-10-2015 | Km 0.100 | Work completed of Anjanisain Punanu Motor Road | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
18. | 22-10-2015 | Km0.025 | Starting point of Anjanisain Penanu Motor Road | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
19. | 24-07-2015 | Km15.200_15.400 | Road closed due to chronic slip | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
20. | 24-07-2015 | Km22.200_22.400 | Chronic slide zone | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
|
|