UDRP/PWD/01/31/RD/033
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
33 |
Package Name: |
UDRP/PWD/01/31/RD/033 |
Sanction Cost: |
433.71 lakhs |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 3126 Bhukki Kujjan Tihaar Motor Road (5.000 KM.) (completed) | 2 3206 Saura Sari Motor Road (1.750 KM.) (completed) |
|
Procurement: |
Package No.: 33
Package Name: UDRP/PWD/01/31/RD/033
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/033
Contractor Name: Arya Construction
|
Start Date: 11-06-2015
Intended Completion Date: 31-07-2017
Original End Date: 10-09-2016
|
Total Bond Cost: 30095179.78 (300.95 lakhs)
Variation Cost: 12251575.02 (122.52 lakhs) Hence Total Bond Cost is 42346754.8 (423.47 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1820808 for 121 days
LD Analysis for Milestone2: calculated LD is Rs 5567760 for 370 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.05 KM | 24.25 | 2.05 KM | 2.05 KM | 8.09 | 24.25 | 2. | R/Wall, B/ Wall Type Protection works | 1775.00 m | 105.89 | 1775.00 m | 1775.00 m | 36.29 | 105.89 | 3. | GSB/RBI/G-1 | 3.85 KM | 19.21 | 3.85 KM | 3.85 KM | 6.37 | 19.21 | 4. | G-2 | 3.85 KM | 18.31 | 3.85 KM | 3.85 KM | 6.25 | 18.31 | 5. | G-3 | 3.85 KM | 19.16 | 3.85 KM | 3.85 KM | 6.53 | 19.16 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.85 KM | 48.14 | 3.85 KM | 3.85 KM | 16.55 | 48.14 | 7. | Cause Way | 6.00 No | 20.30 | 6.00 No | 6.00 No | 6.36 | 20.30 | 8. | Culverts/Scupper | 10.00 No | 24.66 | 10.00 No | 10.00 No | 8.18 | 24.66 | 9. | longitudinal Drain | 6300.00 m | 13.18 | 6300.00 m | 6300.00 m | 4.62 | 13.18 | 10. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 40.00 No | 1.48 | 40.00 No | 40.00 No | 0.45 | 1.48 | 12. | Road Furniture | 55.00 No | 1.00 | 55.00 No | 55.00 No | 0.32 | 1.00 |
Total Amount: |
295.58 |
|
100 |
295.58 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015
Updation of work program on:
13-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 12.00 lakhs |
2. | 30-September-2015 | 8.82 lakhs |
3. | 19-December-2015 | 0.03 lakhs |
4. | 19-February-2016 | 22.90 lakhs |
5. | 11-March-2016 | 21.07 lakhs |
6. | 30-March-2016 | 5.93 lakhs |
7. | 27-October-2016 | 10.85 lakhs |
8. | 09-December-2016 | 16.81 lakhs |
9. | 11-January-2017 | 15.50 lakhs |
10. | 29-March-2017 | 19.36 lakhs |
11. | 18-May-2017 | 48.31 lakhs |
12. | 30-June-2017 | 31.65 lakhs |
13. | 31-July-2017 | 43.16 lakhs |
14. | 12-October-2017 | 37.73 lakhs |
15. | 27-November-2017 | 28.81 lakhs |
16. | 23-December-2017 | 1.16 lakhs |
17. | 17-February-2018 | 65.22 lakhs |
18. | 21-April-2018 | 17.71 lakhs |
19. | 31-May-2018 | 17.77 lakhs |
20. | 15-July-2019 | 11.94 lakhs |
Total |
436.73 lakhs |
% Payment |
103.13 % |
|
Advance Amount: 70.90 lakhs
Recovered Amount: 70.90 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 164 |
Number of Notice(s) issued: 138 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-10-2017 | Ch2/39 | Slip cleaning | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
2. | 17-10-2017 | Ch2/40 | Site visit with EE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
3. | 16-10-2017 | Ch0/26 | Site inspaction by EE sir regarding site hand over progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
4. | 15-10-2017 | Ch0/36 | Slip cleaning | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 28-09-2017 | Ch 1/9 | Removing Defects in Plum work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
6. | 30-08-2017 | Ch 2/7 | Slip from PMGSY new cutting | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
7. | 30-08-2017 | Ch0/27 | Rejected breast wall | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
8. | 30-08-2017 | Ch 0/30 | Soling rejected taken it as surface dressing | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
9. | 07-05-2017 | Ch 0/6 | Wire crate work on sinking wall portion | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
10. | 21-04-2017 | Ch 2/3 | Bitumen supply for PC | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
11. | 08-02-2017 | Excavation in foundations for B/wall km 4/12 | Excavation in foundations for B /wall work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
12. | 02-02-2017 | RENFORSMENT Checking in bed block km 0/23 | RENFORSMENT Checking in bed block work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
13. | 24-01-2017 | Excavation in poundation for causeway | Work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
14. | 15-01-2017 | 1/22 | Site visit with contractor regarding site work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
15. | 15-01-2017 | 2/7 | KC drain 50mtr rejected due to poor quality | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
16. | 11-01-2017 | Ch 1/23 | Causeway location | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
17. | 11-01-2017 | Ch 2/6 -2/7 | K.C drain rejected poor workmanship | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
18. | 31-12-2016 | R.R.Dry wall km 1/22 | Dry wall work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 26-12-2016 | Ch 2/7 | KC drain rejected due to alignment and without compaction | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
20. | 21-12-2016 | Ch 1/22 | HP stone filling backside of R/W | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
|
|