Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/30/RD/032 Agreement signed
Project: UDRP-RB Package No.: 32 Package Name: UDRP/PWD/01/30/RD/032 Sanction Cost: 422.06  lakhs
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  3133   Ranari to Danda Majaf MR (4.600 KM.) (completed)
2  3237   Dunda Kurah Motor road Phase2 (0.750 KM.) (completed)
Procurement:
Package No.: 32        Package Name: UDRP/PWD/01/30/RD/032        Tender Date: 21-10-2014        Current Status: Agreement signed        Achieved on Date: 03-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/032        Contractor Name: Dilawar Singh Contractor       
Start Date: 10-06-2015        Intended Completion Date: 17-11-2016        Original End Date:  09-09-2016
Total Bond Cost: 38718032.06 (387.18 lakhs)        Variation Cost: 3263774.37 (32.64 lakhs)     Hence Total Bond Cost is   41981806.43 (419.82 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 522693 for 27 days        LD Analysis for Milestone2: calculated LD is Rs 1684233 for 87 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.00 KM13.154.00 KM4.00 KM3.5713.15
2.R/Wall, B/ Wall Type Protection works2119.00 m88.022119.00 m2119.00 m23.9288.02
3.GSB/RBI/G-14.60 KM35.554.60 KM4.60 KM9.6635.55
4.G-24.60 KM25.934.60 KM4.60 KM7.0525.93
5.G-34.60 KM33.884.60 KM4.60 KM9.2133.88
6.PC/CC i/c Prime Coat, Tack Coat5.35 KM73.015.35 KM5.35 KM19.9773.01
7.Cause Way1.00 No17.031.00 No1.00 No4.6317.03
8.Culverts/Scupper 21.00 No39.0621.00 No21.00 No10.7739.06
9.longitudinal Drain5100.00 m27.305100.00 m5100.00 m7.5227.30
10.Crash Barrier410.00 m9.38410.00 m410.00 m2.679.38
11.Road Furniture28.00 No0.8228.00 No28.00 No0.230.82
12.Parapet132.00 No2.85132.00 No132.00 No0.812.85
Total Amount: 365.98 100   365.98
Remarks: No Remarks       Work Program Made On: 11-08-2015       Updation of work program on: 20-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201539.69  lakhs
2.28-October-201526.94  lakhs
3.18-February-201631.65  lakhs
4.29-March-201629.91  lakhs
5.22-June-201656.80  lakhs
6.15-August-201633.77  lakhs
7.24-September-201626.46  lakhs
8.03-October-201626.00  lakhs
9.26-October-201662.50  lakhs
10.31-January-201714.62  lakhs
11.24-March-201711.63  lakhs
12.30-June-201724.15  lakhs
13.13-October-201720.41  lakhs
14.23-December-20176.70  lakhs
15.16-May-20184.46  lakhs
16.08-June-20181.33  lakhs
17.29-August-20182.70  lakhs
Total 419.72  lakhs
% Payment 99.98 %
Advance Amount:  60.61  lakhs        Recovered Amount:  60.61  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 328     No. of Test Done : 380      No. of Test Passed : 361      No. of Test Failed : 19   Test report of this package
Number of Pics Available on Web Repository: 435
Number of Notice(s) issued: 126

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-11-2017Km2Site inspaction by SE SirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
2.05-11-2017Ch. 2/17Repairs of PC surfaceNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.05-11-2017Ch2/28Repairs work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
4.02-11-2017Ch0/2Dispute discussion local representatives with EE, Ae, and contractor, at danda majaf MrNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.02-11-2017Km2Patch work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
6.02-11-2017Ch0/3Site visit regarding local disputeNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
7.02-11-2017Ch0/1Patch work completed at danda majaf Mr.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
8.31-10-20172/18Patch work on progressBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
9.31-10-20172/17Patch work on progressBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
10.31-10-20174/20Patch WorkChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
11.30-10-2017Ch2/17Pc layer depth checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
12.30-10-20173/2Parapet painting work on progressBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
13.30-10-20172/28Whitewashing on road safety parapetBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
14.30-10-20172/16Patch work on progressBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
15.30-10-2017Ch3/2Culvert panting work completeNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
16.30-10-2017Ch2/28Parapet white washing work complete in mantion chNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
17.30-10-2017Ch2/33Patch work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
18.26-10-20174/3Patch work on progressBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
19.25-10-20174/3Patch work on progressBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic
20.06-01-20172/7Dry wallChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic