Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/16/RD/024 Agreement signed
Project: UDRP-RB Package No.: 24 Package Name: UDRP/PWD/07/16/RD/024 Sanction Cost: 1038.67  lakhs
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 2
Subproject in this package
1  2301   Didihat Dunakot (19.060 KM.) (completed)
2  2315   Didihat Aadichura (8.500 KM.) (completed)
Procurement:
Package No.: 24        Package Name: UDRP/PWD/07/16/RD/024        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 03-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/16/RD/024        Contractor Name: Dwarika Projects Limited       
Start Date: 11-07-2014        Intended Completion Date: 30-04-2018        Original End Date:  10-10-2015
Total Bond Cost: 100030227.5 (1000.3 lakhs)        Variation Cost: 28359199.65 (283.59 lakhs)     Hence Total Bond Cost is   128389427.15 (1283.89 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works1250.00 m232.873505.00 m3505.00 m20.32232.87
2.GSB/RBI/G-10.87 KM7.040.25 KM0.25 KM0.717.04
3.G-21.05 KM5.900.36 KM0.36 KM0.65.90
4.G-33.28 KM19.342.20 KM2.20 KM1.7119.34
5.PC/CC i/c Prime Coat, Tack Coat22.08 KM307.4623.58 KM23.58 KM28.1307.46
6.Cause Way15.00 No36.7513.00 No13.00 No3.5136.75
7.Culverts/Scupper 67.00 No203.5160.00 No60.00 No17.4203.51
8.longitudinal Drain24050.00 m77.5718692.00 m18692.00 m7.5377.57
9.Parapet5246.00 No206.784100.00 No4100.00 No19.08206.78
10.Road Furniture419.00 No11.19404.00 No404.00 No1.0411.19
Total Amount: 1108.41 100   1108.41
Remarks: No Remarks       Work Program Made On: 29-09-2014       Updation of work program on: 22-07-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-2014103.96  lakhs
2.31-December-2014129.19  lakhs
3.31-March-2015276.04  lakhs
4.06-June-2015131.21  lakhs
5.24-July-201570.38  lakhs
6.29-September-2015203.05  lakhs
7.30-October-201555.31  lakhs
8.26-December-201518.60  lakhs
9.18-March-201617.24  lakhs
10.30-March-201625.52  lakhs
11.11-May-201679.27  lakhs
12.27-July-201641.52  lakhs
13.31-March-201738.25  lakhs
14.10-November-20175.90  lakhs
15.06-June-201832.91  lakhs
16.21-January-201915.24  lakhs
17.05-February-201816.99  lakhs
18.30-March-20194.46  lakhs
Total 1265.04  lakhs
% Payment 98.53 %
Advance Amount:  106.76  lakhs        Recovered Amount:  106.76  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 130     No. of Test Done : 148      No. of Test Passed : 130      No. of Test Failed : 18   Test report of this package
Number of Pics Available on Web Repository: 247
Number of Notice(s) issued: 86

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-12-2016Ch-4+550Wire creat in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
2.16-12-2016Ch-9+900Excavation of wire createAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
3.15-12-2016Ch-2+625Wire create in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
4.03-12-20169+300Site visit by CE sir pithoragarhDinesh KumarREDSC4 R&B WB Munsyari See Pic
5.29-11-2016Ch-3+050Site visit Chief sir SE sir EE Sir AE sir RE Sir JE sirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
6.03-09-2016Ch5+000Site visit AE sir RE SirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
7.03-09-2016Ch 4+990Site visit AE sir RE SirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
8.01-09-2016Ch 5.050Slip clearanceLaxman RamJEUDRP R&B Munsyari See Pic
9.02-08-2016Ch-9+900Site visit RE SirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
10.29-07-2016Ch-0+720Road opening communication by jcbAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
11.21-07-2016Ch7+950Road opening communication by JcbAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
12.21-07-2016Ch-5+050Slip clearance in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
13.15-07-2016Ch7+850Slip clearance in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
14.11-07-2016Ch 5.875Slip clearance for opening communicationLaxman RamJEUDRP R&B Munsyari See Pic
15.11-07-2016Ch 5.425Slip clearanceLaxman RamJEUDRP R&B Munsyari See Pic
16.11-07-2016Ch 7.900SlipLaxman RamJEUDRP R&B Munsyari See Pic
17.11-07-2016Ch 7.700SlipLaxman RamJEUDRP R&B Munsyari See Pic
18.11-07-2016Ch 7.475SlipLaxman RamJEUDRP R&B Munsyari See Pic
19.11-07-2016Ch 7.475SlipLaxman RamJEUDRP R&B Munsyari See Pic
20.11-07-2016Ch 5.325SlipLaxman RamJEUDRP R&B Munsyari See Pic