UDRP/PWD/07/16/RD/024
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
24 |
Package Name: |
UDRP/PWD/07/16/RD/024 |
Sanction Cost: |
1038.67 lakhs |
District: |
Pithoragarh |
Block: |
Didihat |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2301 Didihat Dunakot (19.060 KM.) (completed) | 2 2315 Didihat Aadichura (8.500 KM.) (completed) |
|
Procurement: |
Package No.: 24
Package Name: UDRP/PWD/07/16/RD/024
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 03-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/024
Contractor Name: Dwarika Projects Limited
|
Start Date: 11-07-2014
Intended Completion Date: 30-04-2018
Original End Date: 10-10-2015
|
Total Bond Cost: 100030227.5 (1000.3 lakhs)
Variation Cost: 28359199.65 (283.59 lakhs) Hence Total Bond Cost is 128389427.15 (1283.89 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 1250.00 m | 232.87 | 3505.00 m | 3505.00 m | 20.32 | 232.87 | 2. | GSB/RBI/G-1 | 0.87 KM | 7.04 | 0.25 KM | 0.25 KM | 0.71 | 7.04 | 3. | G-2 | 1.05 KM | 5.90 | 0.36 KM | 0.36 KM | 0.6 | 5.90 | 4. | G-3 | 3.28 KM | 19.34 | 2.20 KM | 2.20 KM | 1.71 | 19.34 | 5. | PC/CC i/c Prime Coat, Tack Coat | 22.08 KM | 307.46 | 23.58 KM | 23.58 KM | 28.1 | 307.46 | 6. | Cause Way | 15.00 No | 36.75 | 13.00 No | 13.00 No | 3.51 | 36.75 | 7. | Culverts/Scupper | 67.00 No | 203.51 | 60.00 No | 60.00 No | 17.4 | 203.51 | 8. | longitudinal Drain | 24050.00 m | 77.57 | 18692.00 m | 18692.00 m | 7.53 | 77.57 | 9. | Parapet | 5246.00 No | 206.78 | 4100.00 No | 4100.00 No | 19.08 | 206.78 | 10. | Road Furniture | 419.00 No | 11.19 | 404.00 No | 404.00 No | 1.04 | 11.19 |
Total Amount: |
1108.41 |
|
100 |
1108.41 |
|
Remarks:
No Remarks
Work Program Made On:
29-09-2014
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 103.96 lakhs |
2. | 31-December-2014 | 129.19 lakhs |
3. | 31-March-2015 | 276.04 lakhs |
4. | 06-June-2015 | 131.21 lakhs |
5. | 24-July-2015 | 70.38 lakhs |
6. | 29-September-2015 | 203.05 lakhs |
7. | 30-October-2015 | 55.31 lakhs |
8. | 26-December-2015 | 18.60 lakhs |
9. | 18-March-2016 | 17.24 lakhs |
10. | 30-March-2016 | 25.52 lakhs |
11. | 11-May-2016 | 79.27 lakhs |
12. | 27-July-2016 | 41.52 lakhs |
13. | 31-March-2017 | 38.25 lakhs |
14. | 10-November-2017 | 5.90 lakhs |
15. | 06-June-2018 | 32.91 lakhs |
16. | 21-January-2019 | 15.24 lakhs |
17. | 05-February-2018 | 16.99 lakhs |
18. | 30-March-2019 | 4.46 lakhs |
Total |
1265.04 lakhs |
% Payment |
98.53 % |
|
Advance Amount: 106.76 lakhs
Recovered Amount: 106.76 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 247 |
Number of Notice(s) issued: 86 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-12-2016 | Ch-4+550 | Wire creat in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
2. | 16-12-2016 | Ch-9+900 | Excavation of wire create | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
3. | 15-12-2016 | Ch-2+625 | Wire create in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
4. | 03-12-2016 | 9+300 | Site visit by CE sir pithoragarh | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
5. | 29-11-2016 | Ch-3+050 | Site visit Chief sir SE sir EE Sir AE sir RE Sir JE sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
6. | 03-09-2016 | Ch5+000 | Site visit AE sir RE Sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
7. | 03-09-2016 | Ch 4+990 | Site visit AE sir RE Sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
8. | 01-09-2016 | Ch 5.050 | Slip clearance | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
9. | 02-08-2016 | Ch-9+900 | Site visit RE Sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
10. | 29-07-2016 | Ch-0+720 | Road opening communication by jcb | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
11. | 21-07-2016 | Ch7+950 | Road opening communication by Jcb | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
12. | 21-07-2016 | Ch-5+050 | Slip clearance in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
13. | 15-07-2016 | Ch7+850 | Slip clearance in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
14. | 11-07-2016 | Ch 5.875 | Slip clearance for opening communication | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
15. | 11-07-2016 | Ch 5.425 | Slip clearance | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
16. | 11-07-2016 | Ch 7.900 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
17. | 11-07-2016 | Ch 7.700 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
18. | 11-07-2016 | Ch 7.475 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
19. | 11-07-2016 | Ch 7.475 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
20. | 11-07-2016 | Ch 5.325 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
|
|