Package Profile Report

UDRP/PWD/08/06/RD/037 Agreement signed
Project: UDRP-RB Package No.: 37 Package Name: UDRP/PWD/08/06/RD/037 Sanction Cost: 873.42  lakhs
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision No.of Sub project : 3
Subproject in this package
1  1113   Bhyun- Gadera Motor Road (7.000 KM.) (completed)
2  1114   Bhyun- Guler Motor Road (5.000 KM.) (completed)
3  1127   Kapkot- Tehsil-Poling MR Phase1 (2.000 KM.) (completed)
Procurement:
Package No.: 37        Package Name: UDRP/PWD/08/06/RD/037        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 15-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/037        Contractor Name: Dwarika Projects Limited       
Start Date: 22-09-2014        Intended Completion Date: 31-07-2016        Original End Date:  22-12-2015
Total Bond Cost: 82967179.7 (829.67 lakhs)        Variation Cost: 3700237.83 (37 lakhs)     Hence Total Bond Cost is   86667417.53 (866.67 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5558856 for 134 days        LD Analysis for Milestone2: calculated LD is Rs 1866780 for 45 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.15 KM43.883.15 KM3.15 KM4.443.88
2.R/Wall, B/ Wall Type Protection works2752.00 m283.552752.00 m2752.00 m39.89283.55
3.GSB/RBI/G-17.40 KM41.337.40 KM7.40 KM4.1241.33
4.G-27.40 KM68.477.40 KM7.40 KM6.7668.47
5.G-37.40 KM42.187.40 KM7.40 KM4.1942.18
6.PC/CC i/c Prime Coat, Tack Coat7.30 KM107.897.30 KM7.30 KM10.74107.89
7.Cause Way9.00 No48.679.00 No9.00 No4.748.67
8.Culverts/Scupper 29.00 No102.5219.00 No19.00 No11.98102.52
9.longitudinal Drain6120.00 m29.396120.00 m6120.00 m2.8929.39
10.Crash Barrier340.00 m39.86340.00 m340.00 m3.8139.86
11.Parapet120.00 No12.07120.00 No120.00 No1.2112.07
12.Road Furniture110.00 No7.52110.00 No110.00 No0.727.52
13.Other Allied Works & Finishing Work 7.00 Job39.147.00 Job7.00 Job4.5939.14
Total Amount: 866.47 100   866.47
Remarks: No Remarks       Work Program Made On: 01-10-2014       Updation of work program on: 28-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-February-201541.95  lakhs
2.28-May-201542.24  lakhs
3.29-June-201529.41  lakhs
4.28-August-201589.60  lakhs
5.30-October-2015210.16  lakhs
6.29-February-2016129.83  lakhs
7.08-April-20160.25  lakhs
8.31-May-2016108.24  lakhs
9.30-July-2016109.37  lakhs
10.31-March-2017104.64  lakhs
11.24-October-20160.60  lakhs
12.23-December-20160.33  lakhs
13.25-February-20154.61  lakhs
Total 871.23  lakhs
% Payment 100.53 %
Advance Amount:  379.76  lakhs        Recovered Amount:  379.76  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 730     No. of Test Done : 724      No. of Test Passed : 691      No. of Test Failed : 33   Test report of this package
Number of Pics Available on Web Repository: 148
Number of Notice(s) issued: 115

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-04-2017Ch 3.950Plum protecting work completedJagdish Narayan Meenaunknownunknown See Pic
2.30-04-2017Ch 3.650Plum protecting work and crash barrierJagdish Narayan Meenaunknownunknown See Pic
3.30-04-2017Ch 3.600Crash barrierJagdish Narayan Meenaunknownunknown See Pic
4.30-04-2017Ch 3.200B/wall with kc type drainJagdish Narayan Meenaunknownunknown See Pic
5.30-04-2017Ch 2.700Delinator, parapet on R/wallJagdish Narayan Meenaunknownunknown See Pic
6.30-04-2017Ch 2.400Delinator and parapet work completedJagdish Narayan Meenaunknownunknown See Pic
7.30-04-2017Ch 2.130Hair pin bendsJagdish Narayan Meenaunknownunknown See Pic
8.30-04-2017Ch 2.100Road surface after installing Delinator and sign boardJagdish Narayan Meenaunknownunknown See Pic
9.30-04-2017Ch 2.050B/wall with KC type drainJagdish Narayan Meenaunknownunknown See Pic
10.30-04-2017Ch 2.000Information boardJagdish Narayan Meenaunknownunknown See Pic
11.30-04-2017Ch 6.450Crash barrierJagdish Narayan Meenaunknownunknown See Pic
12.30-04-2017Ch 6.500End point information board, required correctionJagdish Narayan Meenaunknownunknown See Pic
13.30-04-2017Ch 6.200Causeway and B/wall with kc type drainJagdish Narayan Meenaunknownunknown See Pic
14.30-04-2017Ch 5.475Road surfaceJagdish Narayan Meenaunknownunknown See Pic
15.30-04-2017Ch 5.400Plum protecting work and R/wallJagdish Narayan Meenaunknownunknown See Pic
16.30-04-2017Ch 3.950B/wallJagdish Narayan Meenaunknownunknown See Pic
17.30-04-2017Ch 3.900Road surface with kc type drainJagdish Narayan Meenaunknownunknown See Pic
18.30-04-2017Ch 3.800Crash barrierJagdish Narayan Meenaunknownunknown See Pic
19.30-04-2017Ch 2.090Sign board and DelinatorJagdish Narayan Meenaunknownunknown See Pic
20.30-04-2017Ch 2.030DelinatorJagdish Narayan Meenaunknownunknown See Pic