UDRP/AF/RBP/07
Agreement signed
|
Project: |
UDRP-AF(RBP) |
Package No.: |
3003 |
Package Name: |
UDRP/AF/RBP/07 |
Sanction Cost: |
738.00 lakhs |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA RPW |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7404 Banswara Mandakani (0.902 KM.) (in prorgress) |
|
Procurement: |
Package No.: 3003
Package Name: UDRP/AF/RBP/07
Tender Date: 16-08-2019
Current Status: Agreement signed
Achieved on Date: 14-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/RBP/07
Contractor Name: Chaudhary Sandeep Contractor & Suppliers
|
Start Date: 21-01-2020
Intended Completion Date: 31-03-2022
Original End Date: 20-07-2021
|
Total Bond Cost: 61098635 (610.99 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 21414849 for 701 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 6.00 Job | 3.28 | 6.00 Job | 5.00 Job | 0.5 | 2.73 | 2. | Other Allied Works & Finishing Work | 15.00 Job | 12.67 | 15.00 Job | 11.00 Job | 1.7 | 9.29 | 3. | Excavation in Foundation | 4119.00 cum | 12.14 | 4119.00 cum | 2945.00 cum | 1.59 | 8.68 | 4. | PCC in Foundation | 304.00 cum | 15.58 | 304.00 cum | 240.15 cum | 2.26 | 12.31 | 5. | Construction Embankments | 4921.00 cum | 2.68 | 4921.00 cum | 3070.00 cum | 0.31 | 1.67 | 6. | Launching Aprons | 836.00 cum | 69.07 | 836.00 cum | 650.00 cum | 9.84 | 53.70 | 7. | Excavation in soil | 11039.00 cum | 4.31 | 11039.00 cum | 7900.00 cum | 0.57 | 3.08 | 8. | CC in R/W and B/W | 3711.00 cum | 226.42 | 3711.00 cum | 3410.00 cum | 38.14 | 208.05 | 9. | RRM in R/W and B/W | 5534.00 cum | 169.23 | 5534.00 cum | 4606.93 cum | 25.82 | 140.88 | 10. | TMT Bar in R/W | 27.00 mt | 13.94 | 27.00 mt | 21.16 mt | 2 | 10.92 | 11. | H.P. Stone | 2470.00 cum | 16.21 | 2470.00 cum | 2000.00 cum | 2.41 | 13.13 |
Total Amount: |
545.53 |
|
85.14 |
464.44 |
|
Remarks:
No Remarks
Work Program Made On:
13-02-2020
Updation of work program on:
07-02-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-February-2021 | 67.23 lakhs |
2. | 27-March-2021 | 58.29 lakhs |
3. | 31-May-2021 | 68.97 lakhs |
4. | 09-July-2021 | 35.06 lakhs |
5. | 31-January-2022 | 98.53 lakhs |
6. | 03-March-2022 | 30.00 lakhs |
7. | 31-March-2022 | 61.85 lakhs |
8. | 31-May-2022 | 40.96 lakhs |
Total |
460.89 lakhs |
% Payment |
75.43 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Banswara Mandakani(7404) | EMP |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 254 |
Number of Notice(s) issued: 89 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-04-2022 | Ch-120-130 | M-20CC concrete work block | Vinod Kumar Gupta | ` | ` | See Pic |
2. | 22-04-2022 | Ch 450 to u/s | RRM structure | Vinod Kumar Gupta | ` | ` | See Pic |
3. | 13-04-2022 | Ch -440-450 RRM WORK 5th lift | RRM WORK in progress | Vinod Kumar Gupta | ` | ` | See Pic |
4. | 12-04-2022 | Ch-440-450 rrm work 4th lift | RRM WORK in progress | Vinod Kumar Gupta | ` | ` | See Pic |
5. | 12-04-2022 | Ch -440-450 rrm 4th lift | RRM WORK in progress | Vinod Kumar Gupta | ` | ` | See Pic |
6. | 08-04-2022 | Ch-170 to 180cc block shuttering | CC block shuttering work | Vinod Kumar Gupta | ` | ` | See Pic |
7. | 07-04-2022 | Ch-430-440 RRM 6th lift | RRM WORK 6th lift | Vinod Kumar Gupta | ` | ` | See Pic |
8. | 06-04-2022 | Ch-430-440, RRM WORK | RRM WORK 5th lift | Vinod Kumar Gupta | ` | ` | See Pic |
9. | 06-04-2022 | Panel number 440 se 450 site visit environment expert EE, and CSC and contractor staff | Site visit environment expert | Vinod Kumar Gupta | ` | ` | See Pic |
10. | 06-04-2022 | Gabion block 180-190 | M-20CC concrete work | Vinod Kumar Gupta | ` | ` | See Pic |
11. | 06-04-2022 | Change -30-40 | Site visit AE EE,JE, CSC contactors staff | Vinod Kumar Gupta | ` | ` | See Pic |
12. | 01-04-2022 | Ch-430-440 d/s | Site views | Vinod Kumar Gupta | ` | ` | See Pic |
13. | 31-03-2022 | Banswara site visit AE,JE, Social expert,CSC and contactor staff | Visit at Banswada site | Vinod Kumar Gupta | ` | ` | See Pic |
14. | 31-03-2022 | Banswara site | Air monitoring test | Vinod Kumar Gupta | ` | ` | See Pic |
15. | 31-03-2022 | Ch- 350-360 m-30 facia 2nd lift | Rebond hammer test | Vinod Kumar Gupta | ` | ` | See Pic |
16. | 31-03-2022 | Ch-60 to 70 facia 2nd lift m-30rcc | Core cutting facia | Vinod Kumar Gupta | ` | ` | See Pic |
17. | 31-03-2022 | Ch-450 to u/s | Site rrm work and site cleaning | Vinod Kumar Gupta | ` | ` | See Pic |
18. | 26-03-2022 | Panel location 430-440 m-20cc concrete | M-20CC concrete work | Vinod Kumar Gupta | ` | ` | See Pic |
19. | 26-03-2022 | Panel location 430-440 Excavation work | Excavation work at Banswara site | Vinod Kumar Gupta | ` | ` | See Pic |
20. | 26-03-2022 | Panel location 110-120 rrm 5th lift | RRM WORK in progress | Vinod Kumar Gupta | ` | ` | See Pic |
|
|