UDRP/PWD/09/03/RD/023
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
23 |
Package Name: |
UDRP/PWD/09/03/RD/023 |
Sanction Cost: |
780.85 lakhs |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1007 Chamkhala-Querala-Dabhra MR (6.000 KM.) (completed) | 2 1028 Pasiya-Pipna MR (15.000 KM.) (completed) |
|
Procurement: |
Package No.: 23
Package Name: UDRP/PWD/09/03/RD/023
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 09-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/03/RD/023
Contractor Name: Trilok Singh Ram Singh Jamnal
|
Start Date: 16-09-2014
Intended Completion Date: 15-04-2016
Original End Date: 15-12-2015
|
Total Bond Cost: 75091114.5 (750.91 lakhs)
Variation Cost: -2124403.62 (-21.24 lakhs) Hence Total Bond Cost is 72966710.88 (729.67 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.00 KM | 28.00 | 2.00 KM | 2.00 KM | 3.94 | 28.00 | 2. | R/Wall, B/ Wall Type Protection works | 2516.00 m | 177.96 | 2516.00 m | 2516.00 m | 24.45 | 177.96 | 3. | GSB/RBI/G-1 | 2.00 KM | 10.95 | 2.00 KM | 2.00 KM | 1.54 | 10.95 | 4. | G-2 | 2.03 KM | 8.48 | 2.03 KM | 2.03 KM | 1.19 | 8.48 | 5. | G-3 | 5.08 KM | 13.05 | 5.08 KM | 5.08 KM | 1.81 | 13.05 | 6. | PC/CC i/c Prime Coat, Tack Coat | 21.00 KM | 249.46 | 21.00 KM | 21.00 KM | 33.98 | 249.46 | 7. | Culverts/Scupper | 35.00 No | 99.37 | 35.00 No | 35.00 No | 13.64 | 99.37 | 8. | longitudinal Drain | 21000.00 m | 27.83 | 17900.00 m | 17900.00 m | 3.8 | 27.83 | 9. | Crash Barrier | 4470.00 m | 15.49 | 4470.00 m | 4470.00 m | 2.15 | 15.49 | 10. | Parapet | 347.00 No | 43.41 | 908.00 No | 908.00 No | 5.89 | 43.41 | 11. | Road Furniture | 2608.00 No | 10.37 | 4130.00 No | 4130.00 No | 1.41 | 10.37 | 12. | Other Allied Works & Finishing Work | 2.00 Job | 30.17 | 2.00 Job | 2.00 Job | 4.16 | 30.17 | 13. | Cause Way | 4.00 No | 15.13 | 4.00 No | 4.00 No | 2.03 | 15.13 |
Total Amount: |
729.67 |
|
100 |
729.67 |
|
Remarks:
No Remarks
Work Program Made On:
04-10-2014
Updation of work program on:
13-09-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-October-2014 | 54.57 lakhs |
2. | 03-December-2014 | 61.86 lakhs |
3. | 02-February-2015 | 82.90 lakhs |
4. | 31-March-2015 | 100.50 lakhs |
5. | 12-June-2015 | 278.95 lakhs |
6. | 04-May-2016 | 108.70 lakhs |
7. | 30-July-2016 | 42.18 lakhs |
Total |
729.66 lakhs |
% Payment |
100 % |
|
Advance Amount: 241.28 lakhs
Recovered Amount: 241.28 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 157 |
Number of Notice(s) issued: 63 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-04-2016 | 1+100 | Road visit | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
2. | 05-04-2016 | Ch 0.300 | Site visit Mr Deepak Malik Sir and T.L Sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
3. | 15-03-2016 | Ch 8.250 | Letter writting on culvert | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
4. | 15-03-2016 | Ch 6.325 | Patch Repair work | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
5. | 12-03-2016 | Ch 13.350 | Crash Barrier Work | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
6. | 10-03-2016 | Ch.7.900 | Patch repairing (due to slip zone ) | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
7. | 10-03-2016 | Ch.6.750 | Patch repairing | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
8. | 10-03-2016 | Ch. 13.150 | Patch repairing | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
9. | 07-02-2016 | Km 8 | Excavation for vertical post of crash barrier. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
10. | 05-02-2016 | Ch 4.300 | Inspection by chief engineer sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
11. | 05-02-2016 | Ch 14.650 | Inspection by C.E Sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
12. | 09-01-2016 | Ch 33.750 | Damage dry supper. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
13. | 09-01-2016 | Ch.14.2000 | Protection work. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
14. | 09-01-2016 | Ch.10.750 | Fixing of edge stone and const of b wall. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
15. | 09-01-2016 | Ch.10.050 | Const of b.wall | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
16. | 09-01-2016 | | Fixing of edge stone | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
17. | 09-01-2016 | Ch.2.140 | Const of parapet and kc drain | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
18. | 08-01-2016 | Ch 8.250 | Construction of parapets | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
19. | 08-01-2016 | Ch 8.175 | Fixing of edge stone | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
20. | 08-01-2016 | Ch 3.110 | Construction of R / Wall | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
|
|