Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/07 Agreement signed
Project: IRRIGATION Package No.: 3003 Package Name: UDRP/AF/RBP/07 Sanction Cost: 738.00  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7404   Banswara Mandakani (0.902 KM.) (completed)
Procurement:
Package No.: 3003        Package Name: UDRP/AF/RBP/07        Tender Date: 16-08-2019        Current Status: Agreement signed        Achieved on Date: 14-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/07        Contractor Name: Chaudhary Sandeep Contractor & Suppliers       
Start Date: 21-01-2020        Intended Completion Date: 20-07-2021       
Total Bond Cost: 61098635 (610.99 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 9653484 for 316 days        LD Analysis for Milestone2: calculated LD is Rs 9653484 for 316 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan6.00 Job3.280.00 Job0.00 Job00.00
2.Other Allied Works & Finishing Work 15.00 Job12.670.00 Job0.00 Job00.00
3.Excavation in Foundation4119.00 cum12.140.00 cum0.00 cum00.00
4.PCC in Foundation304.00 cum15.580.00 cum0.00 cum00.00
5.Construction Embankments4921.00 cum2.680.00 cum0.00 cum00.00
6.Launching Aprons836.00 cum69.070.00 cum0.00 cum00.00
7.Excavation in soil11039.00 cum4.310.00 cum0.00 cum00.00
8.CC in R/W and B/W3711.00 cum226.420.00 cum0.00 cum00.00
9.RRM in R/W and B/W5534.00 cum169.230.00 cum0.00 cum00.00
10.TMT Bar in R/W27.00 mt13.940.00 mt0.00 mt00.00
11.H.P. Stone2470.00 cum16.210.00 cum0.00 cum00.00
Total Amount: 545.53 0   0
Remarks: No Remarks       Work Program Made On: 13-02-2020       Updation of work program on: 23-06-2020      
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Analysis:Not applicable because there is no Physical and Financial Progress
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 10
Number of Notice(s) issued: 15

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-11-2020Banswada siteStone breaking workASHISH SINGHunknownunknown See Pic
2.06-11-2020Banswada siteExcavation workASHISH SINGHunknownunknown See Pic
3.04-11-2020Excavation workBanswada siteASHISH SINGHunknownunknown See Pic
4.03-11-2020Banswada siteExcavation workASHISH SINGHunknownunknown See Pic
5.28-10-2020Banswada siteExcavation work at Banswada siteASHISH SINGHunknownunknown See Pic
6.20-10-2020Banswada siteLevel checking at Banswada siteASHISH SINGHunknownunknown See Pic
7.13-08-2020BanswadaBanswara siteDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
8.07-08-2020BanswadaBanswara siteDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
9.15-06-2020BanswadaBoard marked as do's and don't regarding Corona at BanswadaDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
10.15-06-2020BanswadaProject information board of Banswada SiteDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic