UDRP/PWD/07/16/RD/035
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
35 |
Package Name: |
UDRP/PWD/07/16/RD/035 |
Sanction Cost: |
1075.68 lakhs |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 2330 Kqitee Sain Rathi Motor Road (6.500 KM.) (completed) | 2 2346 Shaid Pushker Singh Motor Road (1.875 KM.) (completed) | 3 2347 Shishu Mandir-Nanasen Motor Road (2.750 KM.) (completed) |
|
Procurement: |
Package No.: 35
Package Name: UDRP/PWD/07/16/RD/035
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 27-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/035
Contractor Name: Dwarika Projects Limited
|
Start Date: 03-11-2014
Intended Completion Date: 15-04-2019
Original End Date: 02-02-2016
|
Total Bond Cost: 78211526 (782.12 lakhs)
Variation Cost: 21090687.36 (210.91 lakhs) Hence Total Bond Cost is 99302213.36 (993.02 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2111724 for 54 days
LD Analysis for Milestone2: calculated LD is Rs 1290498 for 33 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.20 KM | 15.77 | 3.20 KM | 3.20 KM | 1.61 | 15.77 | 2. | R/Wall, B/ Wall Type Protection works | 2841.00 m | 285.51 | 2747.00 m | 2747.00 m | 30.91 | 285.51 | 3. | GSB/RBI/G-1 | 7.93 KM | 73.26 | 7.93 KM | 7.93 KM | 7.48 | 73.26 | 4. | G-2 | 7.93 KM | 44.14 | 7.93 KM | 7.93 KM | 4.51 | 44.14 | 5. | G-3 | 9.18 KM | 53.51 | 9.18 KM | 9.18 KM | 5.69 | 53.51 | 6. | PC/CC i/c Prime Coat, Tack Coat | 10.68 KM | 202.13 | 10.68 KM | 10.68 KM | 23.06 | 202.13 | 7. | Cause Way | 9.00 No | 20.29 | 7.00 No | 7.00 No | 2.22 | 20.29 | 8. | Culverts/Scupper | 39.00 No | 112.86 | 38.00 No | 38.00 No | 11.77 | 112.86 | 9. | longitudinal Drain | 8105.00 m | 66.33 | 9710.00 m | 9710.00 m | 7.72 | 66.33 | 10. | Parapet | 975.00 No | 15.99 | 950.00 No | 950.00 No | 1.94 | 15.99 | 11. | Road Furniture | 163.00 No | 5.76 | 156.00 No | 156.00 No | 0.67 | 5.76 | 12. | Other Allied Works & Finishing Work | 3.00 Job | 14.99 | 3.00 Job | 3.00 Job | 1.78 | 14.99 | 13. | Crash Barrier | 250.00 m | 5.91 | 250.00 m | 250.00 m | 0.66 | 5.91 |
Total Amount: |
916.45 |
|
100 |
916.45 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 57.08 lakhs |
2. | 06-June-2015 | 42.24 lakhs |
3. | 22-August-2015 | 178.51 lakhs |
4. | 29-September-2015 | 38.71 lakhs |
5. | 08-January-2016 | 98.45 lakhs |
6. | 18-March-2016 | 53.60 lakhs |
7. | 30-June-2016 | 43.56 lakhs |
8. | 27-July-2016 | 28.81 lakhs |
9. | 31-March-2017 | 59.75 lakhs |
10. | 31-May-2017 | 95.05 lakhs |
11. | 26-November-2017 | 23.79 lakhs |
12. | 16-February-2018 | 49.39 lakhs |
13. | 27-February-2018 | 24.59 lakhs |
14. | 27-March-2018 | 10.61 lakhs |
15. | 30-May-2018 | 56.91 lakhs |
16. | 07-August-2018 | 46.15 lakhs |
17. | 29-October-2018 | 20.70 lakhs |
18. | 20-November-2018 | 12.38 lakhs |
19. | 26-December-2018 | 10.00 lakhs |
20. | 27-December-2018 | 21.49 lakhs |
21. | 15-February-2019 | 11.26 lakhs |
22. | 12-March-2019 | 21.80 lakhs |
23. | 31-May-2019 | 21.88 lakhs |
24. | 22-June-2019 | 25.15 lakhs |
Total |
1051.86 lakhs |
% Payment |
105.92 % |
|
Advance Amount: 88.43 lakhs
Recovered Amount: 88.43 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 285 |
Number of Notice(s) issued: 87 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-02-2018 | 0*300 | Wire crate wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
2. | 03-02-2018 | 0*350 | Edge wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 03-02-2018 | 1+525 | Dry R/W wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
4. | 17-01-2018 | 0+600 | Gabion wall work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
5. | 17-01-2018 | 0+020 | Plum concrete wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
6. | 15-01-2018 | 0+600 | Wire create work | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
7. | 02-01-2018 | 0+220 | B/wall banded | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
8. | 31-12-2017 | 0+220 | Breast wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
9. | 31-12-2017 | 0+425 | Plum concrete for wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
10. | 31-12-2017 | 4+450 | Construction of Retaining wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
11. | 27-12-2017 | 0+220 | B/wall banded | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
12. | 21-12-2017 | 0+220 | R/wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
13. | 19-12-2017 | 0+450 | Edge wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
14. | 19-12-2017 | 0+280 | Edge wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
15. | 19-12-2017 | 0+220 | R/wall 1:5 | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
16. | 18-12-2017 | 0+300 | Edge wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
17. | 18-12-2017 | 0+220 | R/wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
18. | 17-12-2017 | 0+220 | R/wall rr1:5 | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
19. | 16-12-2017 | 0+200 | Excavation of edging wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
20. | 16-12-2017 | 0+300 | Excavation of edging wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
|
|