UDRP/AF/RBP/04
Agreement signed
|
Project: |
UDRP-AF(RBP) |
Package No.: |
3001 |
Package Name: |
UDRP/AF/RBP/04 |
Sanction Cost: |
2106.00 lakhs |
District: |
Chamoli |
Block: |
Dasholi |
Constituency: |
Badrinath |
Circle: |
प्रथम वृत्त, लो0नि0वि0, अल्मोडा |
DEA: |
DEA RPW |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7411 Birahi Village RB Alaknanda (0.472 KM.) (completed) |
|
Procurement: |
Package No.: 3001
Package Name: UDRP/AF/RBP/04
Tender Date: 31-01-2018
Current Status: Agreement signed
Achieved on Date: 25-10-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/RBP/04
Contractor Name: Bharat Construction
|
Start Date: 05-11-2018
Intended Completion Date: 28-03-2021
Original End Date: 04-05-2020
|
Total Bond Cost: 173171085 (1731.71 lakhs)
Variation Cost: 6394629.00 (63.95 lakhs) Hence Total Bond Cost is 179565714 (1795.66 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 59571168 for 688 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Env. Man & Moni Plan | 2.00 Job | 1.90 | 2.00 Job | 2.00 Job | 0.11 | 1.90 | 2. | Other Allied Works & Finishing Work | 15.00 Job | 16.81 | 15.00 Job | 15.00 Job | 0.94 | 16.81 | 3. | Excavation in Foundation | 10174.34 cum | 17.09 | 10174.34 cum | 10174.34 cum | 0.95 | 17.09 | 4. | PCC in Foundation | 546.41 cum | 31.82 | 546.41 cum | 546.41 cum | 1.77 | 31.82 | 5. | Construction Embankments | 10019.81 cum | 16.83 | 10019.81 cum | 10019.81 cum | 0.94 | 16.83 | 6. | Launching Aprons | 2375.77 cum | 190.05 | 2375.77 cum | 2375.77 cum | 10.58 | 190.05 | 7. | Excavation in soil | 34291.86 cum | 76.81 | 34291.86 cum | 34291.86 cum | 4.28 | 76.81 | 8. | CC in R/W and B/W | 18771.44 cum | 1273.11 | 18771.44 cum | 18771.44 cum | 70.9 | 1000.00 | 9. | RRM in R/W and B/W | 3891.24 cum | 117.67 | 3891.24 cum | 3891.24 cum | 6.55 | 117.67 | 10. | TMT Bar in R/W | 33.54 mt | 22.54 | 33.54 mt | 33.54 mt | 1.26 | 22.54 | 11. | H.P. Stone | 3461.86 cum | 31.02 | 3461.86 cum | 3461.86 cum | 1.73 | 31.02 |
Total Amount: |
1795.65 |
|
100 |
1522.54 |
|
Remarks:
No Remarks
Work Program Made On:
31-01-2019
Updation of work program on:
26-08-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-March-2019 | 32.89 lakhs |
2. | 14-March-2019 | 91.82 lakhs |
3. | 29-April-2019 | 58.43 lakhs |
4. | 14-May-2019 | 53.00 lakhs |
5. | 17-May-2019 | 94.66 lakhs |
6. | 19-June-2019 | 100.15 lakhs |
7. | 25-February-2020 | 56.00 lakhs |
8. | 07-March-2020 | 60.59 lakhs |
9. | 01-May-2020 | 220.81 lakhs |
10. | 30-December-2020 | 176.98 lakhs |
11. | 25-January-2021 | 91.92 lakhs |
12. | 01-February-2021 | 224.79 lakhs |
13. | 26-February-2021 | 226.65 lakhs |
14. | 27-March-2021 | 173.59 lakhs |
15. | 31-March-2021 | 50.00 lakhs |
16. | 30-September-2021 | 83.37 lakhs |
Total |
1795.65 lakhs |
% Payment |
100 % |
|
Advance Amount: 77.31 lakhs
Recovered Amount: 77.31 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 340 |
Number of Notice(s) issued: 145 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-03-2022 | Test | Test | Hitesh | ` | ` | See Pic |
2. | 22-03-2021 | 194 to 204 | M20 final lift in progress | Deepak | ` | ` | See Pic |
3. | 15-03-2021 | 214 to 224 | 7th lift shuttering work in progress | Deepak | ` | ` | See Pic |
4. | 14-03-2021 | 481 to downstream | Apron excavation work | Deepak | ` | ` | See Pic |
5. | 09-03-2021 | 0 to 11 | Excavation work in progress | Rakesh | ` | ` | See Pic |
6. | 09-03-2021 | 0 to 11 | Excavation work in progress | Deepak | ` | ` | See Pic |
7. | 09-03-2021 | 224 to 234 | M15 work in progress 5th lift | Deepak | ` | ` | See Pic |
8. | 06-03-2021 | 224 to 234 | M15 work in progress | Deepak | ` | ` | See Pic |
9. | 06-03-2021 | 224 to 234 | M15 work in progress | Rakesh | ` | ` | See Pic |
10. | 05-03-2021 | 214 to 224 | 4th lift m15 work shuttering work in progress | Deepak | ` | ` | See Pic |
11. | 04-03-2021 | 194 to 204 | M15 work in progress | Deepak | ` | ` | See Pic |
12. | 04-03-2021 | 194 to 204 | M15 oiling work in progress | Deepak | ` | ` | See Pic |
13. | 01-03-2021 | 470 to 481 | M20 final lift in progress | Deepak | ` | ` | See Pic |
14. | 01-03-2021 | 470 to 481 | Last lift shuttering and oiling work in progress | Deepak | ` | ` | See Pic |
15. | 28-02-2021 | 380 to 390 | M20 facia top lift at birahi | Rakesh Singh rawat | ` | ` | See Pic |
16. | 27-02-2021 | 430 to 440 | M15 7th lift progress | Deepak | ` | ` | See Pic |
17. | 27-02-2021 | 440 to 450 | M15 work 6th lift | Deepak | ` | ` | See Pic |
18. | 25-02-2021 | 460 to 470 | M15 6th lift in progress | Deepak | ` | ` | See Pic |
19. | 25-02-2021 | 400 to 410 | Facia m20 work in progress 6th lift | Deepak | ` | ` | See Pic |
20. | 23-02-2021 | 380 to 390 | Facia M20 7th lift | Rakesh Singh rawat | ` | ` | See Pic |
|
|