Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/04 Agreement signed
Project: UDRP-AF(Public Building) Package No.: 3001 Package Name: UDRP/AF/RBP/04 Sanction Cost: 2106.00  lakhs
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7411   Birahi Village RB Alaknanda (0.472 KM.) (completed)
Procurement:
Package No.: 3001        Package Name: UDRP/AF/RBP/04        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/04        Contractor Name: Bharat Construction       
Start Date: 05-11-2018        Intended Completion Date: 28-03-2021        Original End Date:  04-05-2020
Total Bond Cost: 173171085 (1731.71 lakhs)        Variation Cost: 6394629.00 (63.95 lakhs)     Hence Total Bond Cost is   179565714 (1795.66 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 59571168 for 688 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works0.00 m0.000.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.902.00 Job2.00 Job0.111.90
3.Other Allied Works & Finishing Work 15.00 Job16.8115.00 Job15.00 Job0.9416.81
4.Excavation in Foundation10174.34 cum17.0910174.34 cum10174.34 cum0.9517.09
5.PCC in Foundation546.41 cum31.82546.41 cum546.41 cum1.7731.82
6.Construction Embankments10019.81 cum16.8310019.81 cum10019.81 cum0.9416.83
7.Launching Aprons2375.77 cum190.052375.77 cum2375.77 cum10.58190.05
8.Excavation in soil34291.86 cum76.8134291.86 cum34291.86 cum4.2876.81
9.CC in R/W and B/W18771.44 cum1273.1118771.44 cum18771.44 cum70.91000.00
10.RRM in R/W and B/W3891.24 cum117.673891.24 cum3891.24 cum6.55117.67
11.TMT Bar in R/W33.54 mt22.5433.54 mt33.54 mt1.2622.54
12.H.P. Stone3461.86 cum31.023461.86 cum3461.86 cum1.7331.02
Total Amount: 1795.65 100   1522.54
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 26-08-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.12-March-201932.89  lakhs
2.14-March-201991.82  lakhs
3.29-April-201958.43  lakhs
4.14-May-201953.00  lakhs
5.17-May-201994.66  lakhs
6.19-June-2019100.15  lakhs
7.25-February-202056.00  lakhs
8.07-March-202060.59  lakhs
9.01-May-2020220.81  lakhs
10.30-December-2020176.98  lakhs
11.25-January-202191.92  lakhs
12.01-February-2021224.79  lakhs
13.26-February-2021226.65  lakhs
14.27-March-2021173.59  lakhs
15.31-March-202150.00  lakhs
Total 1712.28  lakhs
% Payment 95.36 %
Advance Amount:  77.31  lakhs        Recovered Amount:  77.31  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 2853     No. of Test Done : 2860      No. of Test Passed : 2853      No. of Test Failed : 7   Test report of this package
Number of Pics Available on Web Repository: 339
Number of Notice(s) issued: 145

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-03-2021194 to 204M20 final lift in progressDeepak ` ` See Pic
2.15-03-2021214 to 2247th lift shuttering work in progressDeepak ` ` See Pic
3.14-03-2021481 to downstreamApron excavation workDeepak ` ` See Pic
4.09-03-20210 to 11Excavation work in progressRakesh ` ` See Pic
5.09-03-20210 to 11Excavation work in progressDeepak ` ` See Pic
6.09-03-2021224 to 234M15 work in progress 5th liftDeepak ` ` See Pic
7.06-03-2021224 to 234M15 work in progressDeepak ` ` See Pic
8.06-03-2021224 to 234M15 work in progressRakesh ` ` See Pic
9.05-03-2021214 to 2244th lift m15 work shuttering work in progressDeepak ` ` See Pic
10.04-03-2021194 to 204M15 work in progressDeepak ` ` See Pic
11.04-03-2021194 to 204M15 oiling work in progressDeepak ` ` See Pic
12.01-03-2021470 to 481M20 final lift in progressDeepak ` ` See Pic
13.01-03-2021470 to 481Last lift shuttering and oiling work in progressDeepak ` ` See Pic
14.28-02-2021380 to 390M20 facia top lift at birahiRakesh Singh rawat ` ` See Pic
15.27-02-2021430 to 440M15 7th lift progressDeepak ` ` See Pic
16.27-02-2021440 to 450M15 work 6th liftDeepak ` ` See Pic
17.25-02-2021460 to 470M15 6th lift in progressDeepak ` ` See Pic
18.25-02-2021400 to 410Facia m20 work in progress 6th liftDeepak ` ` See Pic
19.23-02-2021380 to 390Facia M20 7th liftRakesh Singh rawat ` ` See Pic
20.21-02-2021440 to 450Slump test m15 grade.Deepak ` ` See Pic