Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/08 Agreement signed
Project: IRRIGATION Package No.: 3004 Package Name: UDRP/AF/RBP/08 Sanction Cost: 1310.00  lakhs
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7409   Maithana Alaknanda (0.450 KM.) (completed)
Procurement:
Package No.: 3004        Package Name: UDRP/AF/RBP/08        Tender Date: 16-10-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/08        Contractor Name: M/S Ajay kumar contractor       
Start Date: 29-01-2020        Intended Completion Date: 28-07-2021       
Total Bond Cost: 107897353 (1078.97 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 16616292 for 308 days        LD Analysis for Milestone2: calculated LD is Rs 16616292 for 308 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan6.00 Job3.280.00 Job0.00 Job00.00
2.Other Allied Works & Finishing Work 15.00 Job23.490.00 Job0.00 Job00.00
3.Excavation in Foundation4738.00 cum14.310.00 cum0.00 cum00.00
4.PCC in Foundation380.00 cum19.880.00 cum0.00 cum00.00
5.Construction Embankments19401.00 cum10.590.00 cum0.00 cum00.00
6.Launching Aprons931.50 cum78.960.00 cum0.00 cum00.00
7.Excavation in soil18457.00 cum7.060.00 cum0.00 cum00.00
8.CC in R/W and B/W10679.50 cum636.820.00 cum0.00 cum00.00
9.RRM in R/W and B/W4860.00 cum151.640.00 cum0.00 cum00.00
10.TMT Bar in R/W25.50 mt13.240.00 mt0.00 mt00.00
11.H.P. Stone3823.00 cum4.090.00 cum0.00 cum00.00
Total Amount: 963.36 0   0
Remarks: No Remarks       Work Program Made On: 13-02-2020       Updation of work program on: 23-06-2020      
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Analysis:Not applicable because there is no Physical and Financial Progress
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
No Pics Available.
Number of Notice(s) issued: 16

Mobile Pic Upload

( last 20 Pics)
No Pic uploaded.