UDRP/AF/RBP/05
Agreement signed
|
Project: |
UDRP-AF(RBP) |
Package No.: |
3002 |
Package Name: |
UDRP/AF/RBP/05 |
Sanction Cost: |
2566.00 lakhs |
District: |
Tehri |
Block: |
Kirtinagar |
Constituency: |
Deoprayag |
Circle: |
|
DEA: |
DEA RPW |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7412 Dewali RB Alaknanda (0.726 KM.) (completed) |
|
Procurement: |
Package No.: 3002
Package Name: UDRP/AF/RBP/05
Tender Date: 31-01-2018
Current Status: Agreement signed
Achieved on Date: 25-10-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/RBP/05
Contractor Name: Bharat Construction
|
Start Date: 05-11-2018
Intended Completion Date: 25-12-2021
Original End Date: 04-05-2020
|
Total Bond Cost: 222747269 (2227.47 lakhs)
Variation Cost: 9845037.00 (98.45 lakhs) Hence Total Bond Cost is 232592306 (2325.92 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 55464252 for 498 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 2.00 Job | 1.90 | 2.00 Job | 2.00 Job | 0.08 | 1.90 | 2. | Other Allied Works & Finishing Work | 15.00 Job | 8.27 | 15.00 Job | 15.00 Job | 0.34 | 8.27 | 3. | Excavation in Foundation | 23890.33 cum | 45.49 | 23890.33 cum | 23890.33 cum | 1.55 | 45.49 | 4. | PCC in Foundation | 742.50 cum | 44.07 | 742.50 cum | 742.50 cum | 1.5 | 44.07 | 5. | Construction Embankments | 37106.00 cum | 62.34 | 37106.00 cum | 37106.00 cum | 2.97 | 62.34 | 6. | Launching Aprons | 4394.14 cum | 132.88 | 4394.14 cum | 4394.14 cum | 5.74 | 132.88 | 7. | Excavation in soil | 16495.20 cum | 31.41 | 16495.20 cum | 16495.20 cum | 1.27 | 31.41 | 8. | CC in R/W and B/W | 13816.55 cum | 1060.48 | 13816.55 cum | 13816.55 cum | 44.52 | 1000.00 | 9. | TMT Bar in R/W | 1410.49 mt | 853.06 | 1410.49 mt | 1410.49 mt | 37.57 | 853.06 | 10. | H.P. Stone | 3211.73 cum | 32.37 | 3211.73 cum | 3211.73 cum | 1.5 | 32.37 | 11. | Construction of Ghats | 1.00 Job | 60.70 | 1.00 Job | 1.00 Job | 2.96 | 60.70 |
Total Amount: |
2332.97 |
|
100 |
2272.49 |
|
Remarks:
No Remarks
Work Program Made On:
31-01-2019
Updation of work program on:
28-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2019 | 171.79 lakhs |
2. | 29-June-2019 | 149.09 lakhs |
3. | 23-October-2019 | 65.87 lakhs |
4. | 24-December-2019 | 132.00 lakhs |
5. | 25-February-2020 | 320.84 lakhs |
6. | 06-March-2020 | 287.67 lakhs |
7. | 06-May-2020 | 160.61 lakhs |
8. | 08-October-2020 | 14.97 lakhs |
9. | 12-November-2020 | 158.30 lakhs |
10. | 17-November-2020 | 56.71 lakhs |
11. | 24-December-2020 | 216.20 lakhs |
12. | 25-January-2021 | 18.17 lakhs |
13. | 01-February-2021 | 153.76 lakhs |
14. | 27-March-2021 | 273.95 lakhs |
15. | 31-March-2021 | 50.00 lakhs |
16. | 30-September-2021 | 67.28 lakhs |
17. | 31-March-2022 | 19.27 lakhs |
18. | 31-May-2022 | 9.29 lakhs |
Total |
2325.77 lakhs |
% Payment |
99.99 % |
|
Advance Amount: 99.44 lakhs
Recovered Amount: 99.44 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 495 |
Number of Notice(s) issued: 151 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-03-2022 | Devali-jakhni | Changing room work is completed 24/12/21. | PRABHAT BALONI | ` | ` | See Pic |
2. | 31-03-2022 | Devali-jakhni | Ghat work is completed 25/12/21. | PRABHAT BALONI | ` | ` | See Pic |
3. | 31-03-2022 | Devali-jakhni | Ghat work ( staircase) is completed 25/12/21. | PRABHAT BALONI | ` | ` | See Pic |
4. | 17-01-2022 | Devali-jakhni | Counterfort retaining wall work is completed 18/03/21 | PRABHAT BALONI | ` | ` | See Pic |
5. | 17-01-2022 | Devali-jakhni | Counterfort retaining wall work is completed 18/03/21 | PRABHAT BALONI | ` | ` | See Pic |
6. | 17-01-2022 | Devali-jakhni | Counterfort retaining wall work is completed 18/03/21 | PRABHAT BALONI | ` | ` | See Pic |
7. | 17-01-2022 | Devali-jakhni | counterfort retaining wall work is completed 18/03/2021 | PRABHAT BALONI | ` | ` | See Pic |
8. | 07-12-2021 | Devali-jakhni | Diversion work in progress | PRABHAT | ` | ` | See Pic |
9. | 01-12-2021 | Devali-jakhni | Diversion work in progress | PRABHAT | ` | ` | See Pic |
10. | 27-11-2021 | Devali-jakhni | Diversion work in progress | PRABHAT | ` | ` | See Pic |
11. | 25-11-2021 | Devali-jakhni | Diversion work in progress | PRABHAT | ` | ` | See Pic |
12. | 24-11-2021 | Devali-jakhni | River diversion work in progress. | PRABHAT | ` | ` | See Pic |
13. | 20-11-2021 | Devali-jakhni | River diversion work in progress | PRABHAT BALONI | ` | ` | See Pic |
14. | 01-11-2021 | Panel no 37,38 | Water level approx 1.4 mtr | Vinod Kumar Gupta | ` | ` | See Pic |
15. | 30-10-2021 | Up stream side water level 1.2 mtr | No increase water level | Vinod Kumar Gupta | ` | ` | See Pic |
16. | 29-10-2021 | Panel no 36 at water level | No increase water level approx 1.4 | Vinod Kumar Gupta | ` | ` | See Pic |
17. | 28-10-2021 | Down stream side water level | Water level approx 2.4 mtr | Vinod Kumar Gupta | ` | ` | See Pic |
18. | 27-10-2021 | Up stream side | Water level approx at 1.00 mtr | Vinod Kumar Gupta | ` | ` | See Pic |
19. | 25-10-2021 | Devali-jakhni | River water level U/S side. | PRABHAT | ` | ` | See Pic |
20. | 25-10-2021 | Devali-jakhni | River water level d/s side | PRABHAT | ` | ` | See Pic |
|
|