Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/05/RD/038 Agreement signed
Project: UDRP-RB Package No.: 38 Package Name: UDRP/PWD/08/05/RD/038 Sanction Cost: 606.42  lakhs
District: Bageshwar Block: Bageshwar Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision No.of Sub project : 2
Subproject in this package
1  1123   kanda- Mantoli MR (5.000 KM.) (completed)
2  1131   Vijaypur Dhaptri Bastoli Motor Road (6.000 KM.) (completed)
Procurement:
Package No.: 38        Package Name: UDRP/PWD/08/05/RD/038        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 15-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/038        Contractor Name: Dwarika Projects Limited       
Start Date: 22-09-2014        Intended Completion Date: 25-09-2017        Original End Date:  21-12-2015
Total Bond Cost: 60641927.25 (606.42 lakhs)        Variation Cost: 6062931.19 (60.63 lakhs)     Hence Total Bond Cost is   66704858.44 (667.05 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5245533 for 173 days        LD Analysis for Milestone2: calculated LD is Rs 14372154 for 474 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.95 KM35.173.95 KM3.95 KM5.1935.17
2.R/Wall, B/ Wall Type Protection works1309.00 m125.881249.00 m1249.00 m18.55125.88
3.GSB/RBI/G-19.00 KM137.878.50 KM8.50 KM20.26137.87
4.G-20.00 KM0.000.00 KM0.00 KM00.00
5.G-30.00 KM0.008.60 KM8.60 KM00.00
6.PC/CC i/c Prime Coat, Tack Coat9.00 KM162.028.50 KM8.50 KM23.75162.02
7.Cause Way11.00 No50.327.00 No7.00 No7.3750.32
8.Culverts/Scupper 29.00 No84.6724.00 No24.00 No12.4384.67
9.longitudinal Drain7900.00 m10.278500.00 m8500.00 m1.510.27
10.Crash Barrier465.00 m18.803260.00 m3260.00 m2.6818.80
11.Parapet445.00 No15.9075.00 No75.00 No2.3215.90
12.Road Furniture156.00 No5.77315.00 No315.00 No0.855.77
13.Other Allied Works & Finishing Work 1513.00 Job34.901513.00 Job1513.00 Job5.1134.90
Total Amount: 681.57 100   681.57
Remarks: No Remarks       Work Program Made On: 01-10-2014       Updation of work program on: 14-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-May-201548.05  lakhs
2.29-June-201521.74  lakhs
3.28-August-201528.81  lakhs
4.03-November-201539.06  lakhs
5.08-April-20160.20  lakhs
6.27-October-201649.30  lakhs
7.29-December-2016100.33  lakhs
8.22-February-20170.11  lakhs
9.28-February-201790.62  lakhs
10.12-April-201769.17  lakhs
11.20-June-201786.20  lakhs
12.08-September-20170.87  lakhs
13.16-October-2017148.59  lakhs
14.16-November-20183.76  lakhs
Total 686.81  lakhs
% Payment 102.96 %
Advance Amount:  131.35  lakhs        Recovered Amount:  131.35  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 599     No. of Test Done : 607      No. of Test Passed : 580      No. of Test Failed : 27   Test report of this package
Number of Pics Available on Web Repository: 136
Number of Notice(s) issued: 117

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-2017Ch 2.950Crash barrier and sign boardJagdish Narayan Meenaunknownunknown See Pic
2.29-04-20171+500G3 workHarish ChandraJEUDRP R&B Bageshwar See Pic
3.29-04-20171+050Rolling work Rbi 81Harish ChandraJEUDRP R&B Bageshwar See Pic
4.18-02-2017Ch 3.360RBI -81 crust checking by SE sir PWD champawatJagdish Narayan Meenaunknownunknown See Pic
5.18-02-2017Ch 5.900Causeway inspection by SE sir champawatJagdish Narayan Meenaunknownunknown See Pic
6.18-02-2017Ch 1.950SE sir PWD champawat inspectionJagdish Narayan Meenaunknownunknown See Pic
7.18-02-2017Ch 4.750Crust thickness checking by SE sir PWD champawatJagdish Narayan Meenaunknownunknown See Pic
8.18-02-2017Ch 2.362SE sir PWD champawat inspectionJagdish Narayan Meenaunknownunknown See Pic
9.29-01-2017At HM plantSafety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38 & 45Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
10.28-01-2017At plantEnvironmental trainingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
11.28-01-2017At HM plantSafety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38,45 & 37Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
12.23-01-2017Ch-3+660Curing on RBI-81 surfaceMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
13.21-01-2017Ch-4+620Construction of R/Wall Regected because Base width of wall only 60 & 70 cmMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
14.12-01-2017Ch 1.005Checking of PC surface by EE sir PWD PD bageshwar.Jagdish Narayan Meenaunknownunknown See Pic
15.12-01-2017Ch 1.200Site inspection by EE PWD bageshwar and EE pmgsy .Jagdish Narayan Meenaunknownunknown See Pic
16.29-12-20161+075PMC Sample collecting from site for testingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
17.28-12-2016Ch-0+300Subgrade preparationMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
18.28-12-2016Ch-5+550Dry rolling over WBM GR 3 .Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
19.25-12-2016Ch 3.560Subgrade preparationJagdish Narayan Meenaunknownunknown See Pic
20.25-12-2016Ch 5.880Surface after G3 , required compactionJagdish Narayan Meenaunknownunknown See Pic