Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/01/34/RD/003 Agreement signed
Project: UDRP-RB Package No.: 3 Package Name: UDRP/PWD/01/34/RD/003 Sanction Cost: 183.27  lakhs
District: Uttarkashi Block: Naugaon Constituency: Purola Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 4
Subproject in this package
1  3143   Diyari setwade motor road (5.000 KM.) (completed)
2  3153   Garh Ambedkar motor road (4.000 KM.) (completed)
3  3154   Ghanrali Pul to sarbadiyar motor road (2.500 KM.) (completed)
4  3185   Naugoan Suri Motor road (7.000 KM.) (completed)
Procurement:
Package No.: 3        Package Name: UDRP/PWD/01/34/RD/003        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 11-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/34/RD/003        Contractor Name: Ram krishna Jayara       
Start Date: 18-07-2014        Intended Completion Date: 15-12-2015        Original End Date:  17-10-2015
Total Bond Cost: 13654413.89 (136.54 lakhs)        Variation Cost: 3187196.74 (31.87 lakhs)     Hence Total Bond Cost is   16841610.63 (168.42 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works955.00 m68.83955.00 m955.00 m39.9668.83
2.Road Furniture8.00 No0.838.00 No8.00 No0.490.83
3.GSB/RBI/G-12.75 KM16.502.75 KM2.75 KM9.9216.50
4.Culverts/Scupper 1.00 No7.491.00 No1.00 No3.967.49
5.longitudinal Drain5300.00 m33.165300.00 m5300.00 m18.4133.16
6.G-21.55 KM9.561.55 KM1.55 KM5.619.56
7.G-31.55 KM11.301.55 KM1.55 KM6.6311.30
8.PC/CC i/c Prime Coat, Tack Coat1.55 KM20.351.55 KM1.55 KM11.9520.35
9.Cause Way2.00 No5.232.00 No2.00 No3.075.23
Total Amount: 173.25 100   173.25
Remarks: No Remarks       Work Program Made On: 21-08-2014       Updation of work program on: 22-07-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-December-201422.89  lakhs
2.27-February-201521.28  lakhs
3.29-May-201527.82  lakhs
4.19-February-201630.09  lakhs
5.08-December-20179.69  lakhs
6.30-March-201516.15  lakhs
7.30-June-201512.02  lakhs
8.18-May-201614.30  lakhs
9.09-February-20180.30  lakhs
10.30-October-201513.06  lakhs
Total 167.6  lakhs
% Payment 99.52 %
Advance Amount:  10.10  lakhs        Recovered Amount:  10.10  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 777     No. of Test Done : 777      No. of Test Passed : 767      No. of Test Failed : 10   Test report of this package
Number of Pics Available on Web Repository: 282
Number of Notice(s) issued: 81

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-12-20160.000- 3.850N.O.C. By Mr. Dinesh Dhobhal, Regarding disposal and clearance of earth by contractor.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
2.18-10-2016Km7/0Information bordBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
3.06-10-20167/0Plum blockBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
4.04-10-20167+000Work completed as per bond.Sam Allen MatthewsTLDSC1 R&B WB See Pic
5.04-10-20161+750Bush cleaning required before handing over process.Sam Allen MatthewsTLDSC1 R&B WB See Pic
6.04-10-20167+000Informatory board is not as per specification. Need to be replaced.Sam Allen MatthewsTLDSC1 R&B WB See Pic
7.04-10-201600+000Informatory board need to be replaced.Sam Allen MatthewsTLDSC1 R&B WB See Pic
8.14-05-20162/5KC Drain work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
9.12-05-2016Km 1+200Laying and Rolling of WBM Grading -2Baru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
10.12-05-2016Km 0+300Plum blockBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.27-02-20160+300Layout of Box Culvert for Garh Dewal motor roadBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.27-02-20162/7KC drainBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.02-01-2016CH 1/6Screening materialManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
14.30-12-2015Chainage 2/0Kc drain work in progressManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
15.30-12-2015Chainage 2/5Kc drain work in progressManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
16.30-12-2015Chainage 2/9Kc drain work in progressManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
17.30-12-2015Chainage 2/6Kc drain work is completeManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
18.10-12-20152/36Checking of G2 grading by CE during visitPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
19.05-12-2015Chainage 9/0Pc work is completedManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
20.04-12-20152/28BHManeesh ChauhanJEUDRP R&B Uttarkashi See Pic