Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

14/BC/PIU/USIDCL/PB/2015-16 Agreement signed
Project: UDRP-H Package No.: 2264 Package Name: 14/BC/PIU/USIDCL/PB/2015-16 Sanction Cost: 856.00  lakhs
District: Chamoli Block: Joshimath Constituency: Badrinath Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7301   State Allopathic Dispensary Pandukeshwar (0.000 KM.) (completed)
Procurement:
Package No.: 2264        Package Name: 14/BC/PIU/USIDCL/PB/2015-16        Tender Date: 08-04-2016        Current Status: Agreement signed        Achieved on Date: 22-09-2016

Construction Phase

Agreement Details
Bond/Agreement Name: 14/BC/PIU/USIDCL/PB/2015-16        Contractor Name: Ayush Construction Pvt. Ltd.       
Start Date: 21-09-2016        Intended Completion Date: 30-06-2018        Original End Date:  20-12-2017
Total Bond Cost: 52358978 (523.59 lakhs)        Variation Cost: -306161.01 (-3.06 lakhs)     Hence Total Bond Cost is   52052816.99 (520.53 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9921841 for 379 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development20.19 Job105.0920.19 Job20.19 Job20.19105.09
2.Foundation and Plinth Work16.92 Job88.0716.92 Job16.92 Job16.9288.07
3.Structural Frame27.83 Job144.8627.83 Job27.83 Job27.83144.86
4.Doors & Windows 7.17 Job37.327.17 Job7.17 Job7.1737.32
5.Water Supply and Sanitary work 1.98 Job10.311.98 Job1.98 Job1.9810.31
6.Electrification Works6.66 Job34.676.66 Job6.66 Job6.6634.67
7.Other Allied Works & Finishing Work 19.25 Job100.2019.25 Job19.25 Job19.25100.20
Total Amount: 520.52 100   520.52
Remarks: Task finished       Work Program Made On: 07-11-2016       Updation of work program on: 11-07-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-January-201733.32  lakhs
2.25-March-201722.53  lakhs
3.31-March-201734.55  lakhs
4.25-May-201731.18  lakhs
5.21-June-201729.61  lakhs
6.30-June-201719.50  lakhs
7.18-October-201799.66  lakhs
8.16-February-201834.76  lakhs
9.04-August-2018133.63  lakhs
10.03-December-201881.49  lakhs
Total 520.23  lakhs
% Payment 99.94 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 696     No. of Test Done : 696      No. of Test Passed : 696      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 2
Number of Notice(s) issued: 33

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-02-2017PandukeshwarSocial environment training at site safety precautions, helmet ,shoes,jacket,etc.Naresh Kumar 2REUDRP-H Pithoragarh See Pic
2.19-02-2017PandukeshwarSite development workNaresh Kumar 2REUDRP-H Pithoragarh See Pic