Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/AF/RBP/02 Agreement signed
Project: IRRIGATION Package No.: 3000 Package Name: UDRP/AF/RBP/02 Sanction Cost: 1517.00  lakhs
District: Chamoli Block: Dasholi Constituency: Karanprayag Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7408   Alakapuri Kathiyal Sain Alaknanda (0.423 KM.) (in prorgress)
Procurement:
Package No.: 3000        Package Name: UDRP/AF/RBP/02        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/02        Contractor Name: GSCO Infrastructure Pvt Ltd.       
Start Date: 05-11-2018        Intended Completion Date: 04-05-2020       
Total Bond Cost: 109958636.25 (1099.59 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 12425254 for 226 days        LD Analysis for Milestone2: calculated LD is Rs 10061157 for 183 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works0.00 m0.000.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.362.00 Job2.00 Job0.121.36
3.Other Allied Works & Finishing Work 15.00 Job28.8315.00 Job3.00 Job0.525.77
4.Excavation in Foundation7301.00 cum18.257301.00 cum5114.00 cum1.1612.79
5.PCC in Foundation467.00 cum25.22467.00 cum200.00 cum0.9810.80
6.Construction Embankments8974.00 cum4.948974.00 cum1784.70 cum0.090.98
7.Launching Aprons2180.00 cum132.982180.00 cum0.00 cum00.00
8.Excavation in soil33849.00 cum15.2333849.00 cum10054.00 cum0.414.52
9.CC in R/W and B/W7711.00 cum471.107711.00 cum3489.32 cum19.39213.17
10.RRM in R/W and B/W11971.69 cum374.1211971.69 cum2508.00 cum7.1378.38
11.TMT Bar in R/W11.00 mt6.3811.00 mt7.77 mt0.414.51
12.H.P. Stone3850.00 cum21.183850.00 cum561.45 cum0.283.09
Total Amount: 1099.59 30.5   335.37
Remarks: No Remarks       Work Program Made On: 31-01-2019       Updation of work program on: 27-12-2019      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.18-March-201938.93  lakhs
2.14-May-201952.91  lakhs
3.18-July-201958.51  lakhs
4.24-February-2020102.11  lakhs
5.25-February-202084.08  lakhs
6.07-March-202023.04  lakhs
7.01-May-202098.81  lakhs
Total 458.39  lakhs
% Payment 41.69 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Alakapuri Kathiyal Sain Alaknanda(7408) debris disposal
Detailed report of this Package
Quality
No. of Test Required : 705     No. of Test Done : 715      No. of Test Passed : 705      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 297
Number of Notice(s) issued: 76

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-03-2020KothiyalsainCube test M20 28 daysManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
2.21-03-2020KothiyalsainSlump testRohit YadavQCDSC WB Irrigation Chamoli See Pic
3.19-03-2020KothiyalsainAIV test for concrete at kothiyalsainManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
4.19-03-2020Kothiyalsain20 mm gradationAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
5.18-03-2020KothiyalsainExcavation work in progress CH_70 to 80mAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
6.18-03-2020KothiyalsainCube testRohit YadavQCDSC WB Irrigation Chamoli See Pic
7.22-02-2020KothiyalsainBoulders breaking at kothiyaal sainManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
8.22-02-2020KothiyalsainPcc foundation work in progress CH-140-150mAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
9.22-02-2020KothiyalsainCube castingAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
10.19-02-2020KothiyalsainCube testAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
11.19-02-2020KothiyalsainCube casting M30 facie concrete ch 410 to 420Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
12.19-02-2020KothiyalsainDewatering workAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
13.17-02-2020KothiyalsainHealth camp organising at siteAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
14.17-02-2020KothiyalsainExcavation work in progress Ch-140-150mAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
15.15-02-2020KothiyalsainExcavation work ch 150 to 160Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
16.13-02-2020KothiyalsainExcavation work CH-150 to 160mAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
17.12-02-2020KothiyalsainCube casting M 20 pcc in foundation ch 160 to 170Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
18.12-02-2020KothiyalsainExcavation work in ch 150 to 160Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
19.04-02-2020KothiyalsainSand testAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic
20.01-02-2020KothiyalsainExcavation work ch-110 to 120mAshutosh UniyalSite SupervisorDSC WB Irrigation Chamoli See Pic