Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/16/RD/035 Agreement signed
Project: UDRP-RB Package No.: 35 Package Name: UDRP/PWD/07/16/RD/035 Sanction Cost: 782.12  lakhs
District: Pithoragarh Block: Munsiari Constituency: Dharchula Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 3
Subproject in this package
1  2330   Kqitee Sain Rathi Motor Road (6.500 KM.) (in prorgress)
2  2346   Shaid Pushker Singh Motor Road (1.875 KM.) (in prorgress)
3  2347   Shishu Mandir-Nanasen Motor Road (2.750 KM.) (in prorgress)
Procurement:
Package No.: 35        Package Name: UDRP/PWD/07/16/RD/035        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 27-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/16/RD/035        Contractor Name: Dwarika Projects Limited       
Start Date: 03-11-2014        Intended Completion Date: 30-06-2017        Original End Date:  02-02-2016
Total Bond Cost: 78211526 (782.12 lakhs)        Variation Cost: 13431640.94 (134.32 lakhs)     Hence Total Bond Cost is   91643166.94 (916.43 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2111724 for 54 days        LD Analysis for Milestone2: calculated LD is Rs 1290498 for 33 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.20 KM15.772.20 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works2841.00 m285.512590.00 m2451.00 m28.51268.12
3.GSB/RBI/G-17.93 KM73.267.93 KM7.55 KM7.2369.81
4.G-27.93 KM44.147.93 KM6.50 KM3.7236.19
5.G-39.18 KM53.519.18 KM7.05 KM4.2840.36
6.PC/CC i/c Prime Coat, Tack Coat10.68 KM202.1310.68 KM8.55 KM18.29160.94
7.Cause Way9.00 No20.297.00 No7.00 No2.2120.29
8.Culverts/Scupper 39.00 No112.8634.00 No32.00 No11.21107.98
9.longitudinal Drain8105.00 m66.339575.00 m6900.00 m5.1540.74
10.Crash Barrier250.00 m5.91250.00 m0.00 m00.00
11.Parapet975.00 No15.991058.00 No824.00 No1.179.58
12.Road Furniture163.00 No5.76163.00 No0.00 No00.00
13.Other Allied Works & Finishing Work 3.00 Job14.993.00 Job0.00 Job00.00
Total Amount: 916.45 81.77   754.01
Remarks: No Remarks       Work Program Made On: 25-09-2015       Updation of work program on: 29-11-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.31-March-201557.08  lakhs
2.06-June-201542.24  lakhs
3.22-August-2015178.51  lakhs
4.29-September-201538.71  lakhs
5.08-January-201698.45  lakhs
6.18-March-201653.60  lakhs
7.30-June-201643.56  lakhs
8.27-July-201628.81  lakhs
9.31-March-201759.75  lakhs
10.31-May-201795.05  lakhs
11.26-November-201723.79  lakhs
Total 719.55  lakhs
% Payment 78.52 %
Advance Amount:  88.43  lakhs        Recovered Amount:  88.43  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 376     No. of Test Done : 378      No. of Test Passed : 376      No. of Test Failed : 2   Test report of this package
Number of Pics Available on Web Repository: 282
Number of Notice(s) issued: 81

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-01-20180+600Gabion wall work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
2.17-01-20180+020Plum concrete wall in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
3.15-01-20180+600Wire create workRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
4.02-01-20180+220B/wall bandedRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
5.31-12-20170+220Breast wall in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
6.31-12-20170+425Plum concrete for wall in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
7.31-12-20174+450Construction of Retaining wall in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
8.27-12-20170+220B/wall bandedRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
9.21-12-20170+220R/wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
10.19-12-20170+450Edge wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
11.19-12-20170+280Edge wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
12.19-12-20170+220R/wall 1:5Ravindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
13.18-12-20170+300Edge wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
14.18-12-20170+220R/wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
15.17-12-20170+220R/wall rr1:5Ravindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
16.16-12-20170+200Excavation of edging wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
17.16-12-20170+300Excavation of edging wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
18.15-12-20170+650R /wall dryRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
19.15-12-20170+0220R/wallRavindra Singh DafoutiSite SupervisorDSC4 R&B WB Munsyari See Pic
20.08-12-20170+500CE sir site visitDinesh KumarREDSC4 R&B WB Munsyari See Pic