UDRP/PWD/01/34/RD/003
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
3 |
Package Name: |
UDRP/PWD/01/34/RD/003 |
Sanction Cost: |
183.27 lakhs |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
Tehri WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
4 |
Subproject in this package |
1 3143 Diyari setwade motor road (5.000 KM.) (completed) | 2 3153 Garh Ambedkar motor road (4.000 KM.) (completed) | 3 3154 Ghanrali Pul to sarbadiyar motor road (2.500 KM.) (completed) | 4 3185 Naugoan Suri Motor road (7.000 KM.) (completed) |
|
Procurement: |
Package No.: 3
Package Name: UDRP/PWD/01/34/RD/003
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 11-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/34/RD/003
Contractor Name: Ram krishna Jayara
|
Start Date: 18-07-2014
Intended Completion Date: 15-12-2015
Original End Date: 17-10-2015
|
Total Bond Cost: 13654413.89 (136.54 lakhs)
Variation Cost: 3187196.74 (31.87 lakhs) Hence Total Bond Cost is 16841610.63 (168.42 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 955.00 m | 68.83 | 955.00 m | 955.00 m | 39.96 | 68.83 | 2. | Road Furniture | 8.00 No | 0.83 | 8.00 No | 8.00 No | 0.49 | 0.83 | 3. | GSB/RBI/G-1 | 2.75 KM | 16.50 | 2.75 KM | 2.75 KM | 9.92 | 16.50 | 4. | Culverts/Scupper | 1.00 No | 7.49 | 1.00 No | 1.00 No | 3.96 | 7.49 | 5. | longitudinal Drain | 5300.00 m | 33.16 | 5300.00 m | 5300.00 m | 18.41 | 33.16 | 6. | G-2 | 1.55 KM | 9.56 | 1.55 KM | 1.55 KM | 5.61 | 9.56 | 7. | G-3 | 1.55 KM | 11.30 | 1.55 KM | 1.55 KM | 6.63 | 11.30 | 8. | PC/CC i/c Prime Coat, Tack Coat | 1.55 KM | 20.35 | 1.55 KM | 1.55 KM | 11.95 | 20.35 | 9. | Cause Way | 2.00 No | 5.23 | 2.00 No | 2.00 No | 3.07 | 5.23 |
Total Amount: |
173.25 |
|
100 |
173.25 |
|
Remarks:
No Remarks
Work Program Made On:
21-08-2014
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-December-2014 | 22.89 lakhs |
2. | 27-February-2015 | 21.28 lakhs |
3. | 29-May-2015 | 27.82 lakhs |
4. | 19-February-2016 | 30.09 lakhs |
5. | 08-December-2017 | 9.69 lakhs |
6. | 30-March-2015 | 16.15 lakhs |
7. | 30-June-2015 | 12.02 lakhs |
8. | 18-May-2016 | 14.30 lakhs |
9. | 09-February-2018 | 0.30 lakhs |
10. | 30-October-2015 | 13.06 lakhs |
Total |
167.6 lakhs |
% Payment |
99.52 % |
|
Advance Amount: 10.10 lakhs
Recovered Amount: 10.10 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 282 |
Number of Notice(s) issued: 81 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-12-2016 | 0.000- 3.850 | N.O.C. By Mr. Dinesh Dhobhal, Regarding disposal and clearance of earth by contractor. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
2. | 18-10-2016 | Km7/0 | Information bord | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
3. | 06-10-2016 | 7/0 | Plum block | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkahsi | See Pic |
4. | 04-10-2016 | 7+000 | Work completed as per bond. | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
5. | 04-10-2016 | 1+750 | Bush cleaning required before handing over process. | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
6. | 04-10-2016 | 7+000 | Informatory board is not as per specification. Need to be replaced. | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
7. | 04-10-2016 | 00+000 | Informatory board need to be replaced. | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
8. | 14-05-2016 | 2/5 | KC Drain work in progress | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
9. | 12-05-2016 | Km 1+200 | Laying and Rolling of WBM Grading -2 | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
10. | 12-05-2016 | Km 0+300 | Plum block | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 27-02-2016 | 0+300 | Layout of Box Culvert for Garh Dewal motor road | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
12. | 27-02-2016 | 2/7 | KC drain | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
13. | 02-01-2016 | CH 1/6 | Screening material | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
14. | 30-12-2015 | Chainage 2/0 | Kc drain work in progress | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
15. | 30-12-2015 | Chainage 2/5 | Kc drain work in progress | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
16. | 30-12-2015 | Chainage 2/9 | Kc drain work in progress | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
17. | 30-12-2015 | Chainage 2/6 | Kc drain work is complete | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
18. | 10-12-2015 | 2/36 | Checking of G2 grading by CE during visit | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
19. | 05-12-2015 | Chainage 9/0 | Pc work is completed | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
20. | 04-12-2015 | 2/28 | BH | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
|
|