Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/02 Agreement signed
Project: IRRIGATION Package No.: 3000 Package Name: UDRP/AF/RBP/02 Sanction Cost: 1517.00  lakhs
District: Chamoli Block: Dasholi Constituency: Karanprayag Circle:
DEA: DEA RPW DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7408   Alakapuri Kathiyal Sain Alaknanda (450.000 KM.) (in prorgress)
Procurement:
Package No.: 3000        Package Name: UDRP/AF/RBP/02        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/02        Contractor Name: GSCO Infrastructure Pvt Ltd.       
Start Date: 05-11-2018        Intended Completion Date: 04-05-2020       
Total Bond Cost: 109958636.25 (1099.59 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 11325674 for 206 days        LD Analysis for Milestone2: calculated LD is Rs 11325674 for 206 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works423.00 m0.00423.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.362.00 Job1.00 Job0.060.68
3.Other Allied Works & Finishing Work 15.00 Job28.8315.00 Job1.00 Job0.171.92
4.Excavation in Foundation7301.00 cum18.257301.00 cum1344.15 cum0.313.36
5.PCC in Foundation467.00 cum25.22467.00 cum57.32 cum0.283.09
6.Construction Embankments8974.00 cum4.948974.00 cum30.00 cum00.02
7.Launching Aprons2180.00 cum132.98423.00 cum0.00 cum00.00
8.Excavation in soil33849.00 cum15.2333849.00 cum2712.26 cum0.111.22
9.CC in R/W and B/W7711.00 cum471.107711.00 cum1078.00 cum5.9965.86
10.RRM in R/W and B/W11971.69 cum374.1211971.69 cum201.56 cum0.576.29
11.TMT Bar in R/W11.00 mt6.3811.00 mt0.54 mt0.030.31
12.H.P. Stone3850.00 cum21.183850.00 cum60.00 cum0.030.33
Total Amount: 1099.59 7.56   83.08
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 22-03-2019      
Work Program Status:Program Failed
Financial Progress
No Financial Progress.
Analysis:Not applicable because there is no Physical and Financial Progress
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): Conscent to establish., conscent to operate
Environment & Social Compliances(Sub Project level):
Alakapuri Kathiyal Sain Alaknanda(7408)EMP, debris disposal
Detailed report of this Package
Quality
No. of Test Required : 234     No. of Test Done : 235      No. of Test Passed : 227      No. of Test Failed : 8   Test report of this package
Number of Pics Available on Web Repository: 171
Number of Notice(s) issued: 6

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-05-2019kothiyalsainsite visit PIU Expert TeamPraveen Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
2.16-05-2019KothiyalsainSite visit.PIU. UDRP teamManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
3.15-05-2019kothiyalsain chainage 320-330RRM at section 320-330Praveen Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
4.11-05-2019KothiyalsainRRM work section-01 CH-0 to 10 mAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
5.08-05-2019KothiyalsainLevel checkingAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
6.07-05-2019KothiyalsainRRM work section-01 CH-0 to 10mAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
7.06-05-2019KothiyalsainExcavation work section-07 CH-350 to 360mAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
8.05-05-2019KothiyalsainSite discussionAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
9.05-05-2019KothiyalsainVisit by EE sir,AE sir with CSC staffAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
10.04-05-2019KothiyalsainCube TestAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
11.03-05-2019KothiyalsainCube castingAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
12.03-05-2019KothiyalsainSlump testAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
13.03-05-2019KothiyalsainPCC work M20 section-07 CH-340 to 350mAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
14.30-04-2019KothiyalsainCube test M20Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
15.30-04-2019KothiyalsainAIV test ReportAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
16.30-04-2019KothiyalsainAIV testAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
17.30-04-2019KothiyalsainDewatering work section-07Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
18.29-04-2019KothiyalsainSlump testAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
19.29-04-2019KothiyalsainConcrete casting work with front steelAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
20.29-04-2019KothiyalsainBoulder breaking workAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic