                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/04 Agreement signed
Project: IRRIGATION Package No.: 3001 Package Name: UDRP/AF/RBP/04 Sanction Cost: 2106.00  lakhs
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7411   Birahi Village RB Alaknanda (0.472 KM.) (in prorgress)
Procurement:
Package No.: 3001        Package Name: UDRP/AF/RBP/04        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/04        Contractor Name: Bharat Construction       
Start Date: 05-11-2018        Intended Completion Date: 28-03-2021        Original End Date:  04-05-2020
Total Bond Cost: 173171085 (1731.71 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 65891946 for 761 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works0.00 m0.000.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.702.00 Job1.00 Job0.060.85
3.Other Allied Works & Finishing Work 15.00 Job16.4115.00 Job8.00 Job0.578.75
4.Excavation in Foundation10193.00 cum15.2910193.00 cum6819.55 cum0.6610.23
5.PCC in Foundation554.00 cum28.81554.00 cum247.50 cum0.8312.87
6.Construction Embankments3207.00 cum4.813207.00 cum1008.97 cum0.11.51
7.Launching Aprons2410.00 cum144.602410.00 cum0.00 cum00.00
8.Excavation in soil31281.00 cum62.5631281.00 cum15765.36 cum2.0431.53
9.CC in R/W and B/W19216.00 cum1131.0619216.00 cum8710.00 cum33.16512.71
10.RRM in R/W and B/W3940.00 cum106.383940.00 cum3719.00 cum6.49100.41
11.TMT Bar in R/W11.00 mt6.6011.00 mt10.80 mt0.426.48
12.H.P. Stone3493.00 cum27.943493.00 cum1509.85 cum0.7812.08
Total Amount: 1546.16 45.11   697.42
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 22-06-2020      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.12-March-201932.89  lakhs
2.14-March-201991.82  lakhs
3.29-April-201958.43  lakhs
4.14-May-201953.00  lakhs
5.17-May-201994.66  lakhs
6.19-June-2019100.15  lakhs
7.25-February-202056.00  lakhs
8.07-March-202060.59  lakhs
9.01-May-2020220.81  lakhs
Total 768.35  lakhs
% Payment 44.37 %
Advance Amount:  77.31  lakhs        Recovered Amount:  68.60  lakhs        Balance to be Recovered  8.71  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Birahi Village RB Alaknanda(7411) debris disposal
Detailed report of this Package
Quality
No. of Test Required : 1057     No. of Test Done : 1064      No. of Test Passed : 1057      No. of Test Failed : 7   Test report of this package
Number of Pics Available on Web Repository: 311
Number of Notice(s) issued: 120

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-07-2020300 to 370Water level increase at birahi siteRakesh Singh rawatunknownunknown See Pic
2.21-03-2020BirahiCube testRohit YadavQCDSC WB Irrigation Chamoli See Pic
3.18-03-2020BirahiAIV testRakesh Singh rawatunknownunknown See Pic
4.16-03-2020BirahiSilt contentRohit YadavQCDSC WB Irrigation Chamoli See Pic
5.22-02-2020194 to 204shuttering workRakesh Singh rawatunknownunknown See Pic
6.19-02-2020At birahi 194 to 204Reinforced for faciaRakesh Singh rawatunknownunknown See Pic
7.18-02-2020Chainage at 194 to 204Shuttering work second lift of foundationRakesh Singh rawatunknownunknown See Pic
8.15-02-2020164 to 204Excavation workRakesh Singh rawatunknownunknown See Pic
9.14-02-2020BirahiExcavation work at Birahi SiteAkhilesh Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
10.12-02-2020BirahiCh. 204 to 214 3rd lift superstructure m15 grade concrete work in progressRohit YadavQCDSC WB Irrigation Chamoli See Pic
11.12-02-2020BirahiCh. 204 to 214 3rd lift superstructure m15 grade concrete work in progressRohit YadavQCDSC WB Irrigation Chamoli See Pic
12.08-02-2020Chain age 150 to 164RRM work at birahiRakesh Singh rawatunknownunknown See Pic
13.07-02-2020Chainage bw 200 to 220Shuttering for M15 concrete workRakesh Singh rawatunknownunknown See Pic
14.07-02-2020Chainage 150 to 164At birahiRakesh Singh rawatunknownunknown See Pic
15.30-01-2020BirahiBoulder breaking and dressing of boulders at Birahi SiteAkhilesh Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
16.30-01-2020BirahiHPS filling at Birahi SiteAkhilesh Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
17.30-01-2020BirahiR.R.M.work between ch 150 to 164 mAkhilesh Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
18.04-01-2020BirahiFacia Reinforcement work in progress. Ch 90 to 100SukhChain NegiJEUDRP AF S&B PAURI See Pic
19.03-01-2020BirahiLevel checkingSukhChain NegiJEUDRP AF S&B PAURI See Pic
20.01-01-2020BirahiFacia 2nd lift Reinforcement work in progress ch 90 to 100SukhChain NegiJEUDRP AF S&B PAURI See Pic