Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/02 Agreement signed
Project: UDRP-AF(RBP) Package No.: 3000 Package Name: UDRP/AF/RBP/02 Sanction Cost: 1517.00  lakhs
District: Chamoli Block: Dasholi Constituency: Karanprayag Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7408   Alakapuri Kathiyal Sain Alaknanda (0.423 KM.) (in prorgress)
Procurement:
Package No.: 3000        Package Name: UDRP/AF/RBP/02        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/02        Contractor Name: GSCO Infrastructure Pvt Ltd.       
Start Date: 05-11-2018        Intended Completion Date: 28-03-2021        Original End Date:  04-05-2020
Total Bond Cost: 123153672 (1231.54 lakhs)        Variation Cost: -17993600.00 (-179.94 lakhs)     Hence Total Bond Cost is   105160072 (1051.6 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 17426291 for 283 days        LD Analysis for Milestone2: calculated LD is Rs 25308147 for 411 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Env. Man & Moni Plan2.00 Job1.472.00 Job2.00 Job0.121.47
2.Other Allied Works & Finishing Work 15.00 Job13.5915.00 Job15.00 Job2.6213.59
3.Excavation in Foundation6378.65 cum17.866378.65 cum6378.25 cum1.6617.86
4.PCC in Foundation368.55 cum22.29368.55 cum368.55 cum2.2922.29
5.Construction Embankments10398.84 cum6.4110398.84 cum10398.84 cum0.456.41
6.Launching Aprons1308.00 cum105.411308.00 cum1308.00 cum12.09105.41
7.Excavation in soil20747.64 cum10.4620747.64 cum20747.64 cum1.3910.46
8.CC in R/W and B/W7493.06 cum539.217493.06 cum7493.06 cum42.84539.21
9.RRM in R/W and B/W8557.46 cum299.518557.46 cum8557.46 cum34.02299.51
10.TMT Bar in R/W25.19 mt16.3625.19 mt25.19 mt0.5816.36
11.H.P. Stone3090.86 cum19.043090.86 cum3090.86 cum1.9319.04
Total Amount: 1051.61 100   1051.61
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 17-08-2021      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-March-201938.93  lakhs
2.14-May-201952.91  lakhs
3.18-July-201958.51  lakhs
4.24-February-2020102.11  lakhs
5.25-February-202084.08  lakhs
6.07-March-202023.04  lakhs
7.01-May-202098.81  lakhs
8.30-December-2020165.27  lakhs
9.25-January-202131.58  lakhs
10.06-February-2021106.82  lakhs
11.06-March-202194.92  lakhs
12.27-March-202187.05  lakhs
13.31-March-202120.00  lakhs
14.30-September-202187.58  lakhs
Total 1051.61  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Alakapuri Kathiyal Sain Alaknanda(7408) debris disposal
Detailed report of this Package
Quality
No. of Test Required : 1498     No. of Test Done : 1508      No. of Test Passed : 1498      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 334
Number of Notice(s) issued: 125

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-03-2021KothiyalsainRRM work in progress ch_70 to 80m(5th lift)Ashutosh uniyal ` ` See Pic
2.20-03-2021KothiyalsainBoulder breaking workAshutosh uniyal ` ` See Pic
3.19-03-2021KothiyalsainRRM work in progress ch_70 to 80m(4th lift)Ashutosh uniyal ` ` See Pic
4.17-03-2021KothiyalsainApron work in progress ch_40 to 50mAshutosh uniyal ` ` See Pic
5.17-03-2021KothiyalsainCube testAshutosh uniyal ` ` See Pic
6.16-03-2021KothiyalsainRRM work in progress ch_460 to 470m(3rd lift)Ashutosh uniyal ` ` See Pic
7.13-03-2021KothiyalsainPcc m20 work ch_470 to 480m(3rd lift)Ashutosh uniyal ` ` See Pic
8.12-03-2021KothiyalsainExcavation for apron ch_30 to 40mAshutosh uniyal ` ` See Pic
9.12-03-2021KothiyalsainRRM work in progress ch_460 to 470m(1st lift)Ashutosh uniyal ` ` See Pic
10.09-03-2021KothiyalsainRRM work in progress ch_70 to 80m(3rd lift)Ashutosh uniyal ` ` See Pic
11.09-03-2021KothiyalsainExcavation work in progress dor apron ch_10 to 20mAshutosh uniyal ` ` See Pic
12.08-03-2021KothiyalsainShuttering work in progress ch_460 to 470m(3rd lift)Ashutosh uniyal ` ` See Pic
13.06-03-2021KothiylasainRRM work in progress ch_60 to 70m(2nd lift)Ashutosh uniyal ` ` See Pic
14.06-03-2021KothiyalsainExcavation work in progress ch_460 to 470mAshutosh uniyal ` ` See Pic
15.05-03-2021KothiyalsainRRM work in progress ch_70 to 80m(2nd lift)Ashutosh uniyal ` ` See Pic
16.04-03-2021KothiyalsainExcavation work for apron ch_0 to 30mAshutosh uniyal ` ` See Pic
17.03-03-2021KothiyalsainVisit photographsAshutosh uniyal ` ` See Pic
18.03-03-2021KothiylasainSite visit respected PIU technical experts and social environment teamAshutosh uniyal ` ` See Pic
19.01-03-2021KothiyalsainRRM work in progress ch_280 to 290m(8th lift)Ashutosh uniyal ` ` See Pic
20.27-02-2021KothiyalsainEnvironment test sampling done at siteAshutosh uniyal ` ` See Pic