Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/40/RD/028 Agreement signed
Project: UDRP-RB Package No.: 28 Package Name: UDRP/PWD/03/40/RD/028 Sanction Cost: 238.02  lakhs
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2517   Nagjagai-Fagu MR (4.000 KM.) (completed)
Procurement:
Package No.: 28        Package Name: UDRP/PWD/03/40/RD/028        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 20-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/028        Contractor Name: Sanjay Singh Negi       
Start Date: 27-02-2015        Intended Completion Date: 30-12-2017        Original End Date:  26-05-2016
Total Bond Cost: 18180409.46 (181.8 lakhs)        Variation Cost: 4321592.24 (43.22 lakhs)     Hence Total Bond Cost is   22502001.7 (225.02 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 1736190 for 191 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works550.00 m11.85550.00 m550.00 m7.1811.85
2.GSB/RBI/G-13.30 KM19.933.30 KM3.30 KM12.0719.93
3.G-23.30 KM15.893.30 KM3.30 KM9.6315.89
4.G-33.30 KM23.403.30 KM3.30 KM14.1723.40
5.PC/CC i/c Prime Coat, Tack Coat3.30 KM30.533.30 KM3.30 KM18.4930.53
6.Culverts/Scupper 8.00 No8.868.00 No8.00 No5.378.86
7.longitudinal Drain3880.00 m7.043880.00 m3880.00 m4.267.04
8.Crash Barrier2119.00 m38.352119.00 m2119.00 m23.2338.35
9.Parapet261.00 No7.98261.00 No261.00 No4.837.98
10.Road Furniture20.00 No1.2620.00 No20.00 No0.761.26
Total Amount: 165.09 100   165.09
Remarks: Lab not established       Work Program Made On: 28-09-2015       Updation of work program on: 24-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-March-20153.68  lakhs
2.31-March-20159.30  lakhs
3.13-June-20158.35  lakhs
4.24-June-201514.98  lakhs
5.31-October-20152.44  lakhs
6.26-December-20157.11  lakhs
7.10-March-201617.39  lakhs
8.02-May-201616.10  lakhs
9.02-June-20165.57  lakhs
10.21-September-201611.87  lakhs
11.26-October-20164.33  lakhs
12.31-July-20174.21  lakhs
13.15-October-201743.12  lakhs
14.18-November-201724.03  lakhs
15.22-December-201726.34  lakhs
16.23-March-201825.16  lakhs
Total 223.98  lakhs
% Payment 99.54 %
Advance Amount:  44.36  lakhs        Recovered Amount:  44.36  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 270     No. of Test Done : 306      No. of Test Passed : 285      No. of Test Failed : 21   Test report of this package
Number of Pics Available on Web Repository: 55
Number of Notice(s) issued: 116

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-07-2018Km 5.00 salya-Tulanga motor roadRoad opened for trafficRavi BishtJEUDRP R&B Guptkashi See Pic
2.22-07-2018Km 5.00 salya tulanga motor roadRoad cleaning in progressRavi BishtJEUDRP R&B Guptkashi See Pic
3.22-07-2018Km 5.00 salya-tulanga motor margRoad blocked due to slipRavi BishtJEUDRP R&B Guptkashi See Pic
4.22-07-2018Km 3.00 salya- tulanga motor roadRoad opened for trafficRavi BishtJEUDRP R&B Guptkashi See Pic
5.22-07-2018Km 3.00 salya-tulanga motor roadRoad blocked due to landslideRavi BishtJEUDRP R&B Guptkashi See Pic
6.22-07-2018Km 3.000Road opening is in progressRavi BishtJEUDRP R&B Guptkashi See Pic
7.19-07-20183.025SRMD JCB machine which was dumped in debris is taken out safely today by poclain ... road is open for communication today all vehicles are passed from km 3.00 safely.Siddharth RangharJEUDRP R&B Guptkashi See Pic
8.19-01-20181.800Patch repair over PC .Siddharth RangharJEUDRP R&B Guptkashi See Pic
9.22-11-20170+100Rolling on pc surfaceBhagwat Singh BangariSite SupervisorDSC4 R&B WB Rudraprayag See Pic
10.16-11-20171+420Rolling over pc surfaceDeepak PrasadSite SupervisorDSC4 R&B WB Rudraprayag See Pic
11.08-11-20171+010EE sir site visit ,seal coat layingBhagwat Singh BangariSite SupervisorDSC4 R&B WB Rudraprayag See Pic
12.03-11-20170+890Seal coat rolling under process chainage ... 0+890 Nagjagai FeguBhagwat Singh BangariSite SupervisorDSC4 R&B WB Rudraprayag See Pic
13.31-10-20171+890Laying seal coatBhagwat Singh BangariSite SupervisorDSC4 R&B WB Rudraprayag See Pic
14.27-10-20173.470Protection work by Retaining wallNandan RawatJEUDRP R&B Guptkashi See Pic
15.26-10-20172.340Seal coat after Premix CarpetSiddharth RangharJEUDRP R&B Guptkashi See Pic
16.24-10-20172.870Premix carpet work on progress rolling over seal coat.Nandan RawatJEUDRP R&B Guptkashi See Pic
17.23-10-20172.920Premix carpet work laying in progress Nagjagai fegu Motor RoadSiddharth RangharJEUDRP R&B Guptkashi See Pic
18.22-10-20172+750Nagjaigu fegu m/r Rolling of PCNandan RawatJEUDRP R&B Guptkashi See Pic
19.11-10-20173+470Ee sir discussion to contractor about progress and work programeBhagwat Singh BangariSite SupervisorDSC4 R&B WB Rudraprayag See Pic
20.10-10-20173+110Laying of pc work on progressBhagwat Singh BangariSite SupervisorDSC4 R&B WB Rudraprayag See Pic