Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/02 Agreement signed
Project: IRRIGATION Package No.: 3000 Package Name: UDRP/AF/RBP/02 Sanction Cost: 1517.00  lakhs
District: Chamoli Block: Dasholi Constituency: Karanprayag Circle:
DEA: DEA RPW DSC: DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7408   Alakapuri Kathiyal Sain Alaknanda (450.000 KM.) (in prorgress)
Procurement:
Package No.: 3000        Package Name: UDRP/AF/RBP/02        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/02        Contractor Name: GSCO Infrastructure Pvt Ltd.       
Start Date: 05-11-2018        Intended Completion Date: 04-05-2020       
Total Bond Cost: 109958636.25 (1099.59 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 4453299 for 81 days        LD Analysis for Milestone2: 102 days remained       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works0.00 m0.000.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.362.00 Job1.00 Job0.060.68
3.Other Allied Works & Finishing Work 15.00 Job28.8315.00 Job3.00 Job0.525.77
4.Excavation in Foundation7301.00 cum18.257301.00 cum2168.34 cum0.495.42
5.PCC in Foundation467.00 cum25.22467.00 cum75.00 cum0.374.05
6.Construction Embankments8974.00 cum4.948974.00 cum111.61 cum0.010.06
7.Launching Aprons2180.00 cum132.982180.00 cum0.00 cum00.00
8.Excavation in soil33849.00 cum15.2333849.00 cum3938.63 cum0.161.77
9.CC in R/W and B/W7711.00 cum471.107711.00 cum1609.00 cum8.9498.32
10.RRM in R/W and B/W11971.69 cum374.1211971.69 cum631.00 cum1.7919.72
11.TMT Bar in R/W11.00 mt6.3811.00 mt3.35 mt0.181.94
12.H.P. Stone3850.00 cum21.183850.00 cum116.85 cum0.060.64
Total Amount: 1099.59 12.58   138.37
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 18-06-2019      
Work Program Status:Program Failed
Financial Progress
SNo. Date Payment
1.18-March-201938.93  lakhs
2.14-May-201952.91  lakhs
3.18-July-201958.51  lakhs
Total 150.35  lakhs
% Payment 13.67 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): Conscent to establish., conscent to operate
Environment & Social Compliances(Sub Project level):
Alakapuri Kathiyal Sain Alaknanda(7408)EMP, debris disposal
Detailed report of this Package
Quality
No. of Test Required : 278     No. of Test Done : 279      No. of Test Passed : 269      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 188
Number of Notice(s) issued: 6

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-07-2019KothiyalsainToday's kothiyalsain site sampling filled for mix desgin Grade of M20 and M30Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
2.22-07-2019KothiyalsainSection-01Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
3.22-07-2019KothiyalsainWater level increaseAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
4.11-07-2019KothiyalsainWater level increased todayAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
5.27-06-2019KothiyalsainWater level increaseAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
6.25-06-2019KothiyalsainCube testAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
7.24-06-2019KothiyalsainKothiyalsain siteAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
8.13-06-2019KothiyalsainLevel checking ch 160 to 170Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
9.06-06-2019KothiyalsainVisit Respected sir world bank team & FPIU and UDRPAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
10.05-06-2019KothiyalsainWaterlogging section-07Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
11.05-06-2019KothiyalsainRRM work section-07 CH-300 to 310 mAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
12.31-05-2019KothiyalsainExcavation work ch.380 to 390Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
13.24-05-2019KothiyalsainExcavation work ch .360 to 370Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
14.24-05-2019Kothiyaal sainCube test M20 28 daysManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
15.23-05-2019KothiyalsainBoulders breaking workManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
16.23-05-2019KothiyalsainFacia concrete nominal mix 1:2:4 ch.300 to 310Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
17.22-05-2019KothiyalsainPcc work ch.350 to 360Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
18.17-05-2019kothiyalsainsite visit PIU Expert TeamPraveen Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
19.16-05-2019KothiyalsainSite visit.PIU. UDRP teamManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
20.15-05-2019kothiyalsain chainage 320-330RRM at section 320-330Praveen Singh NegiJEUDRP-AF Irrigation Chamoli See Pic