UDRP/PWD/01/30/RD/032
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
32 |
Package Name: |
UDRP/PWD/01/30/RD/032 |
Sanction Cost: |
422.06 lakhs |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 3133 Ranari to Danda Majaf MR (4.600 KM.) (completed) | 2 3237 Dunda Kurah Motor road Phase2 (0.750 KM.) (completed) |
|
Procurement: |
Package No.: 32
Package Name: UDRP/PWD/01/30/RD/032
Tender Date: 21-10-2014
Current Status: Agreement signed
Achieved on Date: 03-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/032
Contractor Name: Dilawar Singh Contractor
|
Start Date: 10-06-2015
Intended Completion Date: 17-11-2016
Original End Date: 09-09-2016
|
Total Bond Cost: 38718032.06 (387.18 lakhs)
Variation Cost: 3263774.37 (32.64 lakhs) Hence Total Bond Cost is 41981806.43 (419.82 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 522693 for 27 days
LD Analysis for Milestone2: calculated LD is Rs 1684233 for 87 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.00 KM | 13.15 | 4.00 KM | 4.00 KM | 3.57 | 13.15 | 2. | R/Wall, B/ Wall Type Protection works | 2119.00 m | 88.02 | 2119.00 m | 2119.00 m | 23.92 | 88.02 | 3. | GSB/RBI/G-1 | 4.60 KM | 35.55 | 4.60 KM | 4.60 KM | 9.66 | 35.55 | 4. | G-2 | 4.60 KM | 25.93 | 4.60 KM | 4.60 KM | 7.05 | 25.93 | 5. | G-3 | 4.60 KM | 33.88 | 4.60 KM | 4.60 KM | 9.21 | 33.88 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.35 KM | 73.01 | 5.35 KM | 5.35 KM | 19.97 | 73.01 | 7. | Cause Way | 1.00 No | 17.03 | 1.00 No | 1.00 No | 4.63 | 17.03 | 8. | Culverts/Scupper | 21.00 No | 39.06 | 21.00 No | 21.00 No | 10.77 | 39.06 | 9. | longitudinal Drain | 5100.00 m | 27.30 | 5100.00 m | 5100.00 m | 7.52 | 27.30 | 10. | Crash Barrier | 410.00 m | 9.38 | 410.00 m | 410.00 m | 2.67 | 9.38 | 11. | Road Furniture | 28.00 No | 0.82 | 28.00 No | 28.00 No | 0.23 | 0.82 | 12. | Parapet | 132.00 No | 2.85 | 132.00 No | 132.00 No | 0.81 | 2.85 |
Total Amount: |
365.98 |
|
100 |
365.98 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015
Updation of work program on:
20-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 39.69 lakhs |
2. | 28-October-2015 | 26.94 lakhs |
3. | 18-February-2016 | 31.65 lakhs |
4. | 29-March-2016 | 29.91 lakhs |
5. | 22-June-2016 | 56.80 lakhs |
6. | 15-August-2016 | 33.77 lakhs |
7. | 24-September-2016 | 26.46 lakhs |
8. | 03-October-2016 | 26.00 lakhs |
9. | 26-October-2016 | 62.50 lakhs |
10. | 31-January-2017 | 14.62 lakhs |
11. | 24-March-2017 | 11.63 lakhs |
12. | 30-June-2017 | 24.15 lakhs |
13. | 13-October-2017 | 20.41 lakhs |
14. | 23-December-2017 | 6.70 lakhs |
15. | 16-May-2018 | 4.46 lakhs |
16. | 08-June-2018 | 1.33 lakhs |
17. | 29-August-2018 | 2.70 lakhs |
Total |
419.72 lakhs |
% Payment |
99.98 % |
|
Advance Amount: 60.61 lakhs
Recovered Amount: 60.61 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 435 |
Number of Notice(s) issued: 126 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-11-2017 | Km2 | Site inspaction by SE Sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
2. | 05-11-2017 | Ch. 2/17 | Repairs of PC surface | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 05-11-2017 | Ch2/28 | Repairs work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 02-11-2017 | Ch0/2 | Dispute discussion local representatives with EE, Ae, and contractor, at danda majaf Mr | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 02-11-2017 | Km2 | Patch work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
6. | 02-11-2017 | Ch0/3 | Site visit regarding local dispute | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
7. | 02-11-2017 | Ch0/1 | Patch work completed at danda majaf Mr. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
8. | 31-10-2017 | 2/18 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
9. | 31-10-2017 | 2/17 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
10. | 31-10-2017 | 4/20 | Patch Work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
11. | 30-10-2017 | Ch2/17 | Pc layer depth checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
12. | 30-10-2017 | 3/2 | Parapet painting work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
13. | 30-10-2017 | 2/28 | Whitewashing on road safety parapet | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
14. | 30-10-2017 | 2/16 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
15. | 30-10-2017 | Ch3/2 | Culvert panting work complete | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
16. | 30-10-2017 | Ch2/28 | Parapet white washing work complete in mantion ch | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
17. | 30-10-2017 | Ch2/33 | Patch work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
18. | 26-10-2017 | 4/3 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
19. | 25-10-2017 | 4/3 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
20. | 06-01-2017 | 2/7 | Dry wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|