UDRP/PWD/03/40/RD/028
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
28 |
Package Name: |
UDRP/PWD/03/40/RD/028 |
Sanction Cost: |
238.02 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2517 Nagjagai-Fagu MR (4.000 KM.) (completed) |
|
Procurement: |
Package No.: 28
Package Name: UDRP/PWD/03/40/RD/028
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 20-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/028
Contractor Name: Sanjay Singh Negi
|
Start Date: 27-02-2015
Intended Completion Date: 30-12-2017
Original End Date: 26-05-2016
|
Total Bond Cost: 18180409.46 (181.8 lakhs)
Variation Cost: 4321592.24 (43.22 lakhs) Hence Total Bond Cost is 22502001.7 (225.02 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 1736190 for 191 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 550.00 m | 11.85 | 550.00 m | 550.00 m | 7.18 | 11.85 | 2. | GSB/RBI/G-1 | 3.30 KM | 19.93 | 3.30 KM | 3.30 KM | 12.07 | 19.93 | 3. | G-2 | 3.30 KM | 15.89 | 3.30 KM | 3.30 KM | 9.63 | 15.89 | 4. | G-3 | 3.30 KM | 23.40 | 3.30 KM | 3.30 KM | 14.17 | 23.40 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.30 KM | 30.53 | 3.30 KM | 3.30 KM | 18.49 | 30.53 | 6. | Culverts/Scupper | 8.00 No | 8.86 | 8.00 No | 8.00 No | 5.37 | 8.86 | 7. | longitudinal Drain | 3880.00 m | 7.04 | 3880.00 m | 3880.00 m | 4.26 | 7.04 | 8. | Crash Barrier | 2119.00 m | 38.35 | 2119.00 m | 2119.00 m | 23.23 | 38.35 | 9. | Parapet | 261.00 No | 7.98 | 261.00 No | 261.00 No | 4.83 | 7.98 | 10. | Road Furniture | 20.00 No | 1.26 | 20.00 No | 20.00 No | 0.76 | 1.26 |
Total Amount: |
165.09 |
|
100 |
165.09 |
|
Remarks:
Lab not established
Work Program Made On:
28-09-2015
Updation of work program on:
24-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-March-2015 | 3.68 lakhs |
2. | 31-March-2015 | 9.30 lakhs |
3. | 13-June-2015 | 8.35 lakhs |
4. | 24-June-2015 | 14.98 lakhs |
5. | 31-October-2015 | 2.44 lakhs |
6. | 26-December-2015 | 7.11 lakhs |
7. | 10-March-2016 | 17.39 lakhs |
8. | 02-May-2016 | 16.10 lakhs |
9. | 02-June-2016 | 5.57 lakhs |
10. | 21-September-2016 | 11.87 lakhs |
11. | 26-October-2016 | 4.33 lakhs |
12. | 31-July-2017 | 4.21 lakhs |
13. | 15-October-2017 | 43.12 lakhs |
14. | 18-November-2017 | 24.03 lakhs |
15. | 22-December-2017 | 26.34 lakhs |
16. | 23-March-2018 | 25.16 lakhs |
Total |
223.98 lakhs |
% Payment |
99.54 % |
|
Advance Amount: 44.36 lakhs
Recovered Amount: 44.36 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 55 |
Number of Notice(s) issued: 116 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-07-2018 | Km 5.00 salya-Tulanga motor road | Road opened for traffic | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
2. | 22-07-2018 | Km 5.00 salya tulanga motor road | Road cleaning in progress | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
3. | 22-07-2018 | Km 5.00 salya-tulanga motor marg | Road blocked due to slip | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
4. | 22-07-2018 | Km 3.00 salya- tulanga motor road | Road opened for traffic | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
5. | 22-07-2018 | Km 3.00 salya-tulanga motor road | Road blocked due to landslide | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
6. | 22-07-2018 | Km 3.000 | Road opening is in progress | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
7. | 19-07-2018 | 3.025 | SRMD JCB machine which was dumped in debris is taken out safely today by poclain ... road is open for communication today all vehicles are passed from km 3.00 safely. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
8. | 19-01-2018 | 1.800 | Patch repair over PC . | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
9. | 22-11-2017 | 0+100 | Rolling on pc surface | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
10. | 16-11-2017 | 1+420 | Rolling over pc surface | Deepak Prasad | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
11. | 08-11-2017 | 1+010 | EE sir site visit ,seal coat laying | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
12. | 03-11-2017 | 0+890 | Seal coat rolling under process chainage ... 0+890 Nagjagai Fegu | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
13. | 31-10-2017 | 1+890 | Laying seal coat | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
14. | 27-10-2017 | 3.470 | Protection work by Retaining wall | Nandan Rawat | JE | UDRP R&B Guptkashi | See Pic |
15. | 26-10-2017 | 2.340 | Seal coat after Premix Carpet | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
16. | 24-10-2017 | 2.870 | Premix carpet work on progress rolling over seal coat. | Nandan Rawat | JE | UDRP R&B Guptkashi | See Pic |
17. | 23-10-2017 | 2.920 | Premix carpet work laying in progress Nagjagai fegu Motor Road | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
18. | 22-10-2017 | 2+750 | Nagjaigu fegu m/r Rolling of PC | Nandan Rawat | JE | UDRP R&B Guptkashi | See Pic |
19. | 11-10-2017 | 3+470 | Ee sir discussion to contractor about progress and work programe | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
20. | 10-10-2017 | 3+110 | Laying of pc work on progress | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
|
|