Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/05 Agreement signed
Project: UDRP-AF(RBP) Package No.: 3002 Package Name: UDRP/AF/RBP/05 Sanction Cost: 2566.00  lakhs
District: Tehri Block: Kirtinagar Constituency: Deoprayag Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7412   Dewali RB Alaknanda (0.726 KM.) (completed)
Procurement:
Package No.: 3002        Package Name: UDRP/AF/RBP/05        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/05        Contractor Name: Bharat Construction       
Start Date: 05-11-2018        Intended Completion Date: 25-12-2021        Original End Date:  04-05-2020
Total Bond Cost: 222747269 (2227.47 lakhs)        Variation Cost: 9845037.00 (98.45 lakhs)     Hence Total Bond Cost is   232592306 (2325.92 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 55464252 for 498 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan2.00 Job1.902.00 Job2.00 Job0.081.90
2.Other Allied Works & Finishing Work 15.00 Job8.2715.00 Job15.00 Job0.348.27
3.Excavation in Foundation23890.33 cum45.4923890.33 cum23890.33 cum1.5545.49
4.PCC in Foundation742.50 cum44.07742.50 cum742.50 cum1.544.07
5.Construction Embankments37106.00 cum62.3437106.00 cum37106.00 cum2.9762.34
6.Launching Aprons4394.14 cum132.884394.14 cum4394.14 cum5.74132.88
7.Excavation in soil16495.20 cum31.4116495.20 cum16495.20 cum1.2731.41
8.CC in R/W and B/W13816.55 cum1060.4813816.55 cum13816.55 cum44.521000.00
9.TMT Bar in R/W1410.49 mt853.061410.49 mt1410.49 mt37.57853.06
10.H.P. Stone3211.73 cum32.373211.73 cum3211.73 cum1.532.37
11.Construction of Ghats1.00 Job60.701.00 Job1.00 Job2.9660.70
Total Amount: 2332.97 100   2272.49
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 28-05-2022      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-2019171.79  lakhs
2.29-June-2019149.09  lakhs
3.23-October-201965.87  lakhs
4.24-December-2019132.00  lakhs
5.25-February-2020320.84  lakhs
6.06-March-2020287.67  lakhs
7.06-May-2020160.61  lakhs
8.08-October-202014.97  lakhs
9.12-November-2020158.30  lakhs
10.17-November-202056.71  lakhs
11.24-December-2020216.20  lakhs
12.25-January-202118.17  lakhs
13.01-February-2021153.76  lakhs
14.27-March-2021273.95  lakhs
15.31-March-202150.00  lakhs
16.30-September-202167.28  lakhs
17.31-March-202219.27  lakhs
18.31-May-20229.29  lakhs
Total 2325.77  lakhs
% Payment 99.99 %
Advance Amount:  99.44  lakhs        Recovered Amount:  99.44  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 4284     No. of Test Done : 4297      No. of Test Passed : 4284      No. of Test Failed : 13   Test report of this package
Number of Pics Available on Web Repository: 495
Number of Notice(s) issued: 151

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-03-2022Devali-jakhniChanging room work is completed 24/12/21.PRABHAT BALONI ` ` See Pic
2.31-03-2022Devali-jakhniGhat work is completed 25/12/21.PRABHAT BALONI ` ` See Pic
3.31-03-2022Devali-jakhniGhat work ( staircase) is completed 25/12/21.PRABHAT BALONI ` ` See Pic
4.17-01-2022Devali-jakhniCounterfort retaining wall work is completed 18/03/21PRABHAT BALONI ` ` See Pic
5.17-01-2022Devali-jakhniCounterfort retaining wall work is completed 18/03/21PRABHAT BALONI ` ` See Pic
6.17-01-2022Devali-jakhniCounterfort retaining wall work is completed 18/03/21PRABHAT BALONI ` ` See Pic
7.17-01-2022Devali-jakhnicounterfort retaining wall work is completed 18/03/2021PRABHAT BALONI ` ` See Pic
8.07-12-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
9.01-12-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
10.27-11-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
11.25-11-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
12.24-11-2021Devali-jakhniRiver diversion work in progress.PRABHAT ` ` See Pic
13.20-11-2021Devali-jakhniRiver diversion work in progressPRABHAT BALONI ` ` See Pic
14.01-11-2021Panel no 37,38Water level approx 1.4 mtrVinod Kumar Gupta ` ` See Pic
15.30-10-2021Up stream side water level 1.2 mtrNo increase water levelVinod Kumar Gupta ` ` See Pic
16.29-10-2021Panel no 36 at water levelNo increase water level approx 1.4Vinod Kumar Gupta ` ` See Pic
17.28-10-2021Down stream side water levelWater level approx 2.4 mtrVinod Kumar Gupta ` ` See Pic
18.27-10-2021Up stream sideWater level approx at 1.00 mtrVinod Kumar Gupta ` ` See Pic
19.25-10-2021Devali-jakhniRiver water level U/S side.PRABHAT ` ` See Pic
20.25-10-2021Devali-jakhniRiver water level d/s sidePRABHAT ` ` See Pic