Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/30/RD/031 Agreement signed
Project: UDRP-RB Package No.: 31 Package Name: UDRP/PWD/01/30/RD/031 Sanction Cost: 629.57  lakhs
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  3238   Newgaon Sari Shrikalkhal Motor road phase 2 (10.000 KM.) (completed)
Procurement:
Package No.: 31        Package Name: UDRP/PWD/01/30/RD/031        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 24-03-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/031        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 31-03-2015        Intended Completion Date: 28-02-2018        Original End Date:  30-06-2016
Total Bond Cost: 54495078 (544.95 lakhs)        Variation Cost: 5174099.05 (51.74 lakhs)     Hence Total Bond Cost is   59669177.05 (596.69 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4168944 for +153 days        LD Analysis for Milestone2: calculated LD is Rs 7493200 for 275 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence9.00 KM8.809.00 KM9.00 KM1.338.80
2.R/Wall, B/ Wall Type Protection works1400.00 m179.621400.00 m1400.00 m27.24179.62
3.GSB/RBI/G-19.00 KM70.169.00 KM9.00 KM10.6470.16
4.G-29.00 KM100.599.00 KM9.00 KM15.25100.59
5.G-39.00 KM52.909.00 KM9.00 KM8.0252.90
6.PC/CC i/c Prime Coat, Tack Coat9.72 KM136.949.72 KM9.72 KM20.76136.94
7.Cause Way0.00 No0.000.00 No0.00 No00.00
8.Culverts/Scupper 26.00 No64.5226.00 No26.00 No9.7864.52
9.longitudinal Drain9500.00 m27.369500.00 m9500.00 m4.1527.36
10.Crash Barrier300.00 m6.00300.00 m300.00 m0.916.00
11.Parapet350.00 No6.48350.00 No350.00 No0.986.48
12.Road Furniture57.00 No1.7857.00 No57.00 No0.271.78
13.Env. Man & Moni Plan1.00 Job4.361.00 Job1.00 Job0.664.36
Total Amount: 659.51 100   659.51
Remarks: No Remarks       Work Program Made On: 16-05-2015       Updation of work program on: 10-01-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201540.55  lakhs
2.16-February-201657.73  lakhs
3.30-March-201664.17  lakhs
4.29-June-201622.52  lakhs
5.03-October-201610.20  lakhs
6.13-October-201628.49  lakhs
7.14-October-201620.45  lakhs
8.26-October-201626.00  lakhs
9.09-December-201620.84  lakhs
10.19-May-201720.33  lakhs
11.17-June-201730.72  lakhs
12.30-June-201768.60  lakhs
13.13-October-201733.56  lakhs
14.27-November-201715.31  lakhs
15.23-December-20171.72  lakhs
16.17-February-201826.79  lakhs
17.27-February-201810.20  lakhs
18.31-March-201822.82  lakhs
19.31-May-201862.06  lakhs
20.15-July-20198.88  lakhs
Total 591.94  lakhs
% Payment 99.2 %
Advance Amount:  132.46  lakhs        Recovered Amount:  132.46  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 565     No. of Test Done : 708      No. of Test Passed : 677      No. of Test Failed : 31   Test report of this package
Number of Pics Available on Web Repository: 181
Number of Notice(s) issued: 153

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-20185/25Visit to newgaon sari Shrikalkhal MR by SE sirAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
2.08-01-20181/24 causewayCausewayAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
3.25-12-20170/10Breast wall in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
4.25-12-20176/23Newgaon sari Shrikalkhal M/R B/WAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
5.25-11-2017Ch. 0/15R/W in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
6.24-10-20172/3KC drain work . Quality found good .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.06-10-20171/27crush barrierChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
8.15-06-20177/5PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
9.13-06-20177/35PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
10.12-06-20178/2H.p bend .......proper weidthPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.12-06-20178/2-3PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
12.12-06-20178/1PC workAnkit KuriyalJEUDRP R&B Askot See Pic
13.02-06-20175/20SS 1 ......alll R s drum ....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.26-05-20179/16P.c material temprature on site ....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
15.26-05-20179/14PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
16.25-05-20179/20-19PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.24-05-20179/24Seal coat .......from shrikhaal khaalPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.24-05-20179/25Rolling for p.cPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.24-05-20179/26PC workAnkit KuriyalJEUDRP R&B Askot See Pic
20.23-05-20179/26-25PC work startChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic