Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/31/RD/033 Agreement signed
Project: UDRP-RB Package No.: 33 Package Name: UDRP/PWD/01/31/RD/033 Sanction Cost: 433.71  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 2
Subproject in this package
1  3126   Bhukki Kujjan Tihaar Motor Road (5.000 KM.) (completed)
2  3206   Saura Sari Motor Road (1.750 KM.) (completed)
Procurement:
Package No.: 33        Package Name: UDRP/PWD/01/31/RD/033        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/RD/033        Contractor Name: Arya Construction       
Start Date: 11-06-2015        Intended Completion Date: 31-07-2017        Original End Date:  10-09-2016
Total Bond Cost: 30095179.78 (300.95 lakhs)        Variation Cost: 12251575.02 (122.52 lakhs)     Hence Total Bond Cost is   42346754.8 (423.47 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1820808 for 121 days        LD Analysis for Milestone2: calculated LD is Rs 5567760 for 370 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.05 KM24.252.05 KM2.05 KM8.0924.25
2.R/Wall, B/ Wall Type Protection works1775.00 m105.891775.00 m1775.00 m36.29105.89
3.GSB/RBI/G-13.85 KM19.213.85 KM3.85 KM6.3719.21
4.G-23.85 KM18.313.85 KM3.85 KM6.2518.31
5.G-33.85 KM19.163.85 KM3.85 KM6.5319.16
6.PC/CC i/c Prime Coat, Tack Coat3.85 KM48.143.85 KM3.85 KM16.5548.14
7.Cause Way6.00 No20.306.00 No6.00 No6.3620.30
8.Culverts/Scupper 10.00 No24.6610.00 No10.00 No8.1824.66
9.longitudinal Drain6300.00 m13.186300.00 m6300.00 m4.6213.18
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet40.00 No1.4840.00 No40.00 No0.451.48
12.Road Furniture55.00 No1.0055.00 No55.00 No0.321.00
Total Amount: 295.58 100   295.58
Remarks: No Remarks       Work Program Made On: 11-08-2015       Updation of work program on: 13-08-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201512.00  lakhs
2.30-September-20158.82  lakhs
3.19-December-20150.03  lakhs
4.19-February-201622.90  lakhs
5.11-March-201621.07  lakhs
6.30-March-20165.93  lakhs
7.27-October-201610.85  lakhs
8.09-December-201616.81  lakhs
9.11-January-201715.50  lakhs
10.29-March-201719.36  lakhs
11.18-May-201748.31  lakhs
12.30-June-201731.65  lakhs
13.31-July-201743.16  lakhs
14.12-October-201737.73  lakhs
15.27-November-201728.81  lakhs
16.23-December-20171.16  lakhs
17.17-February-201865.22  lakhs
18.21-April-201817.71  lakhs
19.31-May-201817.77  lakhs
20.15-July-201911.94  lakhs
Total 436.73  lakhs
% Payment 103.13 %
Advance Amount:  70.90  lakhs        Recovered Amount:  70.90  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 281     No. of Test Done : 361      No. of Test Passed : 338      No. of Test Failed : 23   Test report of this package
Number of Pics Available on Web Repository: 164
Number of Notice(s) issued: 138

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-10-2017Ch2/39Slip cleaningNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
2.17-10-2017Ch2/40Site visit with EE sirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
3.16-10-2017Ch0/26Site inspaction by EE sir regarding site hand over progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
4.15-10-2017Ch0/36Slip cleaningNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.28-09-2017Ch 1/9Removing Defects in Plum work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
6.30-08-2017Ch 2/7Slip from PMGSY new cuttingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
7.30-08-2017Ch0/27Rejected breast wallNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
8.30-08-2017Ch 0/30Soling rejected taken it as surface dressingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
9.07-05-2017Ch 0/6Wire crate work on sinking wall portionNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
10.21-04-2017Ch 2/3Bitumen supply for PCNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
11.08-02-2017Excavation in foundations for B/wall km 4/12Excavation in foundations for B /wall work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.02-02-2017RENFORSMENT Checking in bed block km 0/23RENFORSMENT Checking in bed block work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.24-01-2017Excavation in poundation for causewayWork in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.15-01-20171/22Site visit with contractor regarding site workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
15.15-01-20172/7KC drain 50mtr rejected due to poor qualityPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
16.11-01-2017Ch 1/23Causeway locationNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
17.11-01-2017Ch 2/6 -2/7K.C drain rejected poor workmanshipNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
18.31-12-2016R.R.Dry wall km 1/22Dry wall work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.26-12-2016Ch 2/7KC drain rejected due to alignment and without compactionNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
20.21-12-2016Ch 1/22HP stone filling backside of R/WNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic