UDRP/PWD/08/05/RD/038
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
38 |
Package Name: |
UDRP/PWD/08/05/RD/038 |
Sanction Cost: |
606.42 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1123 kanda- Mantoli MR (5.000 KM.) (completed) | 2 1131 Vijaypur Dhaptri Bastoli Motor Road (6.000 KM.) (completed) |
|
Procurement: |
Package No.: 38
Package Name: UDRP/PWD/08/05/RD/038
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/038
Contractor Name: Dwarika Projects Limited
|
Start Date: 22-09-2014
Intended Completion Date: 25-09-2017
Original End Date: 21-12-2015
|
Total Bond Cost: 60641927.25 (606.42 lakhs)
Variation Cost: 6062931.19 (60.63 lakhs) Hence Total Bond Cost is 66704858.44 (667.05 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 5245533 for 173 days
LD Analysis for Milestone2: calculated LD is Rs 14372154 for 474 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.95 KM | 35.17 | 3.95 KM | 3.95 KM | 5.19 | 35.17 | 2. | R/Wall, B/ Wall Type Protection works | 1309.00 m | 125.88 | 1249.00 m | 1249.00 m | 18.55 | 125.88 | 3. | GSB/RBI/G-1 | 9.00 KM | 137.87 | 8.50 KM | 8.50 KM | 20.26 | 137.87 | 4. | G-2 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 0.00 KM | 0.00 | 8.60 KM | 8.60 KM | 0 | 0.00 | 6. | PC/CC i/c Prime Coat, Tack Coat | 9.00 KM | 162.02 | 8.50 KM | 8.50 KM | 23.75 | 162.02 | 7. | Cause Way | 11.00 No | 50.32 | 7.00 No | 7.00 No | 7.37 | 50.32 | 8. | Culverts/Scupper | 29.00 No | 84.67 | 24.00 No | 24.00 No | 12.43 | 84.67 | 9. | longitudinal Drain | 7900.00 m | 10.27 | 8500.00 m | 8500.00 m | 1.5 | 10.27 | 10. | Crash Barrier | 465.00 m | 18.80 | 3260.00 m | 3260.00 m | 2.68 | 18.80 | 11. | Parapet | 445.00 No | 15.90 | 75.00 No | 75.00 No | 2.32 | 15.90 | 12. | Road Furniture | 156.00 No | 5.77 | 315.00 No | 315.00 No | 0.85 | 5.77 | 13. | Other Allied Works & Finishing Work | 1513.00 Job | 34.90 | 1513.00 Job | 1513.00 Job | 5.11 | 34.90 |
Total Amount: |
681.57 |
|
100 |
681.57 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2014
Updation of work program on:
14-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 48.05 lakhs |
2. | 29-June-2015 | 21.74 lakhs |
3. | 28-August-2015 | 28.81 lakhs |
4. | 03-November-2015 | 39.06 lakhs |
5. | 08-April-2016 | 0.20 lakhs |
6. | 27-October-2016 | 49.30 lakhs |
7. | 29-December-2016 | 100.33 lakhs |
8. | 22-February-2017 | 0.11 lakhs |
9. | 28-February-2017 | 90.62 lakhs |
10. | 12-April-2017 | 69.17 lakhs |
11. | 20-June-2017 | 86.20 lakhs |
12. | 08-September-2017 | 0.87 lakhs |
13. | 16-October-2017 | 148.59 lakhs |
14. | 16-November-2018 | 3.76 lakhs |
Total |
686.81 lakhs |
% Payment |
102.96 % |
|
Advance Amount: 131.35 lakhs
Recovered Amount: 131.35 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 136 |
Number of Notice(s) issued: 117 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-06-2017 | Ch 2.950 | Crash barrier and sign board | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 29-04-2017 | 1+500 | G3 work | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
3. | 29-04-2017 | 1+050 | Rolling work Rbi 81 | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
4. | 18-02-2017 | Ch 3.360 | RBI -81 crust checking by SE sir PWD champawat | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 18-02-2017 | Ch 5.900 | Causeway inspection by SE sir champawat | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 18-02-2017 | Ch 1.950 | SE sir PWD champawat inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 18-02-2017 | Ch 4.750 | Crust thickness checking by SE sir PWD champawat | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 18-02-2017 | Ch 2.362 | SE sir PWD champawat inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 29-01-2017 | At HM plant | Safety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38 & 45 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
10. | 28-01-2017 | At plant | Environmental training | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
11. | 28-01-2017 | At HM plant | Safety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38,45 & 37 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
12. | 23-01-2017 | Ch-3+660 | Curing on RBI-81 surface | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
13. | 21-01-2017 | Ch-4+620 | Construction of R/Wall Regected because Base width of wall only 60 & 70 cm | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
14. | 12-01-2017 | Ch 1.005 | Checking of PC surface by EE sir PWD PD bageshwar. | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 12-01-2017 | Ch 1.200 | Site inspection by EE PWD bageshwar and EE pmgsy . | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 29-12-2016 | 1+075 | PMC Sample collecting from site for testing | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
17. | 28-12-2016 | Ch-0+300 | Subgrade preparation | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 28-12-2016 | Ch-5+550 | Dry rolling over WBM GR 3 . | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 25-12-2016 | Ch 3.560 | Subgrade preparation | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 25-12-2016 | Ch 5.880 | Surface after G3 , required compaction | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|